SOW Report
Contract 55061: 2002-072-00 EXP NPT RED RIVER WATERSHED RESTORATION
Project Number:
Title:
Red River/Newsome Creek Watershed Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
55061
Contract Title:
2002-072-00 EXP NPT RED RIVER WATERSHED RESTORATION
Contract Continuation:
Previous: Next:
45427: 200207200 EXP NPT RED RIVER WATERSHED RESTORATION
  • 63446: 2002-072-00 EXP NPT RED RIVER WATERSHED RESTORATION
Contract Status:
Closed
Contract Description:
Contract History:

This project began in 2002 and became part of the Nez Perce Tribe Fisheries Watershed Department’s habitat restoration program.  In 2002, the Red River Ecosystem Analysis at the Watershed Scale (EAWS) was completed.  While this was mainly a Forest Service effort, the NPT was involved in the transportation planning, and review of the entire document.  NPT field crews also surveyed approximately 100 miles of roads and 264 high priority culverts/stream crossings.  In 2003, the NEPA process was initiated on the Upper Red River Watershed Restoration Project which consists of road decommissioning, road improvements, one major culvert replacement, and campground improvements.  NEPA and ESA consultation were completed in 2004, as well as the engineering surveys for the road decommissioning and improvements.  

In 2005, the Bridge Creek Campground Improvements were implemented, and in 2006 - 2007 23 miles of roads were decommissioned, 9 miles of roads were improved, culvert 1709 was replaced, 15,200 riparian plants were planted along approximately 4 miles of the mainstem of Red River, and the Red River Meadow conservation easement pursuit began.  In 2008, approximately 5,000 riparian plants were planted along approximately 4 miles of the mainstem Red River, designs for five culvert replacements were completed (Deadwood, Siegel, Schooner, Deer, and Soda Creeks), and conservation easement activities continued - the appraisal was completed, partners were secured, and a PCSRF Idaho Office of Species Conservation grant awarded for $250,000 towards the purchase of the easement.  In 2009, the Red River Narrows Stream Restoration Project was implemented which consisted of 2 miles of mainstem Red River post dredge mine rehabilitation, mine tailings pile re-grading, stream channel reconstruction, and the installation of instream habitat complexity structures such as engineered log jams.  NPT personnel also planted approximately 4 miles of the riparian corridor (4,500 plants) of the mainstem of Red River, and continued conservation easement acquisition activities in the Red River Meadow.  

In 2010, the Red River Meadow conservation easement was purchased (256 acres), the Red River Narrows revegetation was completed, and revegetation efforts continued in the Red River Meadows.  NPT and NPNF personnel also completed the engineering surveys and design of the Deadwood Road Decommissioning/Improvement Project, and maintained the cattle exclusion fence on the Red River Meadow conservation easement property.  Project implementation/effectiveness monitoring and evaluation was completed for the Red River Narrows Stream Restoration Project, culvert replacements and removals, and road decommissioning and improvement.  In 2011, the Deadwood Road Decommissioning and Improvement was completed, revegetation efforts continued on the Red River Meadow easement and Red River Narrows, fence maintenance was implemented on the easement property, and project implementation/effectiveness monitoring and evaluation continued.  

This project has been, and is still currently a part of the BPA, Nez Perce Tribe, and Nez Perce National Forest Restoration Partnership.  Since the project’s inception we have shared project planning, funding, and implementation responsibilities.


Summary of FY 2012 & 2013 Contract Implementation:

In 2012 we will complete 3 culvert replacement designs, the large woody debris (LWD) and channel restoration design on the Red River Conservation Easement, and the design for another road decommissioning project in the South Fork Red River subwatershed.  Implementation will include the Siegel Creek culvert replacement, riparian planting on the Red River Meadow easement property (with expansion into Gibbler's property), and conducting additional low elevation aerial photography to aid in monitoring and maintenance of the projects.  In 2013 we will finish the design of the LWD and channel restoration project on the easement property.  2013 implementation will include replacement of the Bridge and Siegel Creek culverts, removal of up to 6 log culverts as identified in the Red Pines EIS, the South Fork Red River Road Decommissioning, and the continued pursuit of the acquisition of Siegel Creek from Red River Properties LLC.
Account Type(s):
Expense
Contract Start Date:
12/01/2011
Contract End Date:
11/30/2013
Current Contract Value:
$612,297
Expenditures:
$612,297

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Stephanie Bransford Nez Perce Tribe Yes Contract Manager stephanieb@nezperce.org (208) 983-0675
Michelle Guay Bonneville Power Administration Yes Env. Compliance Lead mxguay@bpa.gov (503) 230-3459
Arleen Henry Nez Perce Tribe No Administrative Contact arleenh@nezperce.org (208) 621-3833
David Kaplowe Bonneville Power Administration Yes COR djkaplowe@bpa.gov (503) 230-5365
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Amber MacLachlan Bonneville Power Administration Yes Contracting Officer almcmahon@bpa.gov (503) 230-3983
Heidi McRoberts Nez Perce Tribe No Supervisor heidim@nezperce.org (208) 621-3548
Michelle Roberts US Forest Service (USFS) Yes Technical Contact mmroberts@fs.fed.us (208) 983-4091
Scott Russell US Forest Service (USFS) No Technical Contact sarussell@fs.fed.us (208) 983-4092
Emmit Taylor, Jr. Nez Perce Tribe No Supervisor emmitt@nezperce.org (208) 621-3544


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental compliance documentation submitted to BPA A: 165. Submit environmental compliance documentation to BPA 11/30/2013 11/25/2013
Designs Complete B: 175. S. Fork Red River Decommissioning, RR Meadows LWD, and Culvert Designs 11/30/2013
Riparian re-vegetation complete C: 47. Plant Red River Meadows 11/30/2013 06/21/2013
Red River Narrows Plant Maintenance Completed D: 197. Red River Narrow Plant and Exclosure Maintenance 10/31/2013 08/30/2013
South Fork Red River road decommissioning complete E: 33. South Fork Red River Road Decommissioning 11/30/2013
Culvert replaced F: 184. Siegel Creek Culvert Replacement 09/30/2012
Bridge Creek Culvert Replacement Complete G: 184. Bridge Creek Culvert Replacement 08/31/2013
Red River Log Culvert Structure Removed H: 85. Red River Log Culvert Removal 11/30/2013 09/20/2013
Red River Log Culvert Structure Removed I: 85. Red River Log Culvert Removal 11/30/2013 09/20/2013
Red River Log Culvert Structure Removed J: 85. Red River Log Culvert Removal 11/30/2013 09/20/2013
Red River Log Culvert Structure Removed K: 85. Red River Log Culvert Removal 11/30/2013 09/20/2013
Red River Log Culvert Structure Removed L: 85. Red River Log Culvert Removal 11/30/2013 09/20/2013
Red River Log Culvert Structure Removed M: 85. Red River Log Culvert Removal 11/30/2013 09/20/2013
Red River Fence Maintained N: 186. Red River Meadows Fence Maintenance (Private Property) 11/30/2013 06/28/2013
Pre-acquisition actions completed O: 172. Siegel Creek Land Acquisition (100 acres) 12/28/2012
Decommissioned and Improved Roads Data Collected P: 157. Decommissioned/Improved Roads Data Collection 11/30/2013 11/25/2013
Culvert Data Collected Q: 157. Culvert and Bridge Replacement/Removal Data Collection 11/30/2013 11/25/2013
Stream Habitat Data Collected R: 157. Stream Habitat Data Collection 11/30/2013 11/25/2013
Data Analyzed and Reports Completed S: 162. Condition/Health of Red River 11/30/2013 11/25/2013
FY 2014 SOW package and FY 2012 & 2013 accrual estimates T: 119. Management, Coordination, and Communication 10/18/2013 10/18/2013
Final FY 2011 annual report attached to this contract U: 132. Submit Annual Report for 12/1/10 - 11/30/11 01/31/2012 12/31/2011
Final FY 2012 annual report attached to this contract V: 132. Submit Annual Report for 12/1/11 - 11/30/12 12/31/2012 12/31/2012
Final FY 2013 annual report attached to this contract W: 132. Submit Annual Report for 12/1/12 - 11/30/13 11/30/2013 11/25/2013
Soda Creek Tributary #1 Culvert (MP 2.1) Replaced Y: 184. Soda Creek Tributary #1 Culvert Replacement (MP 2.1) 08/31/2013

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 197 Maintain/Remove Vegetation
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 33 Decommission Road/Relocate Road
  • 1 instance of WE 47 Plant Vegetation
  • 6 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 3 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 197 Maintain/Remove Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 33 Decommission Road/Relocate Road
  • 1 instance of WE 47 Plant Vegetation
  • 6 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 3 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 175 Produce Design
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Submit environmental compliance documentation to BPA 12/01/2011
B 175 S. Fork Red River Decommissioning, RR Meadows LWD, and Culvert Designs 12/01/2011
C 47 Plant Red River Meadows 11/01/2006
D 197 Red River Narrow Plant and Exclosure Maintenance 12/01/2011
E 33 South Fork Red River Road Decommissioning 11/01/2006
F 184 Siegel Creek Culvert Replacement 11/01/2006
G 184 Bridge Creek Culvert Replacement 11/01/2006
H 85 Red River Log Culvert Removal 11/01/2006
I 85 Red River Log Culvert Removal 11/01/2006
J 85 Red River Log Culvert Removal 11/01/2006
K 85 Red River Log Culvert Removal 11/01/2006
L 85 Red River Log Culvert Removal 11/01/2006
M 85 Red River Log Culvert Removal 11/01/2006
N 186 Red River Meadows Fence Maintenance (Private Property) 12/01/2011
O 172 Siegel Creek Land Acquisition (100 acres) 12/01/2011
P 157 Decommissioned/Improved Roads Data Collection 12/01/2011
Q 157 Culvert and Bridge Replacement/Removal Data Collection 12/01/2011
R 157 Stream Habitat Data Collection 12/01/2011
S 162 Condition/Health of Red River 12/01/2011
T 119 Management, Coordination, and Communication 12/01/2011
U 132 Submit Annual Report for 12/1/10 - 11/30/11 12/01/2011
V 132 Submit Annual Report for 12/1/11 - 11/30/12 12/01/2011
W 132 Submit Annual Report for 12/1/12 - 11/30/13 12/01/2011
X 185 Periodic Status Reports for BPA 12/01/2011
Y 184 Soda Creek Tributary #1 Culvert Replacement (MP 2.1) 11/02/2006