Contract 60479: 1995-057-02 EXP SHOSHONE-BANNOCK WILDLIFE MITIGATION
Project Number:
Title:
Shoshone-Bannock Wildlife Mitigation Projects
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Upper Snake Snake Upper 100.00%
Contract Number:
60479
Contract Title:
1995-057-02 EXP SHOSHONE-BANNOCK WILDLIFE MITIGATION
Contract Continuation:
Previous: Next:
54764: 1995-057-02 EXP SHOSHONE-BANNOCK WILDLIFE MITIGATION
  • 63492: 1995-057-02 EXP SBT IDAHO WILDLIFE MITIGATION
Contract Status:
Closed
Contract Description:
This contract is a continuation of the Shoshone-Bannock Tribes (SBT) SIWM program.  Under this contract the SBT-SIWM program will continue to acquire properties to mitigate for hydropower development.  In addition, under this contract SBT will maintain and restore the five mitigation properties mitigation properties over which it has management responsibility; Rudeen Ranch and Soda Springs Hills acquired in the late 1990's; Bannock Creek acquired in 2009; and Lavaside and Legacy Springs acquired in 2011. Management entails Operations and Management (O+M) to maintain and enhance acquired lands, monitoring habitat and wildlife populations to allow for adaptive management, and collaboration with other wildlife management entities to protect wildlife habitats and populations both on acquired lands and in southern Idaho as a whole.  

Goals of the SBT-SWIM Program under this contract include:

Acquisition of additional mitigation properties
Completion of a Programmatic Management Plan
Land Management Plans for Legacy Springs and Bannock Creek Properties
Completion of annual reports
Outlines for Management Plans for Lavaside, Rudeen, and Soda Hills Properties for plans to be completed in FY14
Vegetation restoration efforts at Legacy Springs and Bannock Creek properties.
Weed control on all project lands
Maintenance of infrastructure on all project lands
Management of agricultural leases at Legacy Springs and Lavaside properties
Public access management on project lands
Account Type(s):
Expense
Contract Start Date:
12/01/2012
Contract End Date:
11/30/2013
Current Contract Value:
$387,857
Expenditures:
$387,857

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Chad Colter Shoshone-Bannock Tribes Yes Supervisor ccolter@sbtribes.com (208) 239-4553
Joe Deherrera Bonneville Power Administration Yes COR jldeherrera@bpa.gov (503) 230-3442
Aren Eddingsaas Shoshone-Bannock Tribes Yes Contract Manager aeddingsaas.sbtribes@gmail.com (208) 239-4577
Jacee Furniss Shoshone-Bannock Tribes No Administrative Contact jfurniss@sbtribes.com (208) 239-4551
Steve Hagler Shoshone-Bannock Tribes No Administrative Contact shagler@sbtribes.com (208) 478-3843
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Jennifer Lord Bonneville Power Administration Yes Env. Compliance Lead jklord@bpa.gov (503) 230-5192
Daniel Stone Shoshone-Bannock Tribes No Interested Party dstone@sbtribes.com (208) 239-4555
Gaylene Turnage Shoshone-Bannock Tribes No Administrative Contact gturnage@sbtribes.com (208) 478-3821
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Shannell Ward Shoshone-Bannock Tribes No Administrative Contact shannell.ward@sbtribes.com (208) 478-3821
Pam Waterhouse Shoshone-Bannock Tribes No Administrative Contact pwaterhouse@sbtribes.com (208) 478-3819


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Receipt of EC documentation/clearance from BPA A: 165. Satisfy environmental compliance requirements 11/30/2013 11/30/2013
Coordinate project lands management with relevant land agencies B: 191. Coordinate project lands management with relevant land agencies 11/30/2013 11/30/2013
Identify potential mitigation properties C: 114. Identify potential mitigation properties 11/30/2013 11/30/2013
Conduct pre-acquisition activities D: 172. Conduct pre-acquisition activities 11/30/2013 11/30/2013
Produce management plan- Programmatic E: 174. Produce management plan- Programmatic 11/29/2013
Produce management plan- Legacy Springs F: 174. Produce management plan- Legacy Springs 11/29/2013
Produce management plan- Bannock Creek G: 174. Produce management plan- Bannock Creek 11/29/2013
Produce management plan draft H: 174. Produce management plan Draft- Lavaside 11/29/2013
Produce management plan draft I: 174. Produce management plan Draft- Rudeen 11/29/2013
Produce management plan draft J: 174. Produce management plan Draft- Soda Hills 11/29/2013
Implement plan to replant Rudeen ag lands to wildlife friendly vegetation K: 47. Plant Vegetation- Bannock Creek ag lands 11/29/2013
Develop and implement Legacy Springs vegetation restoration efforts. L: 47. Plant Vegetation- Legacy Springs 11/29/2013
Herbicide weed control M: 197. Herbicide weed control 11/30/2013 11/30/2013
Remove debris from project lands. N: 27. Remove Debris 11/29/2013 11/29/2013
Maintain program infrastructure O: 186. Maintain program infrastructure 11/29/2013 11/29/2013
Lease agricultural lands- Legacy Springs P: 194. Administer agricultural Lease- Legacy Springs 11/29/2013 11/29/2013
Lease agricultural lands- Lavaside Q: 194. Administer agricultural Lease- Lavaside 11/29/2013 11/29/2013
Develop, install, and maintain public access information R: 188. Provide public access information 11/29/2013 11/29/2013
Attach Progress Report in Pisces S: 132. Submit Progress Report for the period FY2006 thru FY2010 08/31/2013
Attach Progress Report in Pisces T: 132. Submit Progress Report for the period FY2011 11/01/2013
Attach Progress Report in Pisces U: 132. Submit Progress Report for the period FY2012 11/01/2013
Fulfill all administrative tasks with quality products and in a timely manner. X: 119. Administration of BPA contracts 11/30/2013 11/30/2013
Aerial imagery acquisition, manipulation, and assessment Y: 115. Aerial imagery acquisition, manipulation, and assessment 11/30/2013 11/30/2013

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Wildlife
  • 1 instance of WE 197 Maintain/Remove Vegetation
  • 1 instance of WE 27 Remove Debris
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 47 Plant Vegetation
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 6 instances of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Satisfy environmental compliance requirements 10/01/2012
B 191 Coordinate project lands management with relevant land agencies 10/01/2012
C 114 Identify potential mitigation properties 10/01/2012
D 172 Conduct pre-acquisition activities 10/01/2012
E 174 Produce management plan- Programmatic 12/01/2012
F 174 Produce management plan- Legacy Springs 12/01/2012
G 174 Produce management plan- Bannock Creek 12/01/2012
H 174 Produce management plan Draft- Lavaside 12/01/2012
I 174 Produce management plan Draft- Rudeen 12/01/2012
J 174 Produce management plan Draft- Soda Hills 12/01/2012
K 47 Plant Vegetation- Bannock Creek ag lands 01/29/2013
L 47 Plant Vegetation- Legacy Springs 02/25/2013
M 197 Herbicide weed control 12/01/2012
N 27 Remove Debris 12/01/2012
O 186 Maintain program infrastructure 12/01/2012
P 194 Administer agricultural Lease- Legacy Springs 01/29/2013
Q 194 Administer agricultural Lease- Lavaside 01/29/2013
R 188 Provide public access information 06/24/2013
S 132 Submit Progress Report for the period FY2006 thru FY2010 10/01/2012
T 132 Submit Progress Report for the period FY2011 12/01/2012
U 132 Submit Progress Report for the period FY2012 12/01/2012
V 132 Progress Report for this performance period to be submitted in FY14 12/01/2012
W 185 Periodic Status Reports for BPA 10/01/2012
X 119 Administration of BPA contracts 10/01/2012
Y 115 Aerial imagery acquisition, manipulation, and assessment 12/01/2012