Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 35408: 200739800 CAP MANASTASH FLOW ENHANCEMENT
Project Number:
Title:
Yakima Basinwide Tributary Passage and Flow
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Yakima 100.00%
Contract Number:
35408
Contract Title:
200739800 CAP MANASTASH FLOW ENHANCEMENT
Contract Continuation:
Previous: Next:
n/a
  • 45233: 2007-398-00 CAP MANASTASH FLOW ENHANCEMENT
Contract Status:
Closed
Contract Description:
This contract covers the capital portion of the Manastash Creek Instream Flow Enhancement Project, which is part of the larger Manastash Creek Restoration Project.  The expense portion is covered by CR-87290.
In Manastash Creek, several man-made structures (dams and unscreened diversions) reduce or eliminate fish passage, create the potential for fish entrainment into ditches, and contribute to diminished flow creating a low-flow or no-flow fish passage barrier. These diversions date to the 1870’s and have been actively diverting water for irrigation and stock water since then. Water rights in this watershed have been adjudicated and the Court’s conditional final order is in place.
The overall Manastash Creek Restoration Project includes providing fish screens to protect fish from entrainment in irrigation systems, removing barriers to fish passage and improving instream flow.  Funding is in place through BPA and the Washington Department of Ecology to complete the screening and passage portion of the project.
The Manastash Creek Instream Flow Enhancement Project's purpose is to accomplish the final goal, improving instream flow in lower Manastash Creek, by identifying and implementing projects. This project is guided by the Manastash Creek Restoration Project Instream Flow Enhancement Plan
completed by the Manastash Steering Committee.   The KCCD will work with all water right owners to identify water conservation projects in water delivery systems and water application systems (on-farm), potential options to convert to groundwater, and to match water right owners with groups who purchase or lease water rights. This contract not only identifies projects and implements projects, it will also serve to identify and secure additional funding sources to complete projects.  The Manastash Steering Committee will play a key role in prioritizing projects for implementation.
Account Type(s):
Capital
Contract Start Date:
09/30/2007
Contract End Date:
01/31/2010
Current Contract Value:
$578,500
Expenditures:
$578,500

* Expenditures data includes accruals and are based on data through 30-Apr-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration No Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Anna Lael Kittitas County Conservation District Yes Supervisor anna.lael@kccd.net (509) 925-3352x7
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Jay Marcotte Bonneville Power Administration Yes COR jgmarcotte@bpa.gov (503) 230-3943
Sherry Swanson Kittitas County Conservation District Yes Contract Manager sherry-swanson@conservewa.net (509) 925-3352x6
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Documentation and assistance to support BPA's Environmental Compliance Group A: 165. Environmental Compliance Documentation 09/29/2009 09/29/2009
Project Design and Engineering B: 175. Engineering and Designs 09/30/2009 09/30/2009
Cooke/Rock/Forbes Pipeline System C: 149. Cooke/Rock/ Forbes Pipeline 09/30/2009 09/30/2009
Cancelled D: 150. Forbes Sprinkler System 09/18/2009
Cancelled E: 149. Forbes Pipeline 09/18/2009
Cancelled F: 149. Graf et al Pipeline 09/18/2009
Water Transaction Checklists for Proposed Projects G: 154. Develop Water Rights Transactions and Negotiate donations of water rights 09/30/2009 09/30/2009
0.152 cfs before pro-rationing trusted and protected instream H: 164. Acquire Water Instream at Anderson Diversion via donations 09/30/2009 09/30/2009
Cancelled I: 164. Acquire Water Instream at Anderson Diversion via donations 09/18/2009
Cancelled J: 164. Acquire Water Instream at Jensen Diversion via donations 09/18/2009
Funding Package - Submit draft to COTR K: 119. Manage Projects 07/31/2009 07/31/2009
Attach Progress Report in Pisces L: 132. Submit Draft Progress Report for the period Nov 2007 through Oct 2008 10/31/2009 09/29/2009
Gregerich Sprinkler Conversion N: 150. Gregerich Sprinkler Conversion 01/31/2010 09/30/2009
Cancelled O: 150. Larry Bland Sprinkler Conversions 09/18/2009
Estimated 2 to 3 cfs before pro-rationing saved and protected instream P: 164. Acquire Water Instream at Menastash Diversion via donations 09/30/2009 09/30/2009
MWDA Ditch Flow Measuring Devices Q: 148. MWDA Ditch Flow Measuring Devices 10/30/2009 09/30/2009

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 148 Install Flow Measuring Device
  • 3 instances of WE 149 Install Pipeline
  • 3 instances of WE 150 Install Sprinkler
  • 4 instances of WE 164 Acquire Water Instream

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance Documentation 02/09/2007
B 175 Engineering and Designs 02/09/2007
C 149 Cooke/Rock/ Forbes Pipeline 09/05/2007
D 150 Forbes Sprinkler System 09/05/2007
E 149 Forbes Pipeline 09/05/2007
F 149 Graf et al Pipeline 09/05/2007
G 154 Develop Water Rights Transactions and Negotiate donations of water rights 02/09/2007
H 164 Acquire Water Instream at Anderson Diversion via donations 09/05/2007
I 164 Acquire Water Instream at Anderson Diversion via donations 09/05/2007
J 164 Acquire Water Instream at Jensen Diversion via donations 09/05/2007
K 119 Manage Projects 02/09/2007
L 132 Submit Draft Progress Report for the period Nov 2007 through Oct 2008 02/09/2007
M 185 Periodic Status Reports for BPA 02/09/2007
N 150 Gregerich Sprinkler Conversion 11/03/2008
O 150 Larry Bland Sprinkler Conversions 02/09/2007
P 164 Acquire Water Instream at Menastash Diversion via donations 09/23/2008
Q 148 MWDA Ditch Flow Measuring Devices 03/16/2009