Contract 36930: 1984-021-00 EXP JOHN DAY HABITAT ENHANCEMENT
Project Number:
Title:
John Day Habitat Enhancement
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau John Day 100.00%
Contract Number:
36930
Contract Title:
1984-021-00 EXP JOHN DAY HABITAT ENHANCEMENT
Contract Continuation:
Previous: Next:
33040: 1984-021-00 EXP JOHN DAY HABITAT ENHANCEMENT
  • 41751: 198402100 EXP JOHN DAY HABITAT ENHANCEMENT
Contract Status:
Closed
Contract Description:
This project was initiated on July 1, 1984 under the BPA contract and allows for initial landowner contacts, agreement development, project design, budgeting, and implementation for anadromous fish habitat improvement on privately owned lands within the John Day Basin.  

The purpose of the John Day Fish Habitat Enhancement Program is to enhance production of indigenous wild stocks of spring chinook and summer steelhead within the sub basin through habitat protection, enhancement and fish passage improvements.

In work period 3-1-2008 thru 2-29-2009 the fish habitat program will accomplish approximately 15.0 miles of riparian fence, coordination with 8 landowners (Kenny Holliday, Doug Leach, Alan Jacobs, Bob Collins, Joe Latoesky,  Jim Mabe, Mac Campbell and Ben Norton).  There will be constructed 3.00 miles on Laycock and Fall Creek/ Holliday property tributary to the John Day River, 2.00 miles on Eightmile Creek /Leach property tributary to the North fork of the John Day River, 2.00 miles on Alan Jacobs property tributary of the John Day River, 2.00 miles on Mountain Creek/Collins property tributary of the John Day River, 1.0 miles on South Fork of the John Day River/ Latosky property tributary of the John Day River , 1.0 miles on South Fork of the John Day River/ Mabe property tributary of the John Day River, 3.0 miles on Hay Creek/Campbell property tributary of the John Day River and 1.0 miles on Bear Creek/Norton property tributary of the John Day River.   There will be 2 off-site water developments on Laycock Creek/ Holliday property and 1 off-site water development on Mountain Creek\Collins property.  There will be approximately 35 gates and 13 watergaps constructed on the Eight project sites.  

On Beech Creek/Meredith property juniper rip-rap placement will involve placement of juniper on 3 sites and cover approximately 100 feet per site, 0.20 miles of bank protection.  Juniper protection on Jackie Johns property along Fox Creek to protect 0.50 miles of streambank and use juniper placement to protect approximately 1000 willow cuttings.  These projects are to help eliminate sediment deposits during high flow events on the steelhead redd productions.

Program personnel will talk with landowners where the projects have expired and see if they would like to resign a Cooperative Agreement for an additional 10-15 years.  The leases that have expired need to be looked at to see if fencelines need to be moved out from original positions, due to the fact that original fences were built close to the ordinary high water line and the program is trying to cut down on maintenance costs.
Account Type(s):
Expense
Contract Start Date:
03/01/2008
Contract End Date:
02/28/2009
Current Contract Value:
$531,428
Expenditures:
$531,428

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Program Management and project prioritization B: 119. Program Management 02/28/2009
BPA project administration C: 119. BPA project administration requirements 01/30/2009 01/30/2009
Reestablish Vegetation D: 47. Plant Vegetation/Meredith Property 05/31/2008
Reestablish Vegetation E: 47. Plant Vegetation/Jackie Johns Property 05/31/2008 04/08/2008
Select Project Sites F: 114. Select Project Sites 02/28/2009
Alternative water source G: 34. Water Development/Bob Collins 09/30/2008 09/30/2008
Alternative Water source H: 34. Water Development/Kenny Holliday 11/30/2008 09/30/2008
Spray approximately 50 acres of noxious weeds, knapweed and thistle mainly. I: 22. Noxious weed control 08/31/2008 08/31/2008
15 year Cooperative Agreement Holliday Property J: 92. Kenny Holliday Property 03/30/2008 03/30/2008
15 year Cooperative Agreement with Doug Leach on Eightmile Creek K: 92. Doug Leach Property 04/28/2008 04/28/2008
Lease land L: 92. Alan Jacobs Property 07/28/2008 05/28/2008
Collins 15 year Cooperative Agreement M: 92. Bob Collins Property phase 2 04/27/2008 04/27/2008
15 year Cooperative Agreement on Mabe Property N: 92. Jim Mabe Property 04/03/2008 04/03/2008
15 year Cooperative Agreement on Latoesky Property O: 92. Latoesky Property 04/03/2008 04/03/2008
15 year Cooperative Agreement on Ben Norton's Property P: 92. Norton Property 04/03/2008
15 year Cooperative Agreements Q: 92. Campbell Property 08/28/2008 08/28/2008
15 year Cooperative Agreements R: 92. Placeholder Property 08/28/2008
Maintenance of riparian projects S: 186. Maintain terrestrial structures 12/06/2008 12/06/2008
Instream work T: 29. Instream Work/Meredith property 08/31/2008
Instream work U: 29. Instream Work/Johns property 10/30/2008
Riparian Fence project V: 40. Holliday Property 11/30/2008 11/30/2008
Leach barbed wire fence W: 40. Leach Property 09/17/2008 09/17/2008
Fence Installation X: 40. Jacobs Property 12/15/2008 12/15/2008
Install Fence Y: 40. Collins Property 12/24/2008 12/24/2008
Mabe Property fence Project Z: 40. Jim Mabe Property 10/15/2008 10/15/2008
Latoesky Fence Project AA: 40. Latoesky Property 11/30/2008 11/30/2008
Fence Project an 15 year Cooperative Agreement on one mile of riparian area. AB: 40. Norton Property 04/30/2008
Fence Project an 15 year Cooperative Agreement on two mile of riparian area. AC: 40. Campbell Property 10/15/2008 10/15/2008
Fence Project an additional 15 years on two miles of riparian area. AD: 40. Renewal of approximately 2 miles (location unknown placeholder) 10/15/2008 08/10/2008
Fence Project an additional 10-15 years on approximately 2 miles of riparian area. AE: 40. Renewal of approximately 2 miles (location unknown placeholder) 12/31/2008
Fence Project an additional 15 years on two miles of riparian area. AF: 40. New fence placeholder approximately 2 miles (location unknown placeholder) 12/24/2008
Monitoring and Evaluation AG: 157. Collect/Generate Field and Lab Data 11/21/2008
EC for the Fish Habitat Program AH: 165. Environmental Compliance 09/30/2008 09/30/2008
Annual Report AI: 132. Produce Annual Report 07/31/2008 07/31/2008

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 92 Lease Land
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 22 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 34 Develop Alternative Water Source
  • 11 instances of WE 40 Install Fence
  • 2 instances of WE 47 Plant Vegetation
  • 8 instances of WE 92 Lease Land
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 02/09/2007
B 119 Program Management 02/09/2007
C 119 BPA project administration requirements 02/09/2007
D 47 Plant Vegetation/Meredith Property 12/18/2008
E 47 Plant Vegetation/Jackie Johns Property 12/18/2008
F 114 Select Project Sites 02/09/2007
G 34 Water Development/Bob Collins 02/09/2007
H 34 Water Development/Kenny Holliday 12/18/2008
I 22 Noxious weed control 01/23/2008
J 92 Kenny Holliday Property 02/09/2007
K 92 Doug Leach Property 02/09/2007
L 92 Alan Jacobs Property 02/09/2007
M 92 Bob Collins Property phase 2 02/09/2007
N 92 Jim Mabe Property 02/09/2007
O 92 Latoesky Property 02/09/2007
P 92 Norton Property 02/09/2007
Q 92 Campbell Property 02/09/2007
R 92 Placeholder Property 02/09/2007
S 186 Maintain terrestrial structures 12/18/2008
T 29 Instream Work/Meredith property 02/09/2007
U 29 Instream Work/Johns property 02/09/2007
V 40 Holliday Property 12/18/2008
W 40 Leach Property 12/18/2008
X 40 Jacobs Property 12/18/2008
Y 40 Collins Property 12/18/2008
Z 40 Jim Mabe Property 12/18/2008
AA 40 Latoesky Property 12/18/2008
AB 40 Norton Property 02/09/2007
AC 40 Campbell Property 12/18/2008
AD 40 Renewal of approximately 2 miles (location unknown placeholder)
AE 40 Renewal of approximately 2 miles (location unknown placeholder)
AF 40 New fence placeholder approximately 2 miles (location unknown placeholder)
AG 157 Collect/Generate Field and Lab Data 02/09/2007
AH 165 Environmental Compliance 02/09/2007
AI 132 Produce Annual Report 02/09/2007