Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 64905: 2007-397-00 CAP JOHN DAY TRIB/PASS & FLOW
Project Number:
Title:
John Day Watershed Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau John Day 100.00%
Contract Number:
64905
Contract Title:
2007-397-00 CAP JOHN DAY TRIB/PASS & FLOW
Contract Continuation:
Previous: Next:
56228: 2007-397-00 CAP JOHN DAY TRIB/PASS & FLOW-CAP
  • 71619: 2007-397-00 EXP JOHN DAY TRIB/PASS & FLOW
Contract Status:
Closed
Contract Description:
The goal of this project is to address limiting factors by implementing restoration actions that protect and restore passage, flow, and habitat for anadromous fish and listed species in the John Day River Basin.  This includes use of an Implementation Strategy to assist the Confederated Tribes of Warm Springs Reservation of Oregon (CTWS),  John Day Basin Office, John Day Watershed Restoration Program with the ability to focus on implementing suites of restoration actions that will more effectively identify and address priority limiting factors.

In addition to addressing limiting factors outlined in the 2008 FCRPS BiOp, the primary goal of the CTWS, Fisheries Habitat Restoration Program is to protect, manage, and restore aquatic habitats in Reservation watersheds. CTWS defines protect, manage and restore as:

1. Protect existing high-quality habitats that have functioning ecological processes;
2. Manage future land use through an integrated planning process to promote ecological integrity and sustainability; and
3. Restore watersheds and habitats using a prioritized approach based on limiting factors analysis.

In 1855, the Confederated Tribes of the Warm Springs Reservation of Oregon ceded a majority of the John Day basin to the Federal government.  In 1997, the Tribes established an office in the basin to coordinate restoration projects, monitoring, planning and other watershed activities on private and public lands.  Once established, the John Day Basin Office (JDBO) formed partnerships with local agencies and stakeholders to implement restoration activities from the John Day Basin Office and Watershed Restoration Program.

The John Day River basin is within the CTWS ceded lands and supporting restoration efforts such as this project is an important part of maintaining cultural foods and fish populations.  The mission of the CTWS Branch of Natural Resources Fisheries Department is to provide fisheries populations at harvestable levels for tribal members using information gained from research, management, production, and habitat programs while exercising our co-management authority across ceded lands and usual and accustomed stations.

The John Day is the nation’s second longest free-flowing river in the contiguous United States and the longest containing entirely un-supplemented runs of anadromous fish.  Located in eastern Oregon, the basin drains over 8,000 square miles, Oregon’s fourth largest drainage basin, and incorporates portions of eleven counties.  Originating in the Strawberry Mountains near Prairie City, the John Day River flows 284 miles in a northwesterly direction, entering the Columbia River approximately four miles upstream of the John Day dam.  With wild runs of spring Chinook salmon and summer steelhead, westslope cutthroat, and redband and bull trout, the John Day system is truly a basin with national significance.

The John Day Watershed Restoration Program (JDWR) is an on-going, multi-agency program that has historically focused on inefficient, detrimental land-use practices and implemented irrigation system upgrades, diversion passage improvements, upland restoration, and riparian fencing and planting.  The Program’s objectives include removing fish passage impediments, increasing water flows, increasing water quality, and enhancing riparian and stream channel recovery.  Though benefits most readily apply to fish species, the cumulative effects apply to basin-wide watershed recovery.

Projects implemented by the JDWR under this contract are intended to increase in-season river flows through a combination of irrigation efficiency measures; reduce bank instability, sedimentation, bed load movement, and summer passage impediments; improve riparian condition; and implement an annual monitoring program evaluating each of the projects.  These projects respond directly to, and are consistent with, tribal, state, and federal goals and objectives within the region's plans and programs.  Previous projects of these types have demonstrated success in addressing limiting factors identified for salmonid production in the basin.  They follow comprehensive assessments of the watershed, the John Day Subbasin plan and Mid-Columbia Steelhead Recovery Plan.  The benefits are to entirely wild stocks and associated habitats.  Each project utilizes standard design criteria, and was selected using an evaluation and prioritization process.  The effects of individual projects have been evaluated as to short and long term beneficial and/or adverse effects on aquatic and terrestrial species.

For project implementation the JDWR has worked with local SWCDs, Watershed Councils, and other agencies to complete landowner contacts, preliminary planning, engineering designs, permitting, construction contracting, and construction implementation phases.  The JDWR has worked to complete the planning, grant solicitation/defense, environmental compliance, administrative contracting, monitoring, juniper removal contracting, water development implementation, riparian planting, and reporting for the program.  Most phases of project planning, implementation, and monitoring are coordinated with the private landowners and basin agencies, such as the Oregon Department of Fish and Wildlife (ODFW) and Oregon Water Resources Department.  The projects implemented through the JDWR are strictly voluntary and the majority on private land, these multi-agency partnerships are essential to local support and private landowner involvement.  Project efforts rely and build adaptively upon previous and ongoing activities. The overall restoration program appears to have resulted in some significant successes, in particular with spawning and rearing of spring Chinook on private lands.

Through the Accord period (2008-2017) active restoration projects have and will be implemented throughout the John Day Basin, through the CTWS JDWR under this conttact.  Actions going forward from 2014 will be prioritized through a scientific and stakeholder technical advisory team and based on an implementation strategy.
Account Type(s):
Capital
Contract Start Date:
02/01/2014
Contract End Date:
01/31/2016
Current Contract Value:
$4,269,491
Expenditures:
$4,269,491

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Amy Charette Confederated Tribes of Warm Springs Yes Contract Manager amy.charette@ctwsbnr.org (541) 575-1866
Jamie Cleveland Bonneville Power Administration Yes COR jacleveland@bpa.gov (503) 230-3160
Brian Cochran Confederated Tribes of Warm Springs Yes Technical Contact brian.cochran@ctwsbnr.org (541) 553-2003
Lisa Dexter Bonneville Power Administration No lldexter@bpa.gov (503) 230-3893
David Evans Confederated Tribes of Warm Springs Yes Technical Contact david.evans@ctwsbnr.org (541) 575-1866
Allen Gillette Confederated Tribes of Warm Springs Yes Technical Contact allen.gillette@ctwsbnr.org (541) 575-1866
Brad Houslet Confederated Tribes of Warm Springs No Interested Party brad.houslet@ctwsbnr.org (541) 553-2039
Dennis Johnson Confederated Tribes of Warm Springs No Interested Party dennis.johnson@wstribes.org (541) 553-3479
Solomonn Marsh Bonneville Power Administration Yes Contracting Officer spmarsh@bpa.gov (503) 230-3943
Arthur Mitchell Confederated Tribes of Warm Springs No Administrative Contact arthur.mitchell@wstribes.org (541) 553-3219
Chris Moan Confederated Tribes of Warm Springs Yes Technical Contact chris.moan@ctwsbnr.org (541) 575-1866
Wendy Neal Confederated Tribes of Warm Springs Yes Technical Contact wendy.neal@ctwsbnr.org (541) 575-1866
Jenna Peterson Bonneville Power Administration Yes Env. Compliance Lead jepeterson@bpa.gov (503) 230-3018
John Skidmore Bonneville Power Administration Yes F&W Approver jtskidmore@bpa.gov (503) 230-5494
Scott Turo Confederated Tribes of Warm Springs Yes Supervisor scott.turo@ctwsbnr.org (541) 553-2025
Sean Welch Bonneville Power Administration No Interested Party spwelch@bpa.gov (503) 230-7691


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Coordination with John Day Partners, Project Selection, and Prioritization A: 114. Project Selection and Prioritization 01/31/2015 01/31/2015
BPA Project Administration Requirements B: 119. Manage Administer Projects 01/31/2016 01/29/2016
Produce All Required NEPA Documents C: 165. Produce Environmental Compliance Documentation - 2014 - 2015 01/31/2016 01/29/2016
Jacobs Lower Island Ditch Diversion D: 84. Jacobs Lower Island Ditch Diversion 11/30/2015 09/30/2015
Voigt Lower Clear Creek Diversion F: 84. Voigt Lower Clear Creek Diversion 11/30/2015 09/30/2015
Baucum Passage Improvements G: 184. Baucum Passage Improvements 10/31/2015 12/31/2014
Enterprise Passage Improvements H: 184. Enterprise Passage Improvements 10/31/2014 10/31/2014
Submit Drawings and/or Specifications to BPA J: 175. Ricco: Eight John Day River Push-up Dam Replacements Designs 01/31/2016 09/30/2015
Jacobs Roberts Creek Diversion Head Wall and Check Sill L: 184. Jacobs Roberts Creek Diversion 12/31/2015 09/30/2015
Submit Drawings and/or Specifications to BPA M: 175. Design of Nine Diversion Projects 12/31/2015 09/30/2015
Weed Control N: 199. Noxious Weed Control at Project Sites 11/30/2015
Mountain Creek Water Quality O: 29. Mountain Creek Water Quality 10/31/2014 10/31/2014
Mountain/Indian Creek Culvert Replacements P: 85. Mountain/Indian Creek Culvert Replacements 12/31/2014 12/31/2014
Indian Creek Diversion and Pipeline Q: 84. Indian Creek Diversion and Pipeline 10/31/2015 09/30/2015
Replace Diversion R: 84. Badger Creek #3 Diversion 10/31/2015 09/30/2015
Mountain Creek Restoration Phase 4 S: 29. Mountain Creek Restoration Phase 4 10/31/2014 10/31/2014
Bridge-Bear Habitat Phase #3 T: 29. Bridge-Bear Habitat Phase #3 12/31/2014 12/31/2014
Badger Creek Habitat #2 U: 29. Badger Creek Habitat #2 11/30/2014 11/30/2014
Butte Creek Culvert Replacements V: 85. Butte Creek-Hoover Culverts 10/31/2015 09/30/2015
Hashknife Juniper W: 199. Hashknife Juniper 01/31/2016 01/29/2016
Bear Creek Juniper Removal X: 199. Bear Creek Juniper 01/31/2016 01/29/2016
Remove Fish Passage Structure Y: 84. Bettencourt/Olson Diversion 11/30/2014 11/30/2014
Replace Diversion Z: 84. Lonerock/Campbell Diversion 10/31/2015 10/31/2015
Replace Culvert AA: 184. Lonerock Culvert #2 Brown 10/31/2014 10/31/2014
Replace Culvert AB: 184. Lonerock Culvert #1 Buckhorn 10/31/2014 10/31/2014
Eliminate fish passage issues caused by the Deer Creek culvert AD: 85. Deer Creek Culvert Replacement 09/30/2015 09/30/2015
Install Pipeline AE: 149. Osburn Pipeline Phase 2 12/31/2015 12/31/2015
Lower Cottonwood Diversion Passage Improvements AF: 85. Lower Cottonwood Diversion Passage Improvements 11/30/2015 11/30/2015
IDIQ Contract AI: 122. IDIQ Engineering Support 01/31/2015 01/31/2015
Oxbow Phase 3A AJ: 30. Oxbow Phase 3A 11/30/2014 11/30/2014
John Day Basin CTWS Strategy AK: 174. John Day Basin Strategy and Project Prioritization Development 02/28/2015 02/28/2015
Dunstan Preserve Low Flow Enhancement AL: 30. Dunstan Preserve Low Flow Enhancement 10/30/2015 09/30/2015
Planting and Maintenance AM: 198. Edigar Riparian Planting and Maintenance 12/31/2015 09/30/2014
Planting and Maintenance AN: 198. Izee Riparian Planting and Maintenance 12/31/2015 12/31/2015
Planting and Maintenance AO: 198. Kinzau Riparian Planting and Maintenance 12/31/2015 12/31/2015
Planting and Maintenance AP: 198. St. Clair/Rosebud Riparian Planting and Maintenance 12/31/2015 12/31/2015
Planting and Maintenance AQ: 198. Circle W Riparian Planting and Maintenance 12/31/2015 12/31/2015
Planting and Maintenance AR: 198. Barker Riparian Planting and Maintenance 12/31/2015 12/31/2015
Planting and Maintenance AS: 198. Blanchett Riparian Planting and Maintenance 12/31/2015 12/31/2015
Planting and Maintenance AT: 198. Rittner Riparian Planting and Maintenance 12/31/2015 12/31/2015
Planting and Maintenance AU: 198. Painted Hills Planting and Maintenance 12/31/2015 12/31/2015
Planting and Maintenance AV: 198. Meredith Riparian Planting and Maintenance 12/31/2015 12/31/2015
Planting AW: 47. Bridge/Bear Creek Riparian Planting 11/30/2015 11/30/2015
Windlass Creek Culvert Replacement AX: 85. Windlass Creek Culvert Replacement 12/31/2015 12/31/2015
Construct RPB Easement Fence AY: 40. RPB Easement Fence 01/31/2016 12/31/2015
Develop Design Plan BA: 115. Starr Habitat 12/31/2015 12/31/2015
Develop Plan to Install Fish Screen and Piping BB: 115. Pope - Moon Creek Irrigation Ditch Piping and Fish Screen 12/31/2015 12/31/2015
John Day Native Hardwood Planting BD: 47. John Day Native Hardwood Planting 11/30/2015 09/30/2015
Willow Springs Channel and Meadow Restoration BF: 29. Willow Springs Channel and Meadow Restoration 10/31/2014 10/31/2014
Attach Progress Report in Pisces BH: 132. Submit Annual Report for the Period (02/01/2010) to (01/31/2012) 12/31/2015
Attach Progress Report in Pisces BI: 132. Submit Annual Report for the Period (02/01/2012) to (01/31/2014) 12/31/2015
John Day Partnership BJ: 191. John Day Partnership 01/31/2016 12/31/2015
Aspen Fence BK: 40. Sheep Creek Restoration 01/31/2016 12/31/2015
Produce accessible, error-checked datasets BL: 157. Telemetry Tracking 01/31/2016 12/31/2015
Fish Passage on Meredith #3 BM: 184. Meredith #3 12/31/2015 09/30/2015
Fish Passage on Meredith #4 BN: 184. Meredith #4 12/31/2015 09/30/2015
Cottonwood Diversion Improvement #2 Cox/Bansen BQ: 84. Cottonwood Creek #2 Cox/Bansen Diversion 10/31/2015 09/30/2015
EC Compliance for 2016-2017 Projects BR: 165. Produce Environmental Compliance Documentation - 2016 - 2017 01/31/2016 01/29/2016
Design of Mallory Creek Road Re-Route BS: 175. Design of Mallory Creek Road Re-Route 01/31/2016 09/30/2015
Design of Pope Moon Creek Project BT: 175. Design of Pope Moon Creek Project 01/31/2016 01/29/2016

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 3 instances of WE 199 Remove Vegetation
  • 10 instances of WE 198 Maintain Vegetation
  • 6 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 33 Decommission Road/Relocate Road
  • 2 instances of WE 40 Install Fence
  • 3 instances of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 9 instances of WE 84 Remove/Install Diversion
  • 5 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 8 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 114 Identify and Select Projects
  • 3 instances of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 174 Produce Plan
  • 5 instances of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 3 instances of WE 149 Install Pipeline
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 3 instances of WE 199 Remove Vegetation
  • 10 instances of WE 198 Maintain Vegetation
  • 6 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 33 Decommission Road/Relocate Road
  • 2 instances of WE 40 Install Fence
  • 3 instances of WE 47 Plant Vegetation
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 9 instances of WE 84 Remove/Install Diversion
  • 5 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 8 instances of WE 184 Install Fish Passage Structure
  • 1 instance of WE 114 Identify and Select Projects
  • 3 instances of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 174 Produce Plan
  • 5 instances of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 3 instances of WE 149 Install Pipeline

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 114 Project Selection and Prioritization 02/01/2014
B 119 Manage Administer Projects 02/01/2014
C 165 Produce Environmental Compliance Documentation - 2014 - 2015 02/01/2014
D 84 Jacobs Lower Island Ditch Diversion 08/11/2014
E 84 Emmel-Mill/Galbraith Ditch Diversion
F 84 Voigt Lower Clear Creek Diversion 06/10/2015
G 184 Baucum Passage Improvements 08/14/2014
H 184 Enterprise Passage Improvements 07/28/2014
I 29 Holliday Streambank Stabilization
J 175 Ricco: Eight John Day River Push-up Dam Replacements Designs
K 84 Larson: One Canyon and Three Berry Creek Push-Up Dam Replacements
L 184 Jacobs Roberts Creek Diversion 07/24/2015
M 175 Design of Nine Diversion Projects 02/01/2014
N 199 Noxious Weed Control at Project Sites 01/29/2016
O 29 Mountain Creek Water Quality 09/19/2014
P 85 Mountain/Indian Creek Culvert Replacements 09/19/2014
Q 84 Indian Creek Diversion and Pipeline 07/14/2015
R 84 Badger Creek #3 Diversion 07/14/2015
S 29 Mountain Creek Restoration Phase 4 09/19/2014
T 29 Bridge-Bear Habitat Phase #3 08/14/2015
U 29 Badger Creek Habitat #2 09/24/2014
V 85 Butte Creek-Hoover Culverts 09/08/2015
W 199 Hashknife Juniper 07/24/2015
X 199 Bear Creek Juniper 07/24/2015
Y 84 Bettencourt/Olson Diversion 08/20/2014
Z 84 Lonerock/Campbell Diversion 03/09/2016
AA 184 Lonerock Culvert #2 Brown 06/19/2014
AB 184 Lonerock Culvert #1 Buckhorn 06/19/2014
AC 180 Cavender Riparian Habitat and Wetland Habitat Protection
AD 85 Deer Creek Culvert Replacement 07/14/2015
AE 149 Osburn Pipeline Phase 2 01/29/2016
AF 85 Lower Cottonwood Diversion Passage Improvements 07/28/2014
AG 175 Dovenberg Fish Habitat Improvement Design
AH 47 Dovenberg Habitat Planting
AI 122 IDIQ Engineering Support 02/01/2014
AJ 30 Oxbow Phase 3A 12/04/2014
AK 174 John Day Basin Strategy and Project Prioritization Development 02/01/2014
AL 30 Dunstan Preserve Low Flow Enhancement 07/14/2015
AM 198 Edigar Riparian Planting and Maintenance 06/19/2014
AN 198 Izee Riparian Planting and Maintenance 06/19/2014
AO 198 Kinzau Riparian Planting and Maintenance 06/19/2014
AP 198 St. Clair/Rosebud Riparian Planting and Maintenance 06/19/2014
AQ 198 Circle W Riparian Planting and Maintenance 06/19/2014
AR 198 Barker Riparian Planting and Maintenance 06/19/2014
AS 198 Blanchett Riparian Planting and Maintenance 06/19/2014
AT 198 Rittner Riparian Planting and Maintenance 06/19/2014
AU 198 Painted Hills Planting and Maintenance 06/19/2014
AV 198 Meredith Riparian Planting and Maintenance 06/19/2014
AW 47 Bridge/Bear Creek Riparian Planting 06/19/2014
AX 85 Windlass Creek Culvert Replacement 04/27/2015
AY 40 RPB Easement Fence 06/26/2014
AZ 115 Widows Creek Habitat Assessment 02/01/2014
BA 115 Starr Habitat 06/10/2014
BB 115 Pope - Moon Creek Irrigation Ditch Piping and Fish Screen 06/10/2014
BC 149 Vidourek-Cates Irrigation Ditch Piping
BD 47 John Day Native Hardwood Planting 03/09/2016
BE 33 Mallory Creek Road Re-Route 02/01/2014
BF 29 Willow Springs Channel and Meadow Restoration 06/10/2015
BG 185 Periodic Status Reports for BPA 02/01/2014
BH 132 Submit Annual Report for the Period (02/01/2010) to (01/31/2012) 02/01/2014
BI 132 Submit Annual Report for the Period (02/01/2012) to (01/31/2014) 02/01/2014
BJ 191 John Day Partnership 02/01/2014
BK 40 Sheep Creek Restoration 11/03/2015
BL 157 Telemetry Tracking 01/29/2016
BM 184 Meredith #3 07/14/2015
BN 184 Meredith #4 07/14/2015
BO 184 Pope Moon Creek Diversion
BP 149 Pope Moon Creek Pipeline
BQ 84 Cottonwood Creek #2 Cox/Bansen Diversion 07/14/2015
BR 165 Produce Environmental Compliance Documentation - 2016 - 2017 02/01/2014
BS 175 Design of Mallory Creek Road Re-Route 02/01/2014
BT 175 Design of Pope Moon Creek Project 01/29/2016