Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 22720: 2002-053-00 ASOTIN SALMONID M&E 2005 CONTRACT
Project Number:
Title:
Asotin Creek Salmon Population Assessment
Stage:
Implementation
Area:
Province Subbasin %
Blue Mountain Asotin 100.00%
Contract Number:
22720
Contract Title:
2002-053-00 ASOTIN SALMONID M&E 2005 CONTRACT
Contract Continuation:
Previous: Next:
18229: 2002-053-00 ASSESS SALMONIDS IN ASOTIN CREEK WATERSHED
  • 25282: 2002-053-00 ASSESS SALMONIDS IN ASOTIN CREEK WATERSHED
Contract Status:
History
Contract Description:
Draft April 2005
Assess Salmonids in Asoti Creek Watershed
Statement of Work and Budget FY2005

BPA Project Number:  2002-053-00
BPA Project Title: Assess Salmonids in the Asotin Creek Watershed
Contract Number:  (Replacing BPA #00018229)
Contract Title:  Assess Salmonids in the Asotin Creek Watershed
Performance/Budget Period: June 1, 2005 to December 31, 2005

Technical Contact:  Mark Schuck
Title:  Project Leader
Washington Department of Fish and Wildlife
1049 Port Way
Clarkston, WA  99403
Contact Phone / Fax:  509-751-0823 / 509-751-8631
schucmls@dfw.wa.gov

Contracting Contact:  Ted Nelson
Title:  Deputy Contracts Officer
Washington Department of Fish and Wildlife
600 Capitol Way N.
Olympia, WA  98501-1091
Phone / Fax:  360-902-2401 / 360-902-2941
nelsotfn@dfw.wa.gov

Financial Contact:  Karen Southwell
Title:  Accounts Recievable - Federal Contracts
Washington Department of Fish and Wildlife
600 Capitol Way N
Olympia, WA  98501-1091
Phone / Fax:  360-664-4993 / 360-664-3160
southkjs@dfw.wa.gov

Assess Salmonids in the Asotin Creek Watershed, BPA Project # 2002-053-00.
Project Goal:  Assess the status of anadromous salmonid populations in the Asotin Creek watershed.  Estimate the abundance, productivity, survival rates, and temporal and spatial distribution of steelhead/rainbow trout (Oncorhynchus mykiss) and Chinook salmon (O. tshawytscha).
Executive Summary:  The fundamental aspects of the project are adult enumeration and smolt emigration estimation, including statistical estimates of bounds for estimates.  Data from the Asotin Creek assessment project will document population status and change over time as required under RPA 180.
Objective 1:  Document juvenile steelhead life history patterns, survival rate and smolt production in the Asotin Creek watershed above George Creek.
Objective 2:  Estimate escapement of hatchery and wild steelhead and salmon into the Asotin Creek watershed above George Creek; and measure adult trap fallback and adult trap efficiency.
Objective 3: Estimate spawner abundance and adults per redd.
Objective 4: Genetics sampling.
Objective 5:  Deliverables.  Annual report: Abstract, introduction, description, methods, results, discussion, summary, and expenditures.
Location of Project:  Asotin Creek and its tributaries above George Creek, starting at river kilometer 4.9, in Asotin County, Washington.
Account Type(s):
Expense
Contract Start Date:
06/01/2005
Contract End Date:
12/31/2005
Current Contract Value:
$97,178
Expenditures:
$97,178

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Deliverable complete A: 119. Administrative Duties 10/17/2005
Deliverable complete B: 141. Status Reports 07/15/2005 10/17/2005
Deliverable complete C: 165. Submit 4(d) Research Application 12/30/2005
Deliverable complete D: 157. Data Collection 10/17/2005
Deliverable complete E: 158. Fish Tagging Activities 10/17/2005
Deliverable complete F: 162. Data Analysis 12/30/2005
Deliverable complete G: 132. Annual Report

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Administrative Duties
B 141 Status Reports
C 165 Submit 4(d) Research Application
D 157 Data Collection
E 158 Fish Tagging Activities
F 162 Data Analysis
G 132 Annual Report
H 185