Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 43501: 2007-268-00 EXP IDAHO WATERSHED HABITAT RESTORATION-CUSTER
Project Number:
Title:
Idaho Watershed Habitat Restoration-Custer District
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
43501
Contract Title:
2007-268-00 EXP IDAHO WATERSHED HABITAT RESTORATION-CUSTER
Contract Continuation:
Previous: Next:
37919: 2007-268-00 EXP ID WATERSHED HABITAT RESTORATION-CUSTER
  • 49514: 2007-268-00 EXP IDAHO WATERSHED HABITAT RESTORATION-CUSTER
Contract Status:
Closed
Contract Description:
The project scope is to implement high priority action items to maintain, enhance and restore fish habitat and fish passage in the priority stream segments of the Upper Salmon Basin area within the administrative boundaries of the Custer Soil and Water Conservation District.

Implementation of measures funded under this plan will achieve the objective of the Northwest Power Planning Council's Strategy for Salmon Recovery, the National Marine Fisheries Service Salmon Recovery Plan in terms of stabilizing and improving habitat for anadromous fish and the "Four Governors Salmon Recovery Recommendations for Salmon Recovery". Migratory and habitat connectivity across the watershed's valley bottom areas is of high importance to ecologically-based restoration efforts because the tributary sub-watersheds tend to be dominated by federal lands and often provide habitat strongholds for native species of fish and wildlife.

Key habitat limitations in the watershed's bottomland areas include migration problems/ blockages and streambed sedimentation. Addressing these limitations may offer an opportunity to enhance the watershed's anadromous salmonids and will clearly benefit other native species of salmonids, other fish, and wildlife.  The primary opportunity for addressing these problems in the East Fork and Upper Salmon watersheds is through the CSWCD and their collaborative efforts on non-federal land.

Projects developed for this SOW will enhance projects installed over the past three to six years under BPA/CSWCD contracts. The Stanley riparian fences has enhanced approximately 4.5 mile of riparian protection in the Upper Salmon. The additional fence to be installed under this contract will continue to show riparian improvements. Riparian plantings in lower Stanley will further enhance approximately six miles of continous riparian fence in lower Stanley. Approximately 4.5 miles was installed under BPA contracts in 2005/2006. Continued efforts are being made in the East Fork, Salmon River, and Challis Creek to improve riparain protection in the Upper Salmon Basin.
Account Type(s):
Expense
Contract Start Date:
08/01/2009
Contract End Date:
08/31/2010
Current Contract Value:
$125,889
Expenditures:
$125,889

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Funding Package - Submit draft to COTR A: 119. Routine contract actions 07/30/2010 08/20/2010
Prepare Necessary Environmental Compliance documentation for relevant projects B: 165. Produce Environmental Compliance Documents for projects 10/01/2009 09/14/2009
Conduct Education and Outreach Program to target key habitat and passages areas within CSWCD. C: 99. Provide Outreach and Education for Habitat Projects 07/30/2010 06/30/2010
Designs and Specifications from NRCS on BPA project D: 175. NRCS Staff Position for Cost 06/30/2010 06/30/2010
Identify and Select Individual Projects E: 114. Identify and develop habitat projects 06/30/2010 06/30/2010
Install approximately 1200 feet of riparian fence F: 40. Install Riparian Fence in Stanley 06/30/2010 12/01/2009
Install 6 Flow Measuring Devices G: 148. Install flow measuring devices to provide water measurement 07/30/2010 06/30/2010
Attach Progress Report in Pisces I: 132. Submit Progress Report for the period August 2009 thru July 2010 08/31/2010
Install approximately 5500 feet of riparian exclusion fence J: 40. Install Riparian Fence near Salmon River/Morgan Creek 07/23/2010 05/14/2010
Install approximately 1000 feet of fence along Challis Creek K: 40. Install Riparian Fence on Challis Creek 08/26/2010
Develop Alternative Stockwater Systems L: 34. Develop Alternative Stock Water for Challis Creek Riparian Area 08/20/2010 08/26/2010
Provide irrigation from an well to replace Elk Creek instream diversion water for irrigation M: 84. Remove Elk Creek In-Stream Diversion 07/15/2010 07/09/2010

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened)
  • 1 instance of WE 34 Develop Alternative Water Source
  • 2 instances of WE 40 Install Fence
  • 1 instance of WE 84 Remove/Install Diversion
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 3 instances of WE 40 Install Fence
  • 1 instance of WE 84 Remove/Install Diversion
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 148 Install Flow Measuring Device
Sockeye (O. nerka) - Snake River ESU (Endangered)
  • 1 instance of WE 84 Remove/Install Diversion
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 34 Develop Alternative Water Source
  • 3 instances of WE 40 Install Fence
  • 1 instance of WE 84 Remove/Install Diversion
  • 1 instance of WE 148 Install Flow Measuring Device

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Routine contract actions 02/09/2007
B 165 Produce Environmental Compliance Documents for projects 02/09/2007
C 99 Provide Outreach and Education for Habitat Projects 02/09/2007
D 175 NRCS Staff Position for Cost 02/09/2007
E 114 Identify and develop habitat projects 02/09/2007
F 40 Install Riparian Fence in Stanley 09/24/2009
G 148 Install flow measuring devices to provide water measurement 06/04/2010
H 185 Periodic Status Reports for BPA 02/09/2007
I 132 Submit Progress Report for the period August 2009 thru July 2010 02/09/2007
J 40 Install Riparian Fence near Salmon River/Morgan Creek 01/26/2010
K 40 Install Riparian Fence on Challis Creek 01/26/2010
L 34 Develop Alternative Stock Water for Challis Creek Riparian Area 08/26/2010
M 84 Remove Elk Creek In-Stream Diversion 01/26/2010