Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 41904: 1984-025-00 EXP ODFW BLUE MOUNTAIN FISH HABITAT IMPROVEMENT
Project Number:
Title:
Grande Ronde and Umatilla Fish Habitat Improvement Program
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Blue Mountain Grande Ronde 100.00%
Contract Number:
41904
Contract Title:
1984-025-00 EXP ODFW BLUE MOUNTAIN FISH HABITAT IMPROVEMENT
Contract Continuation:
Previous: Next:
37261: 1984-025-00 JOSEPH CREEK, GRANDE RONDE
  • 52483: 1984-025-00 EXP ODFW BLUE MT FISH HABITAT IMPROVEMENT
Contract Status:
Closed
Contract Description:
ODFW Grande Ronde Basin Fish Habitat Improvement Project, FY2010 Summary

This project continues the Oregon Department of Fish and Wildlife's efforts to restore the riparian and instream habitats in the Blue Mountain Province as mitigation for fisheries losses resulting from development of the federal Columbia River Power System.  The project focuses on the restoration of the habitats utilized by the ESA listed Snake River Spring/Summer Chinook Salmon and Snake River Summer Steelhead, but benefits many other species of fish and wildlife.

Since the initiation of this project in 1984, a total of 57 projects have been completed along 87.0 miles of stream, restoring 3,595 acres of riparian and instream habitat.  Restoration efforts have focused on the Joseph Creek, Wallowa River and Upper Grande Ronde River systems based on recommendations of agencies, tribes and the Grande Ronde Model Watershed Program (GRMWP).  Staff of this project works closely with the GRMWP who provide additional basin-wide funding, and project review and prioritization of individual projects.  This project frequently works in partnership with other agencies including BOR, CTUIR, ODOT, ODF, NOAA, NRCS, USFWS, USFS,  USWCD and others. The results of these restoration efforts have shown improving conditions in project areas for salmon, steelhead and other native fishes.  An in depth summary of the project history, goals and objectives, summaries of individual project accomplishments, and overall results was recently completed by project staff.  The summary report for 1984-2007 can be found at:

https://pisces.bpa.gov/release/documents/documentviewer.aspx?doc=P107898

New project activities planned for this contract period include project planning, design, permitting, and construction.  Specifically, ODFW will continue work on the Ladd Creek/ODFW-LMWA Channel Reconstruction and Wetland Restoration Project.  This includes portions of the East, Middle and West Forks of Ladd Creek in the Catherine Creek Subbasin.  Construction began in 2009 with 2.1 miles of a total of 5.5 miles completed.  Work in 2010 will include completing the designs for the West Fork and tributaries, and construction of the remaining 3.4 miles of stream.  We will work with ODOT to secure funding for design and construction of a new bridge that will be required to connect this project underneath Highway 203.  ODFW will be lead agency on 2 new projects (Willow Creek/McKenzie and the Wallowa River/Baker projects).  We will continue work closely with the GRMWP on new BiOp projects, and the NRCS on the McCoy Creek/Tipperman project.  Construction of additional riparian fences will occur if time, opportunity and funding allow.

Ongoing project activities include maintenance and monitoring of existing projects.  ODFW staff will inspect 57 habitat projects built earlier, conduct maintenance (i.e. repair fences and water gaps, stream banks, etc.) as necessary to ensure habitat treated by these projects continues to improve.   Monitoring to track progress toward meeting project objectives will continue throughout this fiscal year.  Administration, reporting and outreach activities will be conducted as well.
Account Type(s):
Expense
Contract Start Date:
03/01/2009
Contract End Date:
02/28/2011
Current Contract Value:
$734,243
Expenditures:
$734,243

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Local, state and federal permits A: 165. Environmental compliance for construction activities 02/28/2010 02/28/2010
East, Middle, and West Fork of Ladd Creek designs B: 175. Ladd Creek/ODFW-LMWA project designs 02/28/2010 02/28/2010
Ladd Creek Channel Reconstruction C: 30. Ladd Creek/ODFW-LMWA channel reconstruction 02/28/2010 02/28/2010
Ladd Creek instream habitat restoration D: 29. Ladd Creek/ODFW-LMWA instream habitat restoration 02/28/2010 02/28/2010
Ladd Creek wetland restoration E: 181. Ladd Creek/ODFW-LMWA wetland restoration 02/28/2010 02/28/2010
New Riparian Fence F: 40. Riparian fencing projects 02/28/2010 02/28/2010
Ladd Creek vegetation restoration G: 47. Ladd Creek/ODFW-LMWA riparian vegetation restoration 02/28/2010 02/28/2010
Healthy riparian vegetation H: 22. Maintain and manage riparian vegetation within projects 02/28/2010 02/28/2010
Functioning riparian enclosures I: 186. Maintain riparian areas within projects 02/28/2010 02/28/2010
Functioning channel restoration J: 186. Maintain stream channels within existing projects 02/28/2010 02/28/2010
Monitoring results K: 157. Monitor restoration projects 02/28/2010 02/28/2010
Annual Report results and discussion. L: 162. Prepare field data for Annual Report 02/28/2010 02/28/2010
2008 Annual Report M: 132. Submit progress report for the period (Mar 1, 2008 to Feb 28, 2009) 06/15/2009 06/15/2009
Outreach N: 99. Community outreach and education 02/28/2010 02/28/2010
Technical Review O: 122. Provide technical support for other fish habitat projects 02/28/2010 02/28/2010
Regional Coordination P: 189. Regional coordination 02/28/2010 02/28/2010
Project Management Q: 119. Manage and Administer Project 02/28/2010 02/28/2010
List of potential new Blue Mountain Province projects for implementation in future contracts R: 114. Identify, prioritize, and select new projects 02/28/2010 02/28/2010
Local, state and federal permits T: 165. Environmental Compliance for construction activities 02/28/2011 02/28/2011
Project Surveys, Designs, Specifications U: 175. Surveys, Designs and Specifications 02/28/2011 02/28/2011
Ladd Creek Channel Reconstruction V: 30. Ladd Creek/ODFW-LMWA Channel Reconstruction 11/30/2010 08/23/2010
Ladd Creek Instream Habitat Restoration W: 29. Ladd Creek/ODFW-LMWA Instream Habitat restoration 11/30/2010 08/31/2010
Ladd Creek Wetland Restoration X: 181. Ladd Creek/ODFW-LMWA Wetland restoration 11/30/2010 07/23/2010
New Riparian Fence Y: 40. Riparian Fencing projects 02/28/2011
Ladd Creek planting and seeding. Z: 47. Ladd Creek/ODFW-LMWA Riparian Planting 02/28/2011 02/28/2011
Healthy riparian vegetation AA: 22. Maintain and Manage Riparian Vegetation 02/28/2011 02/28/2011
Maintenance of Riparian Areas AB: 186. Maintain Riparian Management Areas 12/31/2010 12/31/2010
Functioning channel restoration AC: 186. Maintain Stream Channels 02/28/2011 02/28/2011
Monitoring Data AD: 157. Monitor restoration projects 02/28/2011 02/28/2011
Analysis of Monitoring Data AE: 162. Analysis and Interpretation of Monitoring Data 02/28/2011 02/28/2011
Annual Report for 2009 AF: 132. Submit Progress Report for the period (Jan 1, 2009 to Dec 31, 2009) 12/31/2010
Outreach and Education AG: 99. Community Outreach and Education 02/28/2011 02/28/2011
Technical Review AH: 122. Provide Technical Review for other fish habitat projects 02/28/2011 02/28/2011
Regional Coordination AI: 189. Regional Coordination 02/28/2011 02/28/2011
Project Management AJ: 119. Manage and Administer Project 02/28/2011 02/28/2011
Prioritized list of potential new Blue Mountain Province projects AK: 114. Identify, prioritize, and select new projects 02/28/2011 02/28/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 2 instances of WE 22 Maintain Vegetation
  • 4 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 30 Realign, Connect, and/or Create Channel
  • 2 instances of WE 40 Install Fence
  • 2 instances of WE 47 Plant Vegetation
  • 2 instances of WE 181 Create, Restore, and/or Enhance Wetland
  • 2 instances of WE 122 Provide Technical Review and Recommendation
  • 2 instances of WE 175 Produce Design
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 2 instances of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 2 instances of WE 22 Maintain Vegetation
  • 4 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 30 Realign, Connect, and/or Create Channel
  • 2 instances of WE 40 Install Fence
  • 2 instances of WE 47 Plant Vegetation
  • 2 instances of WE 181 Create, Restore, and/or Enhance Wetland
  • 2 instances of WE 122 Provide Technical Review and Recommendation
  • 2 instances of WE 175 Produce Design
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 2 instances of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental compliance for construction activities 02/09/2007
B 175 Ladd Creek/ODFW-LMWA project designs 02/09/2007
C 30 Ladd Creek/ODFW-LMWA channel reconstruction 01/22/2009
D 29 Ladd Creek/ODFW-LMWA instream habitat restoration 01/22/2009
E 181 Ladd Creek/ODFW-LMWA wetland restoration 01/22/2009
F 40 Riparian fencing projects 01/22/2009
G 47 Ladd Creek/ODFW-LMWA riparian vegetation restoration 01/22/2009
H 22 Maintain and manage riparian vegetation within projects 01/22/2009
I 186 Maintain riparian areas within projects 02/09/2007
J 186 Maintain stream channels within existing projects 02/09/2007
K 157 Monitor restoration projects 02/12/2009
L 162 Prepare field data for Annual Report 02/09/2007
M 132 Submit progress report for the period (Mar 1, 2008 to Feb 28, 2009) 02/09/2007
N 99 Community outreach and education 02/09/2007
O 122 Provide technical support for other fish habitat projects 02/09/2007
P 189 Regional coordination 02/09/2007
Q 119 Manage and Administer Project 02/09/2007
R 114 Identify, prioritize, and select new projects 02/09/2007
S 185 Periodic Status Reports for BPA 02/09/2007
T 165 Environmental Compliance for construction activities 03/01/2009
U 175 Surveys, Designs and Specifications 03/01/2009
V 30 Ladd Creek/ODFW-LMWA Channel Reconstruction 03/01/2010
W 29 Ladd Creek/ODFW-LMWA Instream Habitat restoration 03/01/2010
X 181 Ladd Creek/ODFW-LMWA Wetland restoration 03/01/2010
Y 40 Riparian Fencing projects 03/01/2010
Z 47 Ladd Creek/ODFW-LMWA Riparian Planting 03/01/2010
AA 22 Maintain and Manage Riparian Vegetation 03/01/2010
AB 186 Maintain Riparian Management Areas 03/01/2010
AC 186 Maintain Stream Channels 03/01/2010
AD 157 Monitor restoration projects 03/01/2010
AE 162 Analysis and Interpretation of Monitoring Data 03/01/2009
AF 132 Submit Progress Report for the period (Jan 1, 2009 to Dec 31, 2009) 03/01/2009
AG 99 Community Outreach and Education 03/01/2009
AH 122 Provide Technical Review for other fish habitat projects 03/01/2009
AI 189 Regional Coordination 03/01/2009
AJ 119 Manage and Administer Project 03/01/2009
AK 114 Identify, prioritize, and select new projects 03/01/2009