Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 60916: 1988-053-01 EXP NORTHEAST OREGON HATCHERY PROJECT
Project Number:
Title:
Northeast Oregon Hatchery Master Plan
Stage:
Complete
Area:
Province Subbasin %
Blue Mountain Grande Ronde 100.00%
Contract Number:
60916
Contract Title:
1988-053-01 EXP NORTHEAST OREGON HATCHERY PROJECT
Contract Continuation:
Previous: Next:
22098: 1988-053-01 NORTHEAST OREGON HATCHERY PROJECT
  • 64664: 1988-053-01 EXP NORTHEAST OREGON HATCHERY PROJECT
Contract Status:
Closed
Contract Description:
The Bonneville Power Administration (BPA) has requested that HDR provide a scope and budget for anticipated services associated with on-going environmental compliance tasks related to the Northeast Oregon Hatchery Project (NEOH).  Over the past 7 years, BPA has annually extended HDR’s current contract (22098) along with the contract balance.  The funds associated with the existing contract were capital funds, which are typically allotted for projects valued at $1M or greater, with an operational life span of at least 15-years (e.g., hatcheries, weirs, fish screens, etc.).  BPA has recently decided that they will issue a new contract to HDR for work to be completed in 2013.  This would facilitate the expensing of funds related to 2013 tasks under a new contract in lieu of expensing them under the capitalized category.  If construction at the Lostine Hatchery site commences, BPA would shift the funding back to capital funds, and amend this contract, or issue a new one.  

Remaining NEOH project tasks are relatively minimal, and primarily associated with maintenance of existing environmental authorizations previously issued for this project.

Task 1. Environmental Compliance Documentation and Support

a. As necessary, discussions with Corps, DEQ and DSL regarding extensions of CWA 404 and 401 authorizations, and the state-removal fill permit for instream work at the Lostine Hatchery site.
b. Support for BPA regarding these authorizations, primarily in the form of discussions over the phone and preparation of emails to the agencies
c. No deliverables are anticipated to be required for this task.

Task 2. Coordination and Assistance with On-going Documentation and Project History, including Design

a. Provide support to BPA regarding project history and design details as BPA management continues to decide on the potential funding of the Lostine Hatchery.
b. No deliverables are anticipated to be required for this task.

Task 3. Produce Pisces Status Report

a. Produce quarterly status reports as required by Pisces

Task 4. Project Management
a. Monthly invoicing, discussions with BPA on project status


Assumptions
1. No site visits to any of the NEOH facilities are included in this scope for 2013.
2. With the exception of general discussions (see Task 2) relative to the design of the facilities, no design tasks (i.e., preparation of new designs, participation in design charettes, or modifications to designs or drawings) are included in this scope of work.  Any requested work related to design modifications would be require a scope amendment.
3. No deliverables are anticipated to be required under this task, with the exception of emails requested by BPA relative to agency coordination.  No environmental compliance documents, permit applications, technical reports, or modifications to existing documentation are anticipated to be required.
4. This scope does not include any participation in public meetings or updates to recently expired Wallowa County permits.  Any work associated with obtaining new county permits, if desired by BPA, would require a scope amendment.
5. Because the USFWS is actively pursuing modifications to the Imnaha Satellite Facility weir, and will be applying for new permits to complete the work during the summer/fall of 2013, it is assumed that any remaining BPA-funded tasks (i.e., the proposed intake modifications), would require updated authorizations.  However, the preparation of any such applications or permitting documents (e.g., Joint Permit Application, ESA compliance documents) is not included in this scope of work.  Any work related to permitting of remaining instream work elements at the Imnaha Satellite Facility (i.e., intake modifications) would require a scope amendment.
Account Type(s):
Expense
Contract Start Date:
04/01/2013
Contract End Date:
03/31/2014
Current Contract Value:
$3,418
Expenditures:
$3,418

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Time and Materials
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Katey Grange Bonneville Power Administration Yes Env. Compliance Lead kcgrange@bpa.gov (503) 230-4047
Becky Holloway HDR Engineering, Inc. Yes Supervisor becky.holloway@hdrinc.com (425) 263-9111
Sherry Jeffery HDR Engineering, Inc. Yes Contract Manager sherry.jeffery@hdrinc.com (253) 858-5262
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Jonathan McCloud Bonneville Power Administration Yes COR jmmccloud@bpa.gov (503) 230-3110
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Gregory (HDR) Wolfe HDR Engineering, Inc. No Interested Party gregory.wolfe@hdrinc.com (509) 546-2071


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Permits/Authorizations Acquired A: 165. Update and Maintain NEOH Permits 03/31/2014 03/26/2014
Support BPA in NEOH Project history including design of facilities B: 191. Coordination & Assistance with on-going Documentation & Project History including NEOH Design 03/31/2014 03/26/2014
New SOW/Budget & management of contract D: 119. Manage Project and Subconsultants 02/01/2014 03/26/2014

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Update and Maintain NEOH Permits 04/01/2013
B 191 Coordination & Assistance with on-going Documentation & Project History including NEOH Design 04/01/2013
C 132 An Annual Progres Report is not required under this Contract 04/01/2013
D 119 Manage Project and Subconsultants 04/01/2013
E 185 Periodic Status Reports for BPA 04/01/2013