Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 54191: 1988-053-03 EXP CTWS HOOD RIVER M&E
Project Number:
Title:
Hood River Production Program Monitoring and Evaluation (M&E)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Gorge Hood 100.00%
Contract Number:
54191
Contract Title:
1988-053-03 EXP CTWS HOOD RIVER M&E
Contract Continuation:
Previous: Next:
48828: 1988-053-03 EXP CTWS HOOD RIVER M&E
  • 58192: 1988-053-03 EXP CTWS HOOD RIVER M&E
Contract Status:
Closed
Contract Description:
Fisheries Program Manager:  Brad Houslet (541) 553-2039
Fiscal Officer: Arthur Mitchell (541) 553-3219
Hood River Production Program Manager: Chris Brun (541) 352-3548
Technical Contact: Ryan Gerstenberger (541) 352-9326
Address: 6030 Dee Highway, Parkdale, OR 97041

Contracted funds will be used by the  CTWSRO Branch of Natural Resources,  Hood River Production Program to:

Conduct monitoring and evaluation of the existing spring Chinook salmon and winter steelhead re-introduction / supplementation programs. Activities include determining pre-release smolt quality, out migration timing, duration and residualism. 10% of hatchery releases will be fitted with PIT tags.  Spring Chinook spawning locations, timing and success will be monitored. Juvenile distribution salmonid surveys will be conducted. Run size predictions, harvest recommendations and tribal harvest monitoring will be implemented during FY 12.

Water quality monitoring in Rogers Creek and water temperature monitoring throughout the Hood River basin will continue.

Existing HRPP M&E data will be geo-spatially  linked and uploaded to tribal and regional databases.

FY 12 funds from this project will be used to implement the comparative hatchery spring Chinook release group evaluation and begin an winter steelhead residualism investigation.  NOAA fisheries staff will be contracted by BPA to conduct the final year of data collection for the 3 year smolt physiology study. Results from this investigation will assist with determination of long term spring Chinook smolt production strategy.

With funds provided from this project USGS Cook lab will be contracted by BPA to re-construct, maintain and operate and, if possible, determine the detection efficiency of a channel spanning PIT detector installed near the mouth of the Hood River. The results will be used to adjust estimates of out migrating juveniles and returning HOR and NOR adults.
Account Type(s):
Expense
Contract Start Date:
10/01/2011
Contract End Date:
09/30/2012
Current Contract Value:
$227,985
Expenditures:
$227,985

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Submit 2011 SOW to BPA for environmental compliance review. B: 165. Ensure environmental compliance is adequate 09/28/2012 09/28/2012
20,020 PIT tagged steelhead and spring Chinook salmon. C: 158. PIT tag hatchery steelhead and spring Chinook salmon 09/28/2012 09/28/2012
Monitor water temperatures in the Hood River subbasin D: 157. Collect water temperature data in the Hood River subbasin 09/28/2012 09/28/2012
Record water flows in Rogers and Odell Creeks. E: 157. Record stream flows in the Hood River basin. 09/28/2012 09/28/2012
East Fork irrigation canal salvage activities complete F: 28. Salvage and transport fish entrained in irrigation canals to nearest free-flowing waterbody 12/30/2011 12/30/2011
Juvenile spring Chinook salmon distribution G: 157. Conduct basin-wide juvenile spring Chinook distribution surveys. 09/28/2012 09/28/2012
PIT receivers installed. H: 70. Install PIT receivers. 04/20/2012 02/16/2012
Acclimation data I: 157. Collect data during acclimation 07/20/2012 06/05/2012
Submit HRPP hatchery production PIT tag codes to PTAGIS database. J: 159. Input Hood River PIT tag data to appropriate databases 07/02/2012 06/15/2012
BY 12 Hood River spring Chinook salmon spawning distribution and condition. K: 157. Chinook spawning surveys 09/28/2012 09/28/2012
Estimate of adult spring Chinook salmon returns to the mouth of the Hood River. L: 157. Spring Chinook salmon preseason adult run size forecast. 04/27/2012 04/27/2012
Estimate tribal harvest of spring Chinook salmon in the Hood River. M: 157. Spring Chinook salmon tribal harvest monitoring 09/28/2012 09/28/2012
HRPP data uploaded to CTWS master database. N: 159. Consolidate HRPP data and upload into CTWS Tribal database. 09/28/2012 09/28/2012
2011 Final Report uploaded to Pisces (10/1/10 - 9/30/11) O: 132. Produce Annual Report for 10/1/10 - 9/30/11 09/28/2012 09/28/2012
Project administration & coordination complete P: 119. Manage Project 09/28/2012 09/28/2012

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 28 Trap and Haul
  • 1 instance of WE 70 Install Fish Monitoring Equipment
  • 7 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals
  • 2 instances of WE 159 Transfer/Consolidate Regionally Standardized Data
Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 28 Trap and Haul
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened)
  • 1 instance of WE 28 Trap and Haul
  • 1 instance of WE 70 Install Fish Monitoring Equipment
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals
  • 2 instances of WE 159 Transfer/Consolidate Regionally Standardized Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 10/01/2011
B 165 Ensure environmental compliance is adequate 10/01/2011
C 158 PIT tag hatchery steelhead and spring Chinook salmon 10/01/2011
D 157 Collect water temperature data in the Hood River subbasin 10/01/2011
E 157 Record stream flows in the Hood River basin. 10/01/2011
F 28 Salvage and transport fish entrained in irrigation canals to nearest free-flowing waterbody 10/01/2011
G 157 Conduct basin-wide juvenile spring Chinook distribution surveys. 10/01/2011
H 70 Install PIT receivers. 10/01/2011
I 157 Collect data during acclimation 10/01/2011
J 159 Input Hood River PIT tag data to appropriate databases 10/01/2011
K 157 Chinook spawning surveys 10/01/2011
L 157 Spring Chinook salmon preseason adult run size forecast. 10/01/2011
M 157 Spring Chinook salmon tribal harvest monitoring 10/01/2011
N 159 Consolidate HRPP data and upload into CTWS Tribal database. 10/01/2011
O 132 Produce Annual Report for 10/1/10 - 9/30/11 10/01/2011
P 119 Manage Project 10/01/2011