Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 25348: 1998-007-03 GRANDE RONDE SATELLITE FACILITIES O&M
Project Number:
Title:
Grande Ronde Supplementation O&M on Catherine Creek/Upper Grande Ronde River
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Blue Mountain Grande Ronde 100.00%
Contract Number:
25348
Contract Title:
1998-007-03 GRANDE RONDE SATELLITE FACILITIES O&M
Contract Continuation:
Previous: Next:
6509: 1998-007-03 GRANDE RONDE SUPPLEMENTATION M&E O&M
  • 30615: 1998-007-03 GRANDE RONDE SATELLITE FACILITIES O&M
Contract Status:
History
Contract Description:
I. Project Goal

To preserve the genetic variability and enhance the population size of the depressed spring chinook salmon populations in Catherine Creek and the Upper Grande Ronde River using a hatchery program based on the indigenous stock.

II. Background

The ceded lands and usual and accustomed fishing sites in northeast Oregon of the Confederated Tribes of the Umatilla Indian Reservation (CTUIR) include areas where fish and wildlife populations have been negatively affected by the construction and operation of mainstem Columbia and Snake River dams. CTUIR is seeking restoration of these populations.  

The CTUIR, Nez Perce Tribe (NPT), and Oregon Department of Fish and Wildlife (ODFW) are cooperating in a Grande Ronde Endemic Spring Chinook Salmon Supplementation Program (GRESCSP) to increase natural production and eventually allow harvest of spring chinook salmon in the Grande Ronde River basin. This integrated salmon program uses captive and conventional broodstock artificial propagation components in order to prevent extinction, supplement natural production and restore productive fisheries in currently underutilized habitat in the Grande Ronde River basin. A comprehensive plan developed by comanagers to more functionally combine and integrate the captive brood and conventional components of the program was completed in 1998. All aspects of the GRESCSP are fully integrated with the Lower Snake River Compensation Plan (LSRCP).  Project activities are incorporated into the LSRCP/BPA Annual Operations Plan.

The GRESCSP is an extension of the LSRCP which has temporarily changed the emphasis of its spring chinook programs from mitigation to conservation.  Grande Ronde Basin tributaries currently being targeted for spring chinook supplementation under LSRCP include the upper Grande Ronde River, Catherine Creek and the Lostine River.  The primary focus of this project is the programs directed at Catherine Creek and the upper Grande Ronde River which lie within the ceded lands boundary of CTUIR.

The captive broodstock component of the program was initiated by NPT and ODFW in 1995 under initial funding from LSRCP.  CTUIR became involved in the program in late 1996.  Naturally-produced juvenile salmon are captured from three tributaries of the Grande Ronde River (Catherine Creek, upper Grande Ronde, and Lostine rivers) and then reared to maturity and spawned in captivity. Spawning of mature captive brood fish began in 1998.  Final rearing of these captive broodstock progeny occurs at Lookingglass Hatchery.  Smolts are then transferred back to their stream of origin for acclimation and release.

The conventional broodstock component of the program began in 1997 on the same three Grande Ronde tributaries.  Naturally-produced adult spring chinook salmon are captured at weirs on these tributaries and taken to Lookingglass Hatchery for spawning. CTUIR operates the adult collection weirs in the upper Grande Ronde River and Catherine Creek for population monitoring and collection of conventional broodstock. Due to low numbers of returning adults, no conventional broodstock were spawned from either Catherine Creek or the upper Grande Ronde River until 2001.  As with the captive brood portion of the program, final rearing of the conventional progeny is expected to occur at Lookingglass Hatchery.  Smolts will then be transferred back to their stream of origin for acclimation and release.

CTUIR operates juvenile acclimation facilities for spring chinook salmon in the upper Grande Ronde River and Catherine Creek. The first juveniles produced from the program were1998 brood captive brood progeny which were acclimated and released in 2000(37,980 smolts CC and 1,508 smolts GR).  In 2001 we released 136,674 smolts from the Catherine Creek facility and 2,608 smolts from the Upper Grande Ronde facility.  In 2002 we released 180,343 smolts from the Catherine Creek facility and 151,444 smolts from the Upper Grande Ronde facility.  In 2003 we released 129,756 smolts from the Catherine Creek facility and 237,800 smolts from the Upper Grande Ronde facility.  In 2004 we released 163,372 smolts from the Catherine Creek facility and 148,804 smolts from the Upper Grande Ronde facility.   In 2005 we released 189,580 smolts from the Catherine Creek facility and 105,418 smolts from the Upper Grande Ronde facility.

III. Current

Approximately 70,000 smolts are expected to be acclimated and released from the Catherine Creek facility and 17,000 smolts from the Upper Grande Ronde facility in 2006.  Adult facilities will be in place to capture as many returning adults as possible and transport a portion to Lookingglass Hatchery for broodstock (up to broodstock needs).  Maintenance will be conducted on both facilities when needed.  Assistance during spawning activities (spawning ground surveys, spawn at Lookingglass and Bonneville) will be provided to ODFW.  Project administration and coordination will occur throughout the year.

IV. Location of Project

The project is located in the Blue Mountains of eastern Oregon.  The Catherine Creek Acclimation Facility is at river mile 29 (rkm 47.5) of Catherine Creek (HUC 17060104).  The Catherine Creek Adult Collection Facility is at river mile 20 (rkm 33.0) of Catherine Creek (HUC 17060104).
The Grande Ronde Acclimation Facility is at river mile 199 (rkm 319.4) of the Grande Ronde River (HUC 17060104).  The Grande Ronde Adult Collection Facility is at river mile 191 (rkm 307.4) of the Grande Ronde River

V. BPA-Furnished Property

BPA will provide all required water right permits from Oregon Water Resources (water rights) and instream work permits from the Division of State Lands for all facilities.
1. Catherine Creek acclimation water right and intake maintenance
2. Catherine Creek adult weir maintenance.
3. Upper Grande Ronde acclimation water right and intake maintenance.
4. Upper Grande Ronde adult weir maintenance.

In 2002 the project was divided into 2 separate contracts, Operations and Maintenance and Monitoring and Evaluation.
Account Type(s):
Expense
Contract Start Date:
01/01/2006
Contract End Date:
12/31/2006
Current Contract Value:
$458,134
Expenditures:
$458,134

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Documentation and assistance to support BPA's Environmental Compliance Group. A: 165. Obtain Permits and submit copies to BPA NEPA group 12/31/2006 12/31/2006
Pertinent Results of Coordination Meetings B: 118. Coordination of Project Activities 12/31/2006 02/28/2006
Acclimation of fish at Upper Grande Ronde River. C: 56. Upper Grande Ronde River Acclimation 04/17/2006 04/12/2006
Acclimation of fish at Catherine Creek D: 56. Catherine Creek Acclimation 04/17/2006 04/12/2006
Operate adult collection facility at Upper Grande Ronde E: 66. Upper Grande Ronde Adult Collection 08/15/2006 07/25/2006
Operate adult collection facility at Catherine Creek F: 66. Catherine Creek Adult Collection 08/15/2006 07/27/2006
Assist with spawning at Lookingglass Fish Hatchery G: 64. Assist with spawning of broodstock 09/30/2006 09/30/2006
Environmental conditions, fish numbers, fish condition, PIT tag information, fish spawned H: 157. Collection of data at facilities 09/30/2006 09/30/2006
Send weekly reports to co-managers during periods of acclimation and adult facility operation I: 161. Weekly Reports 09/30/2006 02/28/2006
Data Analysis of Current Data Collection For Managment Decisions J: 162. Data Analysis For Management 12/31/2006 12/31/2006
Maintain Upper Grande Ronde Facilities K: 61. Upper Grande Ronde Facility Maintenance 12/31/2006 12/31/2006
Maintain Catherine Creek Facilities L: 61. Catherine Creek Facility Maintenance 12/31/2006 12/31/2006
Maintain La Grande Office/Shop M: 61. La Grande Office/Shop Maintenance 12/31/2006 12/31/2006
FY07 SOW, June/September 06 Accrual Estimates, FY06 Metrics Reports N: 119. Annual Budget Package/Accrual Reports/Provincial Review 10/02/2006 08/31/2006
Produce annual report O: 132. Annual Report 12/31/2006 12/31/2006
Produce quarterly reports P: 141. Quarterly Report (Word/Excel) 12/31/2006 11/30/2006

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 2 instances of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 1 instance of WE 64 Spawn Fish
  • 2 instances of WE 56 Acclimate Juvenile Fish
  • 3 instances of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results
  • 1 instance of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain Permits and submit copies to BPA NEPA group
B 118 Coordination of Project Activities
C 56 Upper Grande Ronde River Acclimation
D 56 Catherine Creek Acclimation
E 66 Upper Grande Ronde Adult Collection
F 66 Catherine Creek Adult Collection
G 64 Assist with spawning of broodstock
H 157 Collection of data at facilities
I 161 Weekly Reports
J 162 Data Analysis For Management
K 61 Upper Grande Ronde Facility Maintenance
L 61 Catherine Creek Facility Maintenance
M 61 La Grande Office/Shop Maintenance
N 119 Annual Budget Package/Accrual Reports/Provincial Review
O 132 Annual Report
P 141 Quarterly Report (Word/Excel)
Q 185 Quarterly Pisces Report