Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 56226: 2000-031-00 EXP N FORK JOHN DAY FISH HABITAT ENHANCEMENT
Project Number:
Title:
Enhance Habitat in the North Fork John Day River
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau John Day 100.00%
Contract Number:
56226
Contract Title:
2000-031-00 EXP N FORK JOHN DAY FISH HABITAT ENHANCEMENT
Contract Continuation:
Previous: Next:
51701: 200003100 EXP N FORK JOHN DAY FISH HABITAT ENHANCEMENT
  • 60597: 2000-031-00 EXP N FORK JOHN DAY FISH HABITAT ENHANCEMENT
Contract Status:
Closed
Contract Description:
Contract History: The purpose of this project is to protect and enhance habitat for improved natural production of indigenous, Mid-Columbia River (MCR) Evolutionary Significant Unit (ESU) summer steelhead (Oncorhynchus mykiss), listed as threatened under the Federal Endangered Species Act (ESA), and spring Chinook salmon (Oncorhynchus tshawytscha) within the North Fork of the John Day River Basin. The project entails coordinated, cooperative efforts to protect and improve anadromous fisheries habitat consistent with the strategies and objectives outlined in the John Day Subbasin Plan.

This project originated in 2000 with initial on-the-ground implementations occurring in 2001. These projects were implemented within lower Camas Creek tributaries (Snipe and Owens Creeks), Deer Creek and the Lower North Fork John Day River. Approximately 16.8 miles of riparian fencing and 20 off-stream water developments have been constructed and two wells reactivated under the project. These improvements have resulted in enhancement of approximately ten stream miles and 708 acres of riparian and floodplain habitat on private properties.

To date, all projects have included cost share funding and/or in-kind assistance from various sources including the Confederated Tribes of the Umatilla Indian Reservation (CTUIR), U.S. Department of Agriculture' s (USDA) Wildlife Habitat Incentive and Conservation Reserve Enhancement Programs (WHIP and CREP), U.S. Bureau of Indian Affairs (BIA), U.S. Army Corps of Engineers (COE), National Oceanic and Atmospheric Administration's (NOAA) Pacific Coastal Salmon Recovery Fund (PCSRF), North Fork John Day Watershed Council (NFJDWC), Oregon Watershed Enhancement Board (OWEB), U.S. Fish & Wildlife (USFWS) Partners for Wildlife Program, Umatilla National Forest (UNF), Community Action Program of East Central Oregon (CAPECO), and Columbia Power Cooperative Association. The project has also partnered with other entities, including the UNF and Grant Soil and Water Conservation District (SWCD) to assist them in obtaining NOAA cost share and habitat recovery on additional North and Middle Fork John Day tributaries. These efforts have resulted in further enhancement of approximately 2.7 stream miles and 97 acres of floodplain and upland habitat.  Upland fencing associated with this project will be financed by these cost share entities since BPA is reluctant to approve funding for this purpose.

Summary of 2012-2013 Contract Work: Implementation during this project cycle shall include: (1) produce status reports, (2) produce weed control documentation, (3) identify and prioritize passive and active habitat enhancement projects for the 2013 performance period within the Lower Camas, Upper Camas, Desolation and Granite Creeks Geographic Areas (GA's), (4) outreach and education,  (5) maintain water developments for easements on Lower and Upper Camas Creek, Snipe Creek, Deer Creek, and NF John Day, (6) investigate livestock trespass for easements on Lower and Upper Camas Creek, Snipe Creek, Deer Creek, and NF John Day, (7) maintain fences for easements on Lower and Upper Camas Creek, Snipe Creek, Deer Creek, and NF John Day, (8) Maintain vegetation for easements on Lower and Upper Camas Creek, Snipe Creek, Deer Creek, and NF John Day, (9) Collect monitoring data to establish baseline conditions and tract project success, (10) acquire stream temperature data and pass on to NOAA, (11)  replace the Ten Cent Creek culvert 1, (12) replace the Ten Cent Creek culvert 2, (13) replace the Ten Cent Creek culvert 3, (14) control Leafy Spurge on Fox Creek, (15) replace a pipeline for the Red Boy Mine, (16) Fox Creek Channel Realignment, (17) Butcherknife Creek Fence Construction, (18) construct the Desolation Creek Fence, (19) make & install the Red Boy Sign, (20) produce the Camas Road Stabilization Design, (21) 5 Mile Fence Maintenance, (22) produce the 1020 Annual Report, (23) produce project deliverables, (24)  implement in-stream restoration efforts along 0.8 mile of Camas Creek.  These projects include partnerships and cost share with the Natural Resources Conservation Service (NRCS), Farm Services Agency (FSA), U.S. Bureau of Reclamation (BOR), NOAA, NFJDWC and potentially OWEB.

CTUIR is aware of a region wide programmatic MOU between BPA and the USFS requiring a 30% USFS cost share for projects on USFS lands.
Account Type(s):
Expense
Contract Start Date:
02/01/2012
Contract End Date:
01/31/2013
Current Contract Value:
$678,436
Expenditures:
$678,436

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Produce Weed Control Compliance Documentation A: 165. Produce Weed Control Compliance Documentation 01/31/2013 01/31/2013
Identify, Prioritize and Select Habitat Project Areas B: 114. Identify, Prioritize and Select Habitat Project Areas 11/05/2012 11/05/2012
Provide Local Community-Based Outreach and Education C: 99. Provide Outreach and Education 01/31/2013 01/31/2013
Maintain Water Developments D: 186. Maintain Water Developments 01/31/2013 01/31/2013
Investigate for Livestock Trespass E: 26. Investigate for Livestock Trespass 01/31/2013 01/31/2013
Maintain Fences F: 186. Maintain Fences 01/31/2013 01/31/2013
Maintain Vegetation G: 197. Maintain Vegetation 01/31/2013 01/31/2013
Collect Data to Monitor Project Effectiveness and temperatures H: 157. Collect Monitoring Data 01/31/2013 01/31/2013
Acquire and Submit Stream Temperature Data to NOAA I: 157. Acquire Stream Temperature Data 01/31/2013 01/31/2013
Lower Ten Cent Creek Culvert Replacement J: 184. Lower Ten Cent Creek Culvert Replacement 09/14/2012 09/14/2012
Middle Ten Cent Creek Culvert Replacement K: 184. Middle Ten Cent Creek Culvert Replacement 09/14/2012 09/14/2012
Upper Ten Cent Creek Culvert Replacement L: 184. Upper Ten Cent Creek Culvert Replacement 09/14/2012 09/14/2012
Fox/Cottonwood Creek Leafy Spurge Control M: 197. Fox/Cottonwood Creek Leafy Spurge Control 12/03/2012 12/03/2012
Red Boy Mine Pipeline Replacement N: 98. Red Boy Mine Pipeline Replacement 12/31/2012
Fox Creek Channel Realignment O: 29. Fox Creek Channel Realignment 10/15/2012 08/15/2012
Butcherknife Creek Fence Construction P: 40. Butcherknife Creek Fence Construction 12/31/2012 12/31/2012
Red Boy Sign R: 99. Red Boy Sign 01/31/2013 01/31/2013
Camas Road Stabilization Design S: 175. Camas Road Stabilization Design 01/31/2013
5 Mile Fence Maintenance T: 186. 5 Mile Fence Maintenance 12/31/2012 12/31/2012
Upper Camas Creek In-stream Implementation U: 29. Upper Camas Creek In-stream Implementation 09/14/2012
Final report uploaded to the BPA website V: 132. Submit Annual Report (1 February 11 - 31 January 12) 01/31/2013 01/31/2013
Funding Package - Submit draft to COTR W: 119. Produce Project Deliverables 01/31/2013 01/31/2013
RPB Fence Z: 40. RPB Fence 01/15/2013
CTUIR Monitoring Plan Development AA: 156. CTUIR Monitoring Plan Development 01/31/2013

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 26 Investigate Trespass
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 34 Develop Alternative Water Source
  • 3 instances of WE 40 Install Fence
  • 2 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 98 Other
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 175 Produce Design
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 2 instances of WE 197 Maintain/Remove Vegetation
  • 1 instance of WE 26 Investigate Trespass
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 34 Develop Alternative Water Source
  • 4 instances of WE 40 Install Fence
  • 2 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 98 Other
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 175 Produce Design
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 40 Install Fence
  • 2 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 98 Other
  • 1 instance of WE 114 Identify and Select Projects
Trout, Rainbow (Oncorhynchus mykiss)
  • 2 instances of WE 197 Maintain/Remove Vegetation
  • 1 instance of WE 26 Investigate Trespass
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 34 Develop Alternative Water Source
  • 2 instances of WE 40 Install Fence
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 175 Produce Design
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Trout, Interior Redband (O. mykiss gairdnerii)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 114 Identify and Select Projects

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Produce Weed Control Compliance Documentation 02/01/2012
B 114 Identify, Prioritize and Select Habitat Project Areas 02/01/2012
C 99 Provide Outreach and Education 02/01/2012
D 186 Maintain Water Developments 02/01/2012
E 26 Investigate for Livestock Trespass 02/01/2012
F 186 Maintain Fences 02/01/2012
G 197 Maintain Vegetation 03/22/2012
H 157 Collect Monitoring Data 03/22/2012
I 157 Acquire Stream Temperature Data 03/22/2012
J 184 Lower Ten Cent Creek Culvert Replacement 04/20/2012
K 184 Middle Ten Cent Creek Culvert Replacement 04/20/2012
L 184 Upper Ten Cent Creek Culvert Replacement 04/20/2012
M 197 Fox/Cottonwood Creek Leafy Spurge Control 03/22/2012
N 98 Red Boy Mine Pipeline Replacement 02/01/2012
O 29 Fox Creek Channel Realignment 03/21/2012
P 40 Butcherknife Creek Fence Construction 03/21/2012
Q 40 Desolation Creek Fence
R 99 Red Boy Sign 02/01/2012
S 175 Camas Road Stabilization Design 02/01/2012
T 186 5 Mile Fence Maintenance 02/14/2012
U 29 Upper Camas Creek In-stream Implementation 02/01/2012
V 132 Submit Annual Report (1 February 11 - 31 January 12) 02/01/2012
W 119 Produce Project Deliverables 02/01/2012
X 185 Periodic Status Reports for BPA 02/01/2012
Y 40 Mud Creek Fence
Z 40 RPB Fence 02/01/2012
AA 156 CTUIR Monitoring Plan Development 02/01/2012
AB 34 Upper Camas Stock Water Development Improvement