Contract 34928: 2006-005-00 EXP ASOTIN CREEK WILDLIFE AREA O&M

Last Modified: Bob Dice, 08/16/2007 8:15 AM   
Basics

Project Number:
Title:
Asotin Creek Wildlife Mitigation
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Blue Mountain Asotin 100.00%
Contract Number:
34928
Contract Title:
2006-005-00 EXP ASOTIN CREEK WILDLIFE AREA O&M
Contract Continuation:
Previous: Next:
29534: 2006-005-00 EXP ASOTIN CREEK WILDLIFE AREA O&M
  • 39682: 200600500 EXP ASOTIN CREEK WILDLIFE AREA O&M
Contract Status:
Closed
Contract Description:
The Asotin Creek Wildlife Area is divided into two units that are located in Asotin and Garfield Counties.  The lower unit is centered around George Creek and is approximately 12,000 acres in size.  The lower Schlee and Bickford units which are BPA funded comprise 5,600 acres of the lower portion of the wildlife area.  The upper unit is centered around the North and South Forks of Asotin Creek and is approximately 20,000 acres is size.  The upper Schlee purchase is approximately 9,000 acres is size and is centered in the Smoothing Iron Ridge Area.

The lower BPA funded units are comprised of steep canyons and is predominately a shrub/steppe habitat type.  The area was traditionally used for livestock production and dryland farming.  The land has several problems associated with that type of long-term management - mainly noxious weeds and degraded riparian management zones.  Noxious weeds are mainly controlled by chemical measures and application is difficult in the steep terrain.

The upper BPA funded unit is again comprised of steep canyons with farm fields on top of the ridges.  Steep canyons with timbered North facing slopes are common while South facing slopes are usually a shrub/steppe habitat type.  Noxious weed problems, boundary fence issues, and facility maintenance are the main issues associated with the upper unit.

Overall management objectives are to reduce noxious weed populations on the upper and lower units and rehabilitate riparian zones.  WDFW also  would like to maintain existing facilities such as the main buildings on Smoothing Iron Ridge and associated water systems for fire protection and a source of water for weed control efforts.  Boundary fences are also in need of maintenance to reduce problems from trespass livestock.    

Public access and information will be addressed in the form of developing educational kiosks for each unit and improvement of parking areas mainly by application of gravel to form an all-weather surface.

The staff on the Asotin Creek Wildlife Area consists of a Wildlife Area Manager, as Fish and Wildlife Biologist 2, two Habitat Tech 1's and three 3-month laborers hired in the spring to conduct weed control activities.  The manager, bio-2, and habitat tech 1 positions are only partially funded under BPA since the BPA lands are merged with State funded lands associated with the Asotin Creek Wildlife Area.
Account Type(s):
Expense
Contract Start Date:
10/01/2007
Contract End Date:
09/30/2008
Current Contract Value:
$103,295
Expenditures:
$103,295

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental Compliance A: 165. Environmental Compliance 03/28/2008 03/28/2008
Noxious Weed Control on a minimum of 150 acres in the George and Bickford Units B: 22. Control Noxious Weeds in George, and Bickford Units 09/30/2008 09/30/2008
Control Noxious weeds on an minimum of 150 acres on Smoothing Iron Unit. C: 22. Control Noxious Weeds in Smoothing Iron Unit 09/30/2008 09/30/2008
20 miles of stock fence D: 186. Maintain Boundary Stock Fences on Smoothing Iron Unit 09/30/2008 07/30/2008
20 miles of stock fence E: 186. Maintain Boundary Stock Fences on George Creek Unit 09/30/2008 09/30/2008
20 miles of stock fence F: 186. Maintain Boundary Stock Fences on Bickford Unit 09/30/2008 09/30/2008
Agricultural Field Restoration G: 47. Agricultural Field Restoration 09/29/2008
Building Maintenance H: 186. Maintain Smoothing Iron Buildings. 09/30/2008 09/30/2008
Building Maintenance I: 186. Maintain Hay Shed on Bickford Unit. 09/30/2008 09/30/2008
Develop alternative water source for wildlife J: 34. Develop alternative water source for wildlife 09/30/2008 06/30/2008
Finish Management Plan K: 174. Complete Wildlife Area Mitigation Plan 09/30/2008
Citizens Advisory Group (CAG) L: 99. Conduct Citizen's advisory group meetings 09/30/2008
Manage and administer Asotin Creek BPA project. M: 119. Administer Asotin Creek Project 09/30/2008 09/30/2008
Annual Report FY07 Contract Period N: 132. Submit Progress Report for the period Oct 2007 to Sep 2008 09/30/2008

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Wildlife
  • 2 instances of WE 22 Maintain Vegetation
  • 5 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 34 Develop Alternative Water Source
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance 02/09/2007
B 22 Control Noxious Weeds in George, and Bickford Units 09/10/2007
C 22 Control Noxious Weeds in Smoothing Iron Unit 09/10/2007
D 186 Maintain Boundary Stock Fences on Smoothing Iron Unit 08/24/2007
E 186 Maintain Boundary Stock Fences on George Creek Unit 08/24/2007
F 186 Maintain Boundary Stock Fences on Bickford Unit 08/24/2007
G 47 Agricultural Field Restoration 08/24/2007
H 186 Maintain Smoothing Iron Buildings. 08/24/2007
I 186 Maintain Hay Shed on Bickford Unit. 08/24/2007
J 34 Develop alternative water source for wildlife 04/03/2008
K 174 Complete Wildlife Area Mitigation Plan 02/09/2007
L 99 Conduct Citizen's advisory group meetings 02/09/2007
M 119 Administer Asotin Creek Project 02/09/2007
N 132 Submit Progress Report for the period Oct 2007 to Sep 2008 02/09/2007
O 185 Periodic Status Reports for BPA 02/09/2007