Contract 42560: 1990-044-00 EXP CDA FISHERIES HABITAT RESTORATION
Project Number:
Title:
Coeur D'Alene Reservation Fisheries Habitat
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Coeur D'Alene 100.00%
Contract Number:
42560
Contract Title:
1990-044-00 EXP CDA FISHERIES HABITAT RESTORATION
Contract Continuation:
Previous: Next:
37842: 1990-044-00 COEUR D'ALENE RESERVATION FISHERIES HABITAT RESTORE
  • 47583: 1990-044-00 EXP CDA FISHERIES HABITAT RESTORATION
Contract Status:
Closed
Contract Description:
The scope of work and budget presented in this document describe the activities associated with the Coeur d'Alene Tribe's resident fish enhancement project for the Coeur d'Alene Subbasin corresponding to the contract period June 1, 2009 to May 31, 2010.  The work elements for this project have been grouped under general objective headings corresponding to Planning and Coordination, Construction and Implementation, Research and Monitoring, and Project Administration.

Objective 1 - Planning and Coordination
WE A: NEPA Analysis and Documentation
WE B: Coordinate Restoration Efforts with Stakeholders
WE C: Identify and Select New Restoration Projects

Objective 2 - Construction and Implementation
WE D: Benewah Creek Channel Construction
WE E: Plant Disturbed Areas in Benewah Creek Following Construction
WE F: Enhance Riparian Plant Communities in Benewah Creek
WE G: Conduct O&M Activities at Riparian Planting Site in Benewah Creek
WE H: West Fork Lake Creek Channel Construction
WE I: Plant Disturbed Areas in West Fork Lake Creek Following Construction
WE J: Remove Brook Trout from Benewah Creek
WE K: Analyze Data from Brook Trout Removal from Benewah Creek

Objective 3 - Research and Monitoring
Biological Monitoring
WE L: Install and Maintain Migration Traps - Lake and Benewah Creeks
WE M: Trap Adfluvial Westslope Cutthroat Trout - Lake and Benewah Creeks
WE N: Install PIT tag antenna system in Benewah Creek
WE O: PIT Tag Juvenile Adfluvial Westslope Cutthroat Trout - Lake and Benewah Creeks
WE P: Sample Salmonids in Target Watersheds for Population Estimation
WE Q: Biological Data Management
WE R: Analyze Data Generated from Salmonid Trapping and PIT Tagging
WE S: Analyze Data Generated from Salmonid Sampling

Physical Habitat/Water Quality Monitoring
WE T: Measure Physical Habitat in Reference and Treatment Reaches
WE U: Measure Water and Air Temperature in Target Watersheds
WE V: Measure Thermal Heterogeneity in Benewah Creek
WE W: Physical Data Management
WE X: Analyze Data from Physical Habitat Sampling and Temperature Monitoring

Objective 4 - Project Administration
WE Y: Provide Education and Outreach Opportunities
WE Z: Produce Periodic Status Reports for BPA
WE AA: Submit Annual Report for the period Jan 2008 to Dec 2008
WE AB: Submit Annual Report for the period Jan 2009 to Dec 2009
WE AC: Manage and Administer Project

The total work element budget being submitted with this scope of work is $1,470,548
Account Type(s):
Expense
Contract Start Date:
06/01/2009
Contract End Date:
05/31/2010
Current Contract Value:
$1,426,280
Expenditures:
$1,426,280

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Merve Bearcub Coeur D'Alene Tribe No Interested Party mmbearcub@cdatribe-nsn.gov (208) 686-5104
Stephanie Breeden Bonneville Power Administration No Env. Compliance Lead sfbreeden@bpa.gov (503) 230-5192
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Carla Marratt Coeur D'Alene Tribe No Administrative Contact cmarratt@cdatribe-nsn.gov (208) 686-6803
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Virgil Watts III Bonneville Power Administration Yes COR vlwatts@bpa.gov (503) 230-4625


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
NEPA Checklist A: 165. Complete NEPA Analysis and Documentation 08/28/2009 09/01/2009
Summary of Activities B: 189. Coordinate Restoration Efforts with Stakeholders 05/31/2010 05/31/2010
Project Descriptions/Agreements C: 114. Identify and Select New Restoration Projects 05/31/2010 05/14/2010
Complete Restoration Design Elements D: 30. Benewah Creek Channel Construction 08/14/2009 08/14/2009
Vegetate Disturbed Areas E: 47. Plant Disturbed Areas in Benewah Creek Following Construction 05/31/2010 04/30/2010
Plant 6,040 Deciduous Trees and Shrubs F: 47. Enhance Riparian/Floodplain Plant Communities in Benewah Creek 05/31/2010 04/30/2010
Plant Native Vegetation G: 47. Conduct O&M Activities at Riparian Planting Site in Benewah Creek 05/31/2010 03/12/2010
Complete channel construction H: 30. West Fork Lake Creek Channel Construction 10/30/2009 10/30/2009
Vegetate Disturbed Areas I: 47. Plant Disturbed Areas In Lake Creek Following Construction 05/31/2010 05/14/2010
Remove Brook Trout from Benewah Creek J: 190. Remove Brook Trout from Benewah Creek 10/02/2009 11/13/2009
Evaluate Brook Trout Removal Effectiveness K: 162. Analyze Data from Brook Trout Removal from Benewah Creek 02/26/2010 03/25/2010
Install Migration Traps in Lake and Benewah Creeks L: 70. Install and Maintain Migration Traps Lake and Benewah Creeks 05/31/2010 05/31/2010
Monitored movements and numerical abundances of adfluvial cutthroat trout M: 157. Trap Juvenile and Adult Adfluvial Westslope Cutthroat Trout in Lake and Benewah Creeks 05/31/2010 05/31/2010
Operational PIT Tag Systems N: 70. Install and Maintain PIT tag antenna system in Lake and Benewah Creeks 05/31/2010 05/31/2010
PIT Tag Juvenile Cutthroat in Lake and Benewah Creeks O: 158. PIT Tag Juvenile Adfluvial Westslope Cutthroat Trout in Lake Creek and Benewah Creek 05/31/2010 05/31/2010
Abundance Estimates of Salmonids in Target Watersheds P: 157. Sample Salmonids in Target Watersheds for Population Estimation 10/16/2009 10/30/2009
Updated Database of Biological and Life-History Salmonid Variables for Target Watersheds Q: 160. Biological Data Management 05/31/2010 05/31/2010
Abundance and Life-History Information for Adfluvial Westslope Cutthroat Trout R: 162. Analyze Data Generated from Salmonid Trapping and PIT Tagging in Lake and Benewah Creeks 02/26/2010 03/19/2010
Trend Analyses of Watershed Scale Salmonid Abundance S: 162. Analyze Data Generated from Salmonid Sampling in Target Watersheds 02/26/2010 03/19/2010
Completed Inventories T: 157. Measure Physical Habitat in Reference and Treatment Reaches 10/30/2009 08/31/2009
Hourly Water and Air Temperatures Describing Longitudinal Patterns in Target Watersheds U: 157. Measure Water and Air Temperature in Alder, Lake, Benewah and Evans Creek watersheds 05/31/2010 05/31/2010
Measurement of Thermal Heterogeneity in Benewah Creek V: 157. Measure Thermal Heterogeneity in Benewah Creek 08/29/2009 08/28/2009
Updated Database of Physical Habitat Attributes, Temperature and Discharge Measurements W: 160. Physical Data Management 05/31/2010 05/31/2010
Analyses of Physical Habitat and Temperature Data X: 162. Analyze Data from Physical Habitat Sampling and Temperature Monitoring in Target Watersheds 02/26/2010 03/19/2010
Summary of Education/Outreach Activities Y: 99. Provide Education and Outreach Opportunities 05/31/2010 05/31/2010
Final 2008 report uploaded to the BPA website AA: 132. Submit Annual Report for the period Jan 2008 to Dec 2008 02/26/2010 01/08/2010
Final 2009 report uploaded to the BPA website AB: 132. Submit Annual Report for the period Jan 2009 to Dec 2009 05/31/2010
Accrual Estimates/FY10 SOW/Metrics Reports AC: 119. Manage and Administer Project 05/31/2010 05/31/2010

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Cutthroat Trout, Westslope (O. c. lewisi)
  • 1 instance of WE 190 Remove, Exclude and/or Relocate Animals
  • 2 instances of WE 30 Realign, Connect, and/or Create Channel
  • 4 instances of WE 47 Plant Vegetation
  • 2 instances of WE 70 Install Fish Monitoring Equipment
  • 5 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals
  • 3 instances of WE 162 Analyze/Interpret Data
Trout, Brook (Salvelinus fontinalis)
  • 1 instance of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Complete NEPA Analysis and Documentation 02/09/2007
B 189 Coordinate Restoration Efforts with Stakeholders 02/09/2007
C 114 Identify and Select New Restoration Projects 02/09/2007
D 30 Benewah Creek Channel Construction 01/19/2009
E 47 Plant Disturbed Areas in Benewah Creek Following Construction 01/19/2009
F 47 Enhance Riparian/Floodplain Plant Communities in Benewah Creek 01/19/2009
G 47 Conduct O&M Activities at Riparian Planting Site in Benewah Creek 01/19/2009
H 30 West Fork Lake Creek Channel Construction 01/19/2009
I 47 Plant Disturbed Areas In Lake Creek Following Construction 01/19/2009
J 190 Remove Brook Trout from Benewah Creek 01/19/2009
K 162 Analyze Data from Brook Trout Removal from Benewah Creek 02/09/2007
L 70 Install and Maintain Migration Traps Lake and Benewah Creeks 01/19/2009
M 157 Trap Juvenile and Adult Adfluvial Westslope Cutthroat Trout in Lake and Benewah Creeks 01/19/2009
N 70 Install and Maintain PIT tag antenna system in Lake and Benewah Creeks 01/19/2009
O 158 PIT Tag Juvenile Adfluvial Westslope Cutthroat Trout in Lake Creek and Benewah Creek 01/19/2009
P 157 Sample Salmonids in Target Watersheds for Population Estimation 01/19/2009
Q 160 Biological Data Management 02/09/2007
R 162 Analyze Data Generated from Salmonid Trapping and PIT Tagging in Lake and Benewah Creeks 02/09/2007
S 162 Analyze Data Generated from Salmonid Sampling in Target Watersheds 02/09/2007
T 157 Measure Physical Habitat in Reference and Treatment Reaches 01/19/2009
U 157 Measure Water and Air Temperature in Alder, Lake, Benewah and Evans Creek watersheds 01/19/2009
V 157 Measure Thermal Heterogeneity in Benewah Creek 01/19/2009
W 160 Physical Data Management 02/09/2007
X 162 Analyze Data from Physical Habitat Sampling and Temperature Monitoring in Target Watersheds 02/09/2007
Y 99 Provide Education and Outreach Opportunities 02/09/2007
Z 185 Periodic Status Reports for BPA 02/09/2007
AA 132 Submit Annual Report for the period Jan 2008 to Dec 2008 02/09/2007
AB 132 Submit Annual Report for the period Jan 2009 to Dec 2009 02/09/2007
AC 119 Manage and Administer Project 02/09/2007