SOW Report
Contract 51064: 1998-019-00 EXP WIND RIVER WATERSHED USFS
Project Number:
Title:
Wind River Watershed
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Gorge Wind 100.00%
Contract Number:
51064
Contract Title:
1998-019-00 EXP WIND RIVER WATERSHED USFS
Contract Continuation:
Previous: Next:
45564: 1998-019-00 EXP WIND RIVER WATERSHED
  • 57337: 1998-019-00 EXP WIND RIVER WATERSHED USFS
Contract Status:
Closed
Contract Description:
The Wind River Watershed project is a collaborative effort to restore wild steelhead in the Wind River.  The four agencies forming the nucleus of this partnership include the US Forest Service (FS), Washington Department of Fish and Wildlife (WDFW), U.S. Geological Survey Columbia River Research Lab (CRRL), and Underwood Conservation District (UCD).  This partnership was established in the early 1990's and with support from BPA, has continued to conduct important habitat, research, monitoring and coordination activities across the subbasin.  The project works at multiple levels to identify and characterize key limiting habitat factors in the Wind River, to restore degraded habitats and watershed processes, to measure, track and document fish populations, life histories, and interactions, and to share information across agency and non-agency boundaries.

This contract funds continued habitat restoration within the Wind River watershed.  In FY10, work under this contract includes continued operation of the Wind River Gage to support all of the habitat and monitoring efforts underway across the watershed.  The contract will also fund decommissioning of a road and all of the required surveys, public involvement, environmental coordination and documentation to support the project.  Funds available for this contract are inadequate to cover the full cost of the road decommission, so the FS will be actively pursuing other sources of (non-BPA) funds to provide cost share and allow accomplishment of this important project.  The road to be decommissioned (Forest Road 3056) is currently a source of sediment to the Wind River, and blocks migration of juvenile steelhead, resident fish, and other aquatic organisms on at least three branches of Youngman Creek, a tributary to the upper Wind River.  Removal of the undersized and perched culverts and decommissioning of the road will improve the hydrologic performance of the Youngman Creek drainage by reducing overland water flows, and permitting the streams to properly function over a range of flows.  Sediment introduction to the Wind River will be reduced, and connectivity within the stream and riparian corridor will be re-established, improving migration for all life histories of fish and for other organisms that are an essential part of the aquatic ecosystem.  The road decommission project includes revegetation of the road surface and planting of trees at stream crossings.  In addition to work related to the decommission, this contract provides funding for identification and prioritization of outyear habitat project work in the watershed.
Account Type(s):
Expense
Contract Start Date:
12/01/2010
Contract End Date:
05/31/2012
Current Contract Value:
$99,000
Expenditures:
$99,000

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Erin Black US Forest Service (USFS) No Supervisor ekblack@fs.fed.us (509) 395-3411
Bengt Coffin (USFS) US Forest Service (USFS) Yes Contract Manager bcoffin@fs.fed.us (509) 395-3425
Edward Gresh Bonneville Power Administration Yes Env. Compliance Lead esgresh@bpa.gov (503) 230-5756
Mary Haight Bonneville Power Administration Yes COR mthaight@bpa.gov (503) 230-3112
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Andrew Montano Bonneville Power Administration No Interested Party ammontano@bpa.gov (503) 230-4145
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
Gloria Perez US Forest Service (USFS) No Administrative Contact gperez@fs.fed.us (360) 891-5168
Kimberly Upham Bonneville Power Administration No Interested Party kaupham@bpa.gov (503) 230-3196


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Environmental Assessment and associated reports B: 165. Document that all EC has been completed 04/30/2012 05/31/2012
Attach Progress Report in Pisces C: 132. Submit Progress Report for the period (Dec 2007) to (Nov 2010) 02/24/2012 05/31/2012
Revised final contract funding package to BPA F: 119. Manage Wind River Project 02/29/2012 04/25/2012
Data collection G: 157. Operate and maintain Wind River Gage--contract to River Measurements 05/31/2012 05/31/2012
Decommission Road 3056 H: 33. Decommission Road 3056 09/30/2011 09/30/2011
Revegetate approximately 5.5 acres of road surface I: 47. Plant vegetation on decommissioned Road 3056 11/15/2011 11/15/2011
Removal of four (or more) fish passage barrier culverts J: 184. Remove fish passage barrier culverts on Road 3056 09/30/2011 09/30/2011
Weed Removal K: 53. Pre-project weed removal from Road 3056 and Road 30-136 07/31/2011 07/15/2011
Fish removal completed prior to culvert removal L: 69. Quantify fish presence and install fish screens above and below project 09/30/2011 08/25/2011
Removal of Martha Creek Dam M: 85. Remove Martha Creek Dam 05/31/2012 05/31/2012
Plans for improved crossing structure on Road 4300 at Layout Creek N: 175. Design improved fish passage structure for Layout Creek on Rd 4300 05/31/2012 05/31/2012
Project information exchange O: 191. Exchange project activity and progress information with partner agencies 05/31/2012 05/31/2012

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened)
  • 1 instance of WE 33 Decommission Road/Relocate Road
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 53 Remove Vegetation
  • 1 instance of WE 69 Install Fish Screen
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 12/01/2010
B 165 Document that all EC has been completed 12/01/2010
C 132 Submit Progress Report for the period (Dec 2007) to (Nov 2010) 12/01/2010
D 132 Submit Progress Report for the period (Dec 2010) to (Nov 2011) 12/01/2010
E 132 Delete this WE as its now combined in single report 12/01/2010
F 119 Manage Wind River Project 12/01/2010
G 157 Operate and maintain Wind River Gage--contract to River Measurements 12/01/2010
H 33 Decommission Road 3056 12/01/2010
I 47 Plant vegetation on decommissioned Road 3056 12/01/2010
J 184 Remove fish passage barrier culverts on Road 3056 12/01/2010
K 53 Pre-project weed removal from Road 3056 and Road 30-136 12/01/2010
L 69 Quantify fish presence and install fish screens above and below project 12/01/2010
M 85 Remove Martha Creek Dam 11/16/2011
N 175 Design improved fish passage structure for Layout Creek on Rd 4300 12/01/2010
O 191 Exchange project activity and progress information with partner agencies 12/01/2010