Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 55600: 1998-007-04 EXP GRANDE RONDE SP CHINOOK-ODFW
Project Number:
Title:
Grande Ronde Spring Chinook on Lostine/Catherine Creek/ Upper Grande Ronde Rivers
BPA PM:
Stage:
Closed
Area:
Province Subbasin %
Blue Mountain Grande Ronde 100.00%
Contract Number:
55600
Contract Title:
1998-007-04 EXP GRANDE RONDE SP CHINOOK-ODFW
Contract Continuation:
Previous: Next:
51033: 1998-007-04 EXP GRANDE RONDE SP CHINOOK-ODF&W
  • 60326: 1998-007-04 EXP GRANDE RONDE SPRING CHINOOK-ODF&W
Contract Status:
Closed
Contract Description:
The Grande Ronde endemic spring Chinook (GRESCP) artificial production is authorized under the US Fish and Wildlife Lower Snake River Compensation Program (LSRCP).  LSRCP program was approved by the Water Resources Development Act of 1976 (PL 94-587, Section 102) to mitigate for the losses of fish and wildlife caused by the construction of dams on lower Snake River.

This contract supplements the LSRCP operations to adjust the program to supplementation and mitigation objectives in the Grande Ronde subbasin.
Account Type(s):
Expense
Contract Start Date:
01/01/2012
Contract End Date:
12/31/2012
Current Contract Value:
$188,484
Expenditures:
$188,484

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
HGMP submittal authorization A: 165. Obtain Permits and Submit Copies to BPA NEPA Group 12/31/2012 12/31/2012
2012 AOP B: 174. Produce 2012 Annual Operating plan 03/31/2012 03/31/2012
Count spring Chinook Redds in Grande Ronde and Imnaha sub-basin C: 157. Collect Field Data (Spring Chinook Redds) 11/15/2012 11/15/2012
Spawn adults and Incubate eggs from the Lostine River D: 176. Spawn and incubate spring Chinook eggs from the Lostine River 12/31/2012 12/31/2012
Spawn and incubate spring Chinook eggs from Catherine Creek E: 176. Spawn and incubate spring Chinook eggs from Catherine Creek 12/31/2012 12/31/2012
Spawn and incubate spring Chinook eggs from the Upper Grande Ronde River F: 176. Spawn and incubate spring Chinook eggs from the Upper Grande Ronde River 12/31/2012 12/24/2012
Monitor Fish Health G: 60. Monitor Fish Health 12/31/2012 12/31/2012
2011 Progress report H: 132. Submit Progress Report for the period 1/2/2011 to 12/31/2011 03/16/2012 03/16/2012
Manage and Administer projects I: 119. Manage and Administer Spring Chinook 10/01/2012 10/01/2012

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 3 instances of WE 176 Produce Hatchery Fish
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 60 Maintain Fish Health

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain Permits and Submit Copies to BPA NEPA Group 01/01/2012
B 174 Produce 2012 Annual Operating plan 01/01/2012
C 157 Collect Field Data (Spring Chinook Redds) 01/01/2012
D 176 Spawn and incubate spring Chinook eggs from the Lostine River 01/01/2012
E 176 Spawn and incubate spring Chinook eggs from Catherine Creek 01/01/2012
F 176 Spawn and incubate spring Chinook eggs from the Upper Grande Ronde River 01/01/2012
G 60 Monitor Fish Health 01/01/2012
H 132 Submit Progress Report for the period 1/2/2011 to 12/31/2011 01/01/2012
I 119 Manage and Administer Spring Chinook 01/01/2012
J 185 Periodic Status Reports for BPA 01/01/2012