Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 56348: 1996-046-01 EXP WALLA WALLA BASIN FISH HABITAT ENHANCEMENT
Project Number:
Title:
Walla Walla River Basin Fish Habitat Enhancement
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Walla Walla 100.00%
Contract Number:
56348
Contract Title:
1996-046-01 EXP WALLA WALLA BASIN FISH HABITAT ENHANCEMENT
Contract Continuation:
Previous: Next:
53046: 1996-046-01 EXP WALLA WALLA BASIN FISH HABITAT ENHANCEMENT
  • 61253: 1996-046-01 EXP WALLA WALLA BASIN FISH HABITAT ENHANCEMENT
Contract Status:
Closed
Contract Description:
The CTUIR Walla Walla River Basin Fish Habitat Enhancement Project, initiated in 1996, is an ongoing effort to monitor, protect, enhance, and restore the natural form and function of rivers, floodplains, and native fish habitat.

Major tasks to be completed by the project in this funding cycle include:  

1. Hire a consultant to complete the restoration and design plan for approximately one mile of the mainstem Walla Walla River at the Kentch Property. The subcontract budget for this work will added after bids are in and will be followed by construction in 2014.

2. Coordinate with the Walla Walla Basin Watershed Council in the design of a passage barrier fix at the Smith sill drop-structure on the mainstem Walla Walla River. The project will be providing $10,000 in cost share for this work.

3. Replace an undersized culvert that is currently a passage barrier on Couse Creek near the Konen Rock Pit with a box culvert/bridge.  The subcontract budget for this work will added after bids are in.

4. Continue noxious weed control measures as needed along approximately 10 stream miles of project areas.  

5. Collect and analyze project effectiveness monitoring data within a portion of the project areas.

6. Meet with private landowners, scope and develop conceptual plans for out-year restoration work with priority reaches of the basin.

7. Continue to provide technical support and coordination within the Mill Creek Working Group, Priority Projects Group, Snake River Recovery Board, Oregon Solutions Process, and others as needed.
Account Type(s):
Expense
Contract Start Date:
02/01/2012
Contract End Date:
01/31/2013
Current Contract Value:
$1,034,794
Expenditures:
$1,034,794

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Projects identified for out-years B: 114. Identify and select projects in Walla Walla Basin 08/31/2012 07/30/2012
All project admin activities managed C: 119. Conduct all management activities 01/31/2013 01/31/2011
Environmental compliance complete D: 165. Compliance for on-the-ground work 08/31/2012 06/30/2012
Provide technical support through interagency coordination and public forum E: 122. Provide technical support 01/31/2013 01/31/2013
Final Kentch Site Assessment & Design uploaded to Pisces F: 175. Develop final site assessment and restoration plan at Kentch 10/31/2012
Maintenance of reintroduced native plants and control of noxious weeds G: 197. Control noxious weeds and replant native vegetation within project areas 01/31/2013 12/31/2012
Fences maintained at full functionality H: 186. Maintain Fences 01/31/2013 01/31/2013
Project effectiveness data collection complete I: 157. Field Data Collection 01/31/2013 01/31/2013
Data analysis complete J: 162. Project Monitoring Data Analysis 01/31/2013 01/31/2013
Annual report of progress uploaded to Pisces K: 132. Submit Progress Report for the period 2/1/2010 to 1/31/2012 08/31/2012 01/31/2013
Culvert Replaced on Couse Creek L: 85. Couse Creek Culvert Replacement 10/15/2012 10/15/2012
Passage barrier removed M: 85. Modify Smith Sill on mainstem Walla Walla River 10/31/2012 10/31/2012
Recently planted trees & shrubs at Lampson project site maintained N: 197. Maintain riparian vegetation at Lampsons 11/30/2012 11/30/2012
LWD purchased and stored at Couse Creek O: 29. Stockpile LWD on Couse Creek 11/30/2012 11/30/2012

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 2 instances of WE 197 Maintain/Remove Vegetation
  • 1 instance of WE 114 Identify and Select Projects
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 2 instances of WE 197 Maintain/Remove Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 162 Analyze/Interpret Data
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 162 Analyze/Interpret Data
Trout, Rainbow (Oncorhynchus mykiss)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 02/01/2012
B 114 Identify and select projects in Walla Walla Basin 02/01/2012
C 119 Conduct all management activities 02/01/2012
D 165 Compliance for on-the-ground work 02/01/2012
E 122 Provide technical support 02/01/2012
F 175 Develop final site assessment and restoration plan at Kentch 02/01/2012
G 197 Control noxious weeds and replant native vegetation within project areas 02/17/2012
H 186 Maintain Fences 02/01/2012
I 157 Field Data Collection 02/01/2012
J 162 Project Monitoring Data Analysis 02/01/2012
K 132 Submit Progress Report for the period 2/1/2010 to 1/31/2012 02/01/2012
L 85 Couse Creek Culvert Replacement 05/15/2012
M 85 Modify Smith Sill on mainstem Walla Walla River 09/04/2012
N 197 Maintain riparian vegetation at Lampsons 02/01/2012
O 29 Stockpile LWD on Couse Creek 10/11/2012