Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 42391: 200207000 EXP NPSWCD LAPWAI CREEK WATERSHED RESTORATION
Project Number:
Title:
Lapwai Creek Anadromous Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
42391
Contract Title:
200207000 EXP NPSWCD LAPWAI CREEK WATERSHED RESTORATION
Contract Continuation:
Previous: Next:
38238: 2002-070-00 EXP NPSWCD LAPWAI CREEK WATERSHED RESTORATION
  • 52837: 2002-070-00 EXP NP SWCD LAPWAI CREEK WATERSHED RESTORATION
Contract Status:
Closed
Contract Description:
The Restoring Anadromous Fish Habitat in the Lapwai Creek Watershed, project 2002-070-00, began in 2003.  This multi-year project focuses on restoring and improving fish habitat within the Lapwai Creek watershed.  The limiting factors addressed include low summer flows, wide fluctuation in annual stream flows, connectivity, loss of all or partial floodplain, sedimentation of spawning and rearing habitat, high summer stream temperatures, and lack of in-stream cover.  Past accomplishments have entailed the installation of land improvement projects to address these limiting factors, including 7.8 miles of riparian fencing, 6.21 miles of upland fencing, 160 acres of weed control, two livestock waste systems, 9,000 LF of riparian plantings, one low flow stream crossing, 10.5 miles of road improvements, 1.5 miles of streambank bioengineering restoration, 4.5 acres of wetland enhancement, 15,209 acres of direct seeding, 12 alternative watering systems for livestock, 13 water and sediment control structures, and the development of 34 habitat conservation plans, 9.27 miles of access restored, 3.1 miles of floodplain reconnected, 80 acres of tree planting, and 200 acres of grass seeding.  

Prior to the initiation of this project, a massive data gap existed on fish, the condition of fish habitat, and limiting factors within the watershed.  Under the FY 2007 contract, we focused primarily on the analysis and compilation of the fish presence and abundance data, and stream habitat data collected annually since 2003.  The data was analyzed and converted into a GIS-compatible format and then combined with other available, watershed-wide data sets developed by the Nez Perce Soil and Water Conservation District, the Nez Perce Tribe Watershed Division (NPT) and the NPT Water Resources Division.  The synergistic effect of these combined data sets came together in the development of the "Strategy for the Ecological Restoration of Lapwai Creek Watershed," a document intended to direct efforts and resources toward the highest priority restoration projects and areas of the Lapwai Creek Watershed.  This document provides an accurate assessment of the status and health of the aquatic resources within the watershed, and will allow us to spatially prioritize the implementation of future watershed protection and restoration projects for the Lapwai Creek Watershed. This plan was updated in FY08 to incorporate information identified by the ISRP review.
                                                                                                                                                                          
FY 09 Contract Summary:

The "Strategy for the Ecological Restoration of Lapwai Creek Watershed," which was completed under the FY 07 contract and revised in FY08, was the main reference for prioritizing implementation and developing the FY 09 SOW.  

Under this contract the NPSWCD plans to install 2,500 LF of fence, control 80 acres of noxious weeds, plant 15 acres with native trees and shrubs, install 2 water developments, install 6 erosion control structures, maintain vegetation at 33 sites (160 acres), develop 10 habitat restoration plans and remove one passage barrier.

Status and Trend and Implementation/Effectiveness monitoring under this contract is coordinated with the Nex Perce Tribe.  The Nez Perce Tribe conducts the monitoring and evaluation required to determine population status and trends, as well as the physical and biological response to the habitat/watershed restoration efforts.  The Nez Perce Soil and Water Conservation District (NPSWCD) utilizes the Nez Perce Tribe's monitoring data to prioritize habitat improvement and site specific project areas.  Since the majority of the land within the watershed is privately owned, the District also coordinates with the landowners to obtain project approval for both the NPT and the NPSWCD to continue habitat restoration actions throughout the Lapwai Creek watershed. The Districts efforts focus on non-tribal properties, while the NPT efforts focus on Tribal properties.

UPDATE for FY10 Contract Amendment:

NEED:  The contract is amended to include a second performance period from 5/1/10 through 4/30/11.  The amendment is needed to allow for completion of NHPA section 106 requirements for items in FY09 as well as FY10.  This amendment specifically provides for NPSWCD to re-organize the schedule of Work Elements (WE) initially planned for completion in the first year of the contract to carry into the second year of performance.  There were significant delays in completing environmental and cultural surveys (E/CS) for work scheduled during the first year - these delayed  E/CS will be completed in adequate time for first year WE to be completed within the extended performance period.  Additionally, this amendment includes new WE's that are planned for completion within the performance period (4-30-11).   The new  Work Elements for the extended (second year) work period are WE's Z - AY.   Additionally, WE's  A, C, D, E, F, K, G, H, J, Q, R and V  were also adjusted as part of this amendment.
Account Type(s):
Expense
Contract Start Date:
05/01/2009
Contract End Date:
04/30/2011
Current Contract Value:
$495,863
Expenditures:
$495,863

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Environmental Compliance Requirements Completed A: 165. Environmental Compliance 02/03/2011 02/03/2011
Design package for 8 land improvement projects B: 175. Prepare Engineering and Technical Designs 04/15/2010 12/14/2009
Install 800 linear feet of fence along Lapwai Creek C: 40. Site 0975 Livestock Exclusion from Lapwai Creek 03/25/2011 02/16/2011
Plant native tree, shrub and grass in riparian and upland area D: 47. Site 0975 Plant Spring/Wetland Area with Native Trees and Shrubs 04/30/2011 04/30/2011
Alternative water source installed E: 34. Site 0975 Create Alternative Water Source for Livestock 04/28/2011 04/28/2011
Remove Culvert F: 184. Site 0972 Fish Passage Barrier Removal 11/30/2010 09/18/2009
Install native tree, shrub and grass seed in riparian and post construction areas G: 47. Site 0972 Plant Vegetation in Riparian and Construction Areas 03/31/2011 03/29/2011
Install 1,600 linear feet of fence along Lapwai Creek H: 40. Site 0972 Install Fence 04/05/2011 11/17/2010
80 Acres of Invasive Plant Management I: 53. Treat 80 Acres of Exotic Invasive Plant Species 04/16/2010 04/16/2010
Install 800 linear feet of fence along Lapwai Creek J: 40. Site 0974 Install Fence 04/05/2011 11/17/2010
Road improvement completed K: 38. Site 0974 Improve Road to Reduce Sediment Delivery to Lapwai Creek 08/24/2010 09/22/2010
80 acres seeded with direct seeding systems L: 48. Site 0642 Reduce Sediment Delivery to Sweetwater Creek 11/30/2009 10/22/2009
520 acres seeded with direct seeding systems M: 48. Site 0632 Reduce Sediment Delivery to Webb and Sweetwater Creeks 11/30/2009 10/30/2009
six erosion control structures installed N: 55. Site 0973 Install Erosion Control Measures for Sheet, Rill, and Gully Erosion 04/30/2011 04/30/2011
150 acres of vegetation maintained at 33 sites O: 22. Maintain Vegetation at Previously Planted Sites in Contract Years 2005 through 2009 04/21/2010 04/21/2010
Raw temperature data P: 157. Stream Temperature Data Collection in the Lapwai Creek Watershed 11/28/2009 11/19/2009
Updated GIS database Q: 160. Maintain GIS database 03/31/2011 03/30/2011
Data Sent to Idaho StreamNet Project Leader R: 161. Supply Publicly Available Data to Idaho StreamNet Project Leader 03/14/2011 03/22/2011
Bio-logs and wetland sod planted and stored in holding tanks until 2010 installation S: 47. Preparation of Wetland Sod, Wetland Plugs and Bio-logs for 2010 Planting 03/27/2010 03/30/2010
Project selected for areas prioritized by the Lapwai Ecological Restoration Strategy document T: 114. Select, Prioritize, and Obtain Permission for 2010 Projects 03/31/2010 03/31/2010
Marketing plan implementation U: 99. Implement Lapwai Watershed Marketing Plan 03/31/2010 03/31/2010
FY 10 SOW Package and FY 09 Accrual Estimate V: 119. Management, Coordination, and Communication 02/19/2011 03/01/2011
Final FY 08 report attached to this contract W: 132. Produce Progress Report for Period 4/1/08-4/30/09 10/15/2009 10/15/2009
Completed RIPP Step 1 on 10 non-tribal Properties Y: 115. Complete 10 Habitat Restoration Plans 11/30/2009 12/15/2009
Install 3600 linear feet of fence along Rock Creek Z: 40. Site 1092 Livestock Exclusion from Lapwai Creek 01/16/2011 03/24/2011
Plant native tree, shrub and grass in riparian and upland area AA: 47. Site 1092 Plant Spring/Wetland Area with Native Trees and Shrubs 04/20/2011 04/20/2011
Alternative water source installed AB: 34. Site 1092 Create Alternative Water Source for Livestock 04/15/2011 04/15/2011
Provide livestock access to pasture AC: 38. Site 1092 Livestock Crossing 04/14/2011 04/14/2011
First work period progress report attached to this contract AD: 132. Produce Progress Report for Period 5/1/09-4/30/10 07/30/2010 07/30/2010
Completed RIPP Step 1 on 8 non-tribal Properties AE: 115. Complete 8 Habitat Restoration Plans for second work period 12/30/2010 11/05/2010
Marketing plan implementation AF: 99. Implement Lapwai Watershed Marketing Plan for second work period 04/22/2011 04/22/2011
Project selected for areas prioritized by the Lapwai Ecological Restoration Strategy document AG: 114. Select, Prioritize, and Obtain Permission for 2011 Projects 12/17/2010 12/09/2010
Bio-logs and wetland sod planted and stored in holding tanks until 2011 installation AH: 47. Preparation of Wetland Sod, Wetland Plugs and Bio-logs for 2011 Planting 04/29/2011 04/29/2011
Raw temperature data AI: 157. Stream Temperature Data Collection in the Lapwai Creek Watershed 12/09/2010 12/27/2010
150 acres of vegetation maintained at 33 sites AJ: 22. Second Performanc Period Planted Sites Maintenance 11/11/2010 11/04/2010
Alternative water source installed AK: 34. Site 1097 Create Alternative Water Source for Livestock 04/07/2011 04/30/2011
Install 1000 linear feet of fence along Mission Creek AL: 40. Site 1097 Install Fence 04/07/2011 04/26/2011
Install 1400 linear feet of fence along Lapwai Creek AM: 40. Site 1096 Install Fence 10/30/2010 11/17/2010
Installation of 3,000 lf of grassed waterways AN: 55. Site 0992 Grass Waterway 12/17/2010 11/30/2010
520 acres seeded with direct seeding systems AO: 48. Site 0632 Reduce Sediment Delivery to Webb and Sweetwater Creeks 11/30/2010 11/05/2010
80 acres seeded with direct seeding systems AP: 48. Site 0642 Reduce Sediment Delivery to Sweetwater Creek 11/30/2010 10/27/2010
Alternative water source installed AQ: 34. Site 1095 Create Alternative Water Source for Livestock 04/14/2011 04/30/2011
Road improvement completed AR: 38. Site 1095 Improve Road to Reduce Sediment Delivery to Lapwai Creek 12/08/2010 12/16/2010
Plant native tree, shrub and grass in riparian and upland area AS: 47. Site 1095 Plant Riparian Area with Native Trees and Shrubs 04/20/2011 04/30/2011
Install 2050 linear feet of fence along Tom Beall Creek AT: 40. Site 1095 Install Fence 04/14/2011 04/30/2011
50 Acres of Invasive Plant Management AU: 53. Release biocontrol agents for yellow star thistle and spotted knapweed control. 07/30/2010 07/09/2010
11 miles Stream Treated for Hybrid Knotweed AV: 53. Control Hybrid Knotweed in second contract period 10/29/2010 10/10/2010
15 Acres of Invasive Plant Management AW: 53. Treat 15 Acres of Exotic Invasive Plant Species 11/30/2010 10/10/2010
Install 1,500 linear feet of fence along Rock Creek AX: 40. Site 1094 Install Fence 03/24/2011 03/24/2011
Install native tree, shrub and grass seed in riparian areas AY: 47. Site 1094 Plant Vegetation in Riparian Zone 04/23/2011 04/30/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 2 instances of WE 22 Maintain Vegetation
  • 4 instances of WE 34 Develop Alternative Water Source
  • 3 instances of WE 38 Improve Road for Instream Habitat Benefits
  • 8 instances of WE 40 Install Fence
  • 7 instances of WE 47 Plant Vegetation
  • 4 instances of WE 48 Practice No-till and Conservation Tillage Systems
  • 4 instances of WE 53 Remove Vegetation
  • 2 instances of WE 55 Erosion and Sedimentation Control
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance 02/09/2007
B 175 Prepare Engineering and Technical Designs 02/09/2007
C 40 Site 0975 Livestock Exclusion from Lapwai Creek 09/02/2010
D 47 Site 0975 Plant Spring/Wetland Area with Native Trees and Shrubs 09/02/2010
E 34 Site 0975 Create Alternative Water Source for Livestock 09/02/2010
F 184 Site 0972 Fish Passage Barrier Removal 12/06/2010
G 47 Site 0972 Plant Vegetation in Riparian and Construction Areas 09/02/2010
H 40 Site 0972 Install Fence 09/02/2010
I 53 Treat 80 Acres of Exotic Invasive Plant Species 03/04/2010
J 40 Site 0974 Install Fence 09/02/2010
K 38 Site 0974 Improve Road to Reduce Sediment Delivery to Lapwai Creek 09/02/2010
L 48 Site 0642 Reduce Sediment Delivery to Sweetwater Creek 02/09/2007
M 48 Site 0632 Reduce Sediment Delivery to Webb and Sweetwater Creeks 02/09/2007
N 55 Site 0973 Install Erosion Control Measures for Sheet, Rill, and Gully Erosion 09/02/2010
O 22 Maintain Vegetation at Previously Planted Sites in Contract Years 2005 through 2009 03/04/2010
P 157 Stream Temperature Data Collection in the Lapwai Creek Watershed 03/04/2010
Q 160 Maintain GIS database 02/09/2007
R 161 Supply Publicly Available Data to Idaho StreamNet Project Leader 02/09/2007
S 47 Preparation of Wetland Sod, Wetland Plugs and Bio-logs for 2010 Planting 02/09/2007
T 114 Select, Prioritize, and Obtain Permission for 2010 Projects 02/09/2007
U 99 Implement Lapwai Watershed Marketing Plan 02/09/2007
V 119 Management, Coordination, and Communication 02/09/2007
W 132 Produce Progress Report for Period 4/1/08-4/30/09 02/09/2007
X 185 Periodic Status Reports for BPA 02/09/2007
Y 115 Complete 10 Habitat Restoration Plans 02/09/2007
Z 40 Site 1092 Livestock Exclusion from Lapwai Creek 09/02/2010
AA 47 Site 1092 Plant Spring/Wetland Area with Native Trees and Shrubs 09/02/2010
AB 34 Site 1092 Create Alternative Water Source for Livestock 09/02/2010
AC 38 Site 1092 Livestock Crossing 09/02/2010
AD 132 Produce Progress Report for Period 5/1/09-4/30/10 05/01/2009
AE 115 Complete 8 Habitat Restoration Plans for second work period 05/01/2009
AF 99 Implement Lapwai Watershed Marketing Plan for second work period 05/01/2009
AG 114 Select, Prioritize, and Obtain Permission for 2011 Projects 05/01/2009
AH 47 Preparation of Wetland Sod, Wetland Plugs and Bio-logs for 2011 Planting 05/01/2009
AI 157 Stream Temperature Data Collection in the Lapwai Creek Watershed 09/02/2010
AJ 22 Second Performanc Period Planted Sites Maintenance 09/02/2010
AK 34 Site 1097 Create Alternative Water Source for Livestock 09/02/2010
AL 40 Site 1097 Install Fence 09/02/2010
AM 40 Site 1096 Install Fence 09/02/2010
AN 55 Site 0992 Grass Waterway 09/02/2010
AO 48 Site 0632 Reduce Sediment Delivery to Webb and Sweetwater Creeks 09/02/2010
AP 48 Site 0642 Reduce Sediment Delivery to Sweetwater Creek 09/02/2010
AQ 34 Site 1095 Create Alternative Water Source for Livestock 08/31/2010
AR 38 Site 1095 Improve Road to Reduce Sediment Delivery to Lapwai Creek 08/31/2010
AS 47 Site 1095 Plant Riparian Area with Native Trees and Shrubs 08/31/2010
AT 40 Site 1095 Install Fence 08/31/2010
AU 53 Release biocontrol agents for yellow star thistle and spotted knapweed control. 08/27/2010
AV 53 Control Hybrid Knotweed in second contract period 09/02/2010
AW 53 Treat 15 Acres of Exotic Invasive Plant Species 09/02/2010
AX 40 Site 1094 Install Fence 09/02/2010
AY 47 Site 1094 Plant Vegetation in Riparian Zone 09/02/2010