Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 47583: 1990-044-00 EXP CDA FISHERIES HABITAT RESTORATION
Project Number:
Title:
Coeur D'Alene Reservation Fisheries Habitat
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Coeur D'Alene 100.00%
Contract Number:
47583
Contract Title:
1990-044-00 EXP CDA FISHERIES HABITAT RESTORATION
Contract Continuation:
Previous: Next:
42560: 1990-044-00 EXP CDA FISHERIES HABITAT RESTORATION
  • 52937: 1990-044-00 EXP CDA FISHERIES HABITAT RESTORATION
Contract Status:
Closed
Contract Description:
The scope of work and budget presented in this document describe the activities associated with the Coeur d'Alene Tribe's resident fish enhancement project for the Coeur d'Alene Subbasin corresponding to the contract period June 1, 2010 to May 31, 2011.  The work elements for this project have been grouped under general objective headings corresponding to Planning and Coordination, Construction and Implementation, Research and Monitoring, and Project Administration.

Objective 1 - Planning and Coordination
WE A: NEPA Analysis and Documentation
WE B: Coordinate Restoration Efforts with Stakeholders
WE C: Identify and Select New Restoration Projects
WE D: Inventory In-Channel Large Wood and LWD Recruitment Potential
WE E: Complete project planning for West Fork Benewah Creek Fish Passage Improvement

Objective 2 - Construction and Implementation
WE F: Benewah Creek Channel Construction
WE G: Plant Disturbed Areas in Benewah Creek Following Construction
WE H: Enhance Riparian Plant Communities in Benewah Creek
WE I: West Fork Lake Creek Channel Construction
WE J: Plant Disturbed Areas in West Fork Lake Creek Following Construction
WE K: Remove Brook Trout from Benewah Creek
WE L: Analyze Data from Brook Trout Removal from Benewah Creek

Objective 3 - Research and Monitoring
Biological Monitoring
WE M: Install and Maintain Migration Traps - Lake and Benewah Creeks
WE N: Trap Adfluvial Westslope Cutthroat Trout - Lake and Benewah Creeks
WE O: Install PIT tag antenna system in Benewah Creek
WE P: PIT Tag Juvenile Adfluvial Westslope Cutthroat Trout - Lake and Benewah Creeks
WE Q: Sample Salmonids in Target Watersheds for Population Estimation
WE R: Roving Salmonid Survey in Tributaries in the Lake Creek
WE S: Biological Data Management
WE T: Analyze Data Generated from Salmonid Trapping and PIT Tagging
WE U: Analyze Data Generated from Salmonid Sampling

Physical Habitat/Water Quality Monitoring
WE V: Measure Physical Habitat in Reference and Treatment Reaches
WE W: Measure Physical Habitat Associated with Beaver Dams
WE X: Measure Water and Air Temperature in Target Watersheds
WE Y: Measure Thermal Heterogeneity in Benewah Creek
WE Z: Physical Data Management
WE AA: Analyze Data from Physical Habitat Sampling and Temperature Monitoring
WE AB: Analyze Data from Monitoring of Engineered and Natural Beaver Dam Structures in Benewah Creek

Objective 4 - Project Administration
WE AC: Provide Education and Outreach Opportunities
WE AD: Produce Periodic Status Reports for BPA
WE AE: Submit Annual Report for the period Jan 2009 to Dec 2009
WE AF: Manage and Administer Project

The total work element budget being submitted with this scope of work is $1,502,526
Account Type(s):
Expense
Contract Start Date:
06/01/2010
Contract End Date:
05/31/2011
Current Contract Value:
$1,498,014
Expenditures:
$1,498,014

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Merve Bearcub Coeur D'Alene Tribe Yes Interested Party mmbearcub@cdatribe-nsn.gov (208) 686-5104
Stephanie Breeden Bonneville Power Administration No Env. Compliance Lead sfbreeden@bpa.gov (503) 230-5192
Cameron Heusser Coeur D'Alene Tribe Yes Interested Party cheusser@cdatribe-nsn.gov (208) 686-5521
Jeff Jordan Coeur D'Alene Tribe No Supervisor jjjordan@cdatribe-nsn.gov (208) 686-8702
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Carla Marratt Coeur D'Alene Tribe Yes Administrative Contact cmarratt@cdatribe-nsn.gov (208) 686-6803
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Angelo Vitale Coeur D'Alene Tribe Yes Contract Manager ajvitale@cdatribe-nsn.gov (208) 686-6903
Virgil Watts III Bonneville Power Administration Yes COR vlwatts@bpa.gov (503) 230-4625


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
NEPA Checklist A: 165. Complete NEPA Analysis and Documentation 08/28/2010 07/30/2010
Summary of Activities B: 189. Coordinate Restoration Efforts with Stakeholders 05/31/2011 05/27/2011
Project Descriptions/Agreements C: 114. Identify and Select New Restoration Projects 05/31/2011 05/27/2011
Completed Survey and Management Recommendations D: 115. Inventory In Channel Large Wood and LWD Recruitment Potential 11/30/2010 11/26/2010
Completed design E: 175. Complete project planning for West Fork Benewah Creek Fish Passage Improvement 05/31/2011 05/27/2011
Complete Restoration Design Elements F: 30. Benewah Creek Channel Construction 10/01/2010 09/30/2010
Vegetate Disturbed Areas G: 47. Plant Disturbed Areas in Benewah Creek Following Construction 05/31/2011 05/27/2011
Plant 3,700 Deciduous Trees and Shrubs H: 47. Enhance Riparian/Floodplain Plant Communities in Benewah Creek 05/31/2011 05/27/2011
Complete channel construction I: 30. West Fork Lake Creek Channel Construction 10/31/2010 08/27/2010
Vegetate Disturbed Areas J: 47. Plant Disturbed Areas In Lake Creek Following Construction 05/31/2011 05/27/2011
Remove Brook Trout from Benewah Creek K: 190. Remove Brook Trout from Benewah Creek 10/15/2010 11/30/2010
Evaluate the effectiveness of removal techniques L: 162. Analyze Data from Brook Trout Removal from Benewah Creek 02/25/2011 02/28/2011
Install Migration Traps in Lake and Benewah Creeks M: 70. Install and Maintain Migration Traps Lake and Benewah Creeks 05/31/2011 05/27/2011
Monitored movements and numerical abundances of adfluvial cutthroat trout N: 157. Trap Juvenile and Adult Adfluvial Westslope Cutthroat Trout in Lake and Benewah Creeks 05/31/2011 05/27/2011
Operational PIT Tag Systems O: 70. Install and Maintain PIT tag antenna system in Lake and Benewah Creeks 05/31/2011 05/27/2011
PIT Tag Juvenile Cutthroat in Lake and Benewah Creeks P: 158. PIT Tag Juvenile Adfluvial Westslope Cutthroat Trout in Lake Creek and Benewah Creek 05/31/2011 05/27/2011
Abundance Estimates of Salmonids in Target Watersheds Q: 157. Sample Salmonids in Target Watersheds for Indices of Abundance 10/16/2010 10/15/2010
Distribution maps R: 157. Roving Salmonid Survey in Tributaries in the Lake Creek 08/27/2010 07/30/2010
Updated Database of Biological and Life-History Salmonid Variables for Target Watersheds S: 160. Biological Data Management 05/31/2011 05/27/2011
Abundance and Life-History Information for Adfluvial Westslope Cutthroat Trout T: 162. Analyze Data Generated from Salmonid Trapping and PIT Tagging in Lake and Benewah Creeks 02/25/2011 02/28/2011
Trend Analyses of subbasin and watershed scale salmonid abundance U: 162. Analyze Data Generated from Salmonid Sampling in Target Watersheds 02/25/2011 02/28/2011
Completed Inventories V: 157. Measure Physical Habitat in Reference and Treatment Reaches 10/29/2010 10/29/2010
Description of beaver dam characteristics, stability and physical habitat influence W: 157. Measure Physical Habitat Associated with Beaver Dams 10/29/2010 10/29/2010
Hourly Water and Air Temperatures Describing Longitudinal Patterns in Target Watersheds X: 157. Measure Water and Air Temperature in Alder, Lake, Benewah and Evans Creek watersheds 05/31/2011 05/27/2011
Measurement of Thermal Heterogeneity in Benewah Creek Y: 157. Measure Thermal Heterogeneity in Benewah Creek 08/30/2010 08/13/2010
Updated database of physical habitat attributes, temperature and discharge measurements Z: 160. Physical Data Management 05/31/2011 05/27/2011
Analyses of physical habitat and temperature dynamics at reference and treatment sites AA: 162. Analyze Data from Physical Habitat Sampling and Temperature Monitoring in Target Watersheds 02/25/2011 02/28/2011
Analyses of dam stability and physical data collected at monitored beaver dams AB: 162. Analyze Data from Monitoring of Engineered and Natural Beaver Dam Structures in Benewah Creek 02/25/2011 02/28/2011
Summary of Education/Outreach Activities AC: 99. Provide Education and Outreach Opportunities 05/31/2011 05/27/2011
Final 2009 report uploaded to the BPA website AE: 132. Submit Annual Report for the period Jan 2009 to Dec 2009 04/30/2011
Accrual Estimates/FY2011 SOW/Metrics Reports AF: 119. Manage and Administer Project 05/31/2011 05/27/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Cutthroat Trout, Westslope (O. c. lewisi)
  • 1 instance of WE 190 Remove, Exclude and/or Relocate Animals
  • 2 instances of WE 30 Realign, Connect, and/or Create Channel
  • 3 instances of WE 47 Plant Vegetation
  • 1 instance of WE 175 Produce Design
  • 2 instances of WE 70 Install Fish Monitoring Equipment
  • 7 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals
  • 4 instances of WE 162 Analyze/Interpret Data
Trout, Brook (Salvelinus fontinalis)
  • 1 instance of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Complete NEPA Analysis and Documentation 02/09/2007
B 189 Coordinate Restoration Efforts with Stakeholders 02/09/2007
C 114 Identify and Select New Restoration Projects 02/09/2007
D 115 Inventory In Channel Large Wood and LWD Recruitment Potential 06/01/2010
E 175 Complete project planning for West Fork Benewah Creek Fish Passage Improvement 06/01/2010
F 30 Benewah Creek Channel Construction 08/12/2008
G 47 Plant Disturbed Areas in Benewah Creek Following Construction 08/12/2008
H 47 Enhance Riparian/Floodplain Plant Communities in Benewah Creek 08/12/2008
I 30 West Fork Lake Creek Channel Construction 01/18/2009
J 47 Plant Disturbed Areas In Lake Creek Following Construction 01/18/2009
K 190 Remove Brook Trout from Benewah Creek 02/09/2007
L 162 Analyze Data from Brook Trout Removal from Benewah Creek 02/09/2007
M 70 Install and Maintain Migration Traps Lake and Benewah Creeks 08/12/2008
N 157 Trap Juvenile and Adult Adfluvial Westslope Cutthroat Trout in Lake and Benewah Creeks 08/12/2008
O 70 Install and Maintain PIT tag antenna system in Lake and Benewah Creeks 08/12/2008
P 158 PIT Tag Juvenile Adfluvial Westslope Cutthroat Trout in Lake Creek and Benewah Creek 02/09/2007
Q 157 Sample Salmonids in Target Watersheds for Indices of Abundance 02/09/2007
R 157 Roving Salmonid Survey in Tributaries in the Lake Creek 06/01/2010
S 160 Biological Data Management 02/09/2007
T 162 Analyze Data Generated from Salmonid Trapping and PIT Tagging in Lake and Benewah Creeks 02/09/2007
U 162 Analyze Data Generated from Salmonid Sampling in Target Watersheds 02/09/2007
V 157 Measure Physical Habitat in Reference and Treatment Reaches 02/09/2007
W 157 Measure Physical Habitat Associated with Beaver Dams 06/01/2010
X 157 Measure Water and Air Temperature in Alder, Lake, Benewah and Evans Creek watersheds 02/09/2007
Y 157 Measure Thermal Heterogeneity in Benewah Creek 02/09/2007
Z 160 Physical Data Management 02/09/2007
AA 162 Analyze Data from Physical Habitat Sampling and Temperature Monitoring in Target Watersheds 02/09/2007
AB 162 Analyze Data from Monitoring of Engineered and Natural Beaver Dam Structures in Benewah Creek 06/01/2010
AC 99 Provide Education and Outreach Opportunities 02/09/2007
AD 185 Periodic Status Reports for BPA 02/09/2007
AE 132 Submit Annual Report for the period Jan 2009 to Dec 2009 02/09/2007
AF 119 Manage and Administer Project 02/09/2007