Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 36916: 1996-077-05 EXP USFS MEADOW CREEK WATERSHED RESTORATION
Project Number:
Title:
Meadow Creek Watershed Restoration
BPA PM:
Stage:
Closed
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
36916
Contract Title:
1996-077-05 EXP USFS MEADOW CREEK WATERSHED RESTORATION
Contract Continuation:
Previous: Next:
32691: 1996 077 05 EXP USFS MEADOW CREEK WATERSHED RESTORATION
Contract Status:
Closed
Contract Description:
Contract History:
The Restore McComas Meadows/Meadow Creek Watershed (1996-077-05) has been an ongoing project of the Nez Perce Tribe Fisheries Watershed Program since 1996.  This project is being completed in cooperation with the Nez Perce Tribe (NPT).  The ultimate goal of the project is to restore the physical and biological characteristics of the watershed to provide quality habitat for anadromous and resident fish species that support the historical, cultural and economic practices of the Nez Perce Tribe.  The Meadow Creek watershed contains proposed critical habitat for listed species steelhead trout, potential critical habitat for bull trout, and has moderate habitat potential for spring Chinook salmon.  Restoration in this watershed focuses on restoring riparian processes by addressing increased water temperatures, increased sedimentation, cattle grazing affects, fish passage issues, and noxious weed infestations.  Previously completed contract work includes 4 culvert replacements, 37 miles of road decommissioning, installation of riparian vegetation cages, over 33,500 native riparian trees planted, installation and maintenance of 5 miles of fence, re-contouring of the McComas Meadow ditch, and continued monitoring and evaluation and revegetation surveys.

Summary of FY 2008 - 2009 Contract:
This project is part of the Nez Perce National Forest-Nez Perce Tribe Watershed Restoration Partnership with in kind contributions from the Nez Perce National Forest.  Funding for the Meadow Creek project was approved for the Nez Perce Tribe in the amount of $908,156.  $392,634 of that amount is being awarded to the Nez Perce National Forest under this contract of the project for the Meadow Creek Phase II and Whitman Creek road decommissioning.
  
A) Road decommissioning-
Road densities in the Meadow Creek watershed are 4.6 miles per square mile, the highest road density in the South Fork Clearwater subbasin (USDA Forest Service 1998).  In FY 08 up to 20 miles of roads within Meadow Creek will be decommissioned, and in FY 09 up to 20 miles of roads within Whitman Creek and 16 miles in False Creek will be decommissioned.  Road decommissioning includes re-contouring roads back to natural topography, removing all culverts, re-sloping water crossings to natural gradient, the installation of water bars, and de-compacting landing areas and skid trails which will reduce surface erosion and sediment delivery to streams.  The Nez Perce Tribe, under a separate BPA-NPT contract of this project will assist the Nez Perce National Forest with bid package development, bid review, contractor selection, technical oversight during construction, final inspection, and the associated project implementation/effectiveness monitoring and evaluation.
Account Type(s):
Expense
Contract Start Date:
03/01/2008
Contract End Date:
10/31/2010
Current Contract Value:
$335,282
Expenditures:
$335,282

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration No Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Stephanie Bransford Nez Perce Tribe No Technical Contact stephanieb@nezperce.org (208) 983-0675
Lois Geary US Forest Service (USFS) No Administrative Contact lgeary@fs.fed.us (208) 983-7008
Mark Johnson Nez Perce Tribe Yes Technical Contact markj@nezperce.org (208) 621-3561
David Kaplowe Bonneville Power Administration Yes COR djkaplowe@bpa.gov (503) 230-5365
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Heidi McRoberts Nez Perce Tribe Yes Technical Contact heidim@nezperce.org (208) 621-3548
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
Michelle Roberts US Forest Service (USFS) Yes Contract Manager mmroberts@fs.fed.us (208) 983-4091
Scott Russell US Forest Service (USFS) Yes Supervisor sarussell@fs.fed.us (208) 983-4092


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental compliance documentation submitted to BPA A: 165. Provide Environmental Compliance Documentation to BPA 05/31/2008 05/31/2008
Road decommissioning complete B: 33. Meadow Creek Phase II Road Decommissioning 11/30/2008 11/15/2008
Road decommissioning complete C: 33. Whitman Creek Road Decommissioning 10/31/2010 09/30/2010
FY 2010 SOW package and FY 08 and FY 09 accrual estimates E: 119. Management, Coordination and Communication 12/18/2009 12/18/2009
Road decommissioning complete G: 33. False Creek Phase I Road Decommissioning 11/30/2009 09/30/2009
Designs and cost estimates for culvert replacement H: 175. Design for Farris Creek Culvert Replacement 05/31/2010 05/31/2010
Culvert replacement complete I: 184. Replace Rock Creek Culvert 10/31/2009 09/30/2009

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 3 instances of WE 33 Decommission Road/Relocate Road
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 3 instances of WE 33 Decommission Road/Relocate Road
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Provide Environmental Compliance Documentation to BPA 02/09/2007
B 33 Meadow Creek Phase II Road Decommissioning 02/09/2007
C 33 Whitman Creek Road Decommissioning 02/09/2007
D 132 Progress (Annual) Report Not Required 02/09/2007
E 119 Management, Coordination and Communication 02/09/2007
F 185 Periodic Status Reports for BPA 02/09/2007
G 33 False Creek Phase I Road Decommissioning 02/09/2007
H 175 Design for Farris Creek Culvert Replacement 02/09/2007
I 184 Replace Rock Creek Culvert 02/09/2007