Contract 63451: 2007-402-00 EXP SHO BAN SNAKE RIVER SOCKEYE HABITAT
Project Number:
Title:
Snake River Sockeye Captive Propagation
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
63451
Contract Title:
2007-402-00 EXP SHO BAN SNAKE RIVER SOCKEYE HABITAT
Contract Continuation:
Previous: Next:
60302: 2007-402-00 EXP SHO BAN SNAKE RIVER SOCKEYE HABITAT
  • 67494: 2007-402-00 EXP SHO BAN SNAKE RIVER SOCKEYE HABITAT
Contract Status:
Closed
Contract Description:
Goal:  To assess habitat limitations as it pertains to Snake River sockeye salmon Oncorhynchus nerka preservation and recovery, to implement activities necessary to increase and\or reestablish O. nerka productivity in nursery areas in the historic range of Snake River sockeye salmon, and to investigate fish community dynamics in lake nursery areas, including interactions between resident and anadromous O. nerka in present or potential Sawtooth Valley production areas.  We will collaborate with the IDFG to determine release strategies, and assess fish performance from introduction into the lakes up through smolt migration.

Project objectives include: 1) monitor limnological parameters of the Sawtooth Valley lakes to assess lake productivity; 2) monitor sockeye salmon smolt migration from the production of wild/natural adults in Pettit and Alturas lakes;  3) monitor the number of mature kokanee spawning in Fishhook Creek and estimate fry recruitment in Fishhook and Alturas Lake creeks; 4) conduct sockeye and kokanee salmon population surveys; 5) evaluate potential competition and predation between stocked juvenile sockeye salmon and a variety of fish species in Pettit, and Alturas lakes; and 6) assist IDFG with captive broodstock production activities.
Account Type(s):
Expense
Contract Start Date:
12/01/2013
Contract End Date:
11/30/2014
Current Contract Value:
$547,281
Expenditures:
$547,281

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Chad Colter Shoshone-Bannock Tribes No Supervisor ccolter@sbtribes.com (208) 239-4553
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Jonathan McCloud Bonneville Power Administration Yes COR jmmccloud@bpa.gov (503) 230-3110
Jenna Peterson Bonneville Power Administration Yes Env. Compliance Lead jepeterson@bpa.gov (503) 230-3018
Doug Taki Shoshone-Bannock Tribes Yes Contract Manager dtaki@sbtribes.com (208) 239-4568
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Shannell Ward Shoshone-Bannock Tribes No Interested Party shannell.ward@sbtribes.com (208) 478-3821
Pam Waterhouse Shoshone-Bannock Tribes No Administrative Contact pwaterhouse@sbtribes.com (208) 478-3819


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
NEPA compliance, NOAA and IDEQ permit reports submitted A: 165. NEPA clearance, NOAA/DEQ Permits 11/28/2014 11/28/2014
Complete collection of all limnological variables B: 157. Complete data collection for all limnological variables 11/28/2014 11/13/2014
Evaluate sockeye salmon smolt migrations C: 157. Evaluate sockeye salmon smolt migration from Pettit and Alturas lakes 07/08/2014 07/08/2014
PIT Tag sockeye smolts D: 158. PIT Tag sockeye salmon smolts 06/14/2014 05/24/2014
Complete all adult spawning and hydroacoustic surveys E: 157. Estimate O. nerka populations in three Sawtooth Valley lakes 11/22/2014 11/04/2014
Complete all milestones F: 162. Provide recommendations on lake fertilization and fish stocking 11/30/2014 11/28/2014
Fertilization of selected lakes G: 44. Nutrient Enhancement 10/31/2014 10/23/2014
Attend and Participate in TOC meetings H: 189. Regional Coordination 11/29/2014 11/19/2014
Attach Progress Report in Pisces K: 132. Submit Progress Report for the period 1.01.2013 to 12.31.2013 10/31/2014 11/17/2014
Contract package (SOW, budget and property inventory) L: 119. Preparation of FY15 Pisces SOW 09/13/2014 09/12/2014
Pre-Feasibility Report on Pettit Lake Creek and Alturas Lake Stream adult weirs N: 115. Develop pre-feasibility report of adult weirs on Pettit Lake Creek and Alturas Lake Stream 10/31/2014 10/31/2014
Analysis of Isotopic and Geochemical sediments O: 162. Isotopic and geochemical analyses 11/30/2014 11/28/2014

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Sockeye (O. nerka) - Snake River ESU (Endangered)
  • 1 instance of WE 44 Enhance Nutrients in Water Bodies
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals
  • 2 instances of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 NEPA clearance, NOAA/DEQ Permits 12/01/2013
B 157 Complete data collection for all limnological variables 10/16/2013
C 157 Evaluate sockeye salmon smolt migration from Pettit and Alturas lakes 12/31/2016
D 158 PIT Tag sockeye salmon smolts 10/17/2013
E 157 Estimate O. nerka populations in three Sawtooth Valley lakes 10/17/2013
F 162 Provide recommendations on lake fertilization and fish stocking 12/01/2013
G 44 Nutrient Enhancement 10/17/2013
H 189 Regional Coordination 12/01/2013
I 132 Submit Progress Report for the period 1.01.2011 to 12.31.2011 12/01/2013
J 132 Submit Progress Report for the period 1.01.2012 to 12.31.2012 12/01/2013
K 132 Submit Progress Report for the period 1.01.2013 to 12.31.2013 12/01/2013
L 119 Preparation of FY15 Pisces SOW 12/01/2013
M 185 Periodic Status Reports for BPA 12/01/2013
N 115 Develop pre-feasibility report of adult weirs on Pettit Lake Creek and Alturas Lake Stream 12/01/2013
O 162 Isotopic and geochemical analyses 12/01/2013