Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 67980: 1989-098-00 EXP SALMON STUDIES IN IDAHO RIVERS - SHOBAN - 2015
Project Number:
Title:
Salmon Studies in Idaho Rivers
BPA PM:
Stage:
Closed
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
67980
Contract Title:
1989-098-00 EXP SALMON STUDIES IN IDAHO RIVERS - SHOBAN - 2015
Contract Continuation:
Previous: Next:
63754: 1989-098-00 EXP SALMON STUDIES IDAHO RIVERS - SHOBAN - 2014
Contract Status:
Closed
Contract Description:
ADMINISTRATIVE SUMMARY

2015 is planned as the last year of the implementation of this project.  Primary objectives for all contracts under this project will be to complete all data analysis and cooperate in development and writing of finals reports.


For the majority of the tasks for this contract (January 1, 2015 to December 31, 2015), the project is completing work in the third and final phase of the design.  During the 2015 contract year, the ISS project will move into an analysis phase and will complete final analyses and produce draft versions of the completion report.  All other tasks described in the 2015 SOW and the work elements are simply a continuation of the project's coordination, analysis and reporting requirements.
________________________________________
Fish tagging and marking play important roles in stock assessment, research, management, and recovery of salmonid and other fishes in the Basin.  Results from tagging investigations influence decisions on hydrosystem management such as water spill at dams and fish transport; harvest regimes in the ocean and river; hatchery practices; and endangered species risk assessment.

This Statement of Work for contract year 2015 (Jan - Dec 2015) includes synthesis of research activities and tasks completed by all cooperating agencies.

The ISS program began in 1992.  In 2005, to respond to ISRP recommendations, the program’s data sets were assessed, and the original ISS study design was updated.  The data set review indicated the data would be sufficient to address the program’s two main goals and that the ANOVA technique proposed in the original study design would be appropriate for much of the analysis.  Alternatively, regression and graphical techniques were also developed for some data sets as recommended by the ISRP.  The effect of general production hatchery strays into ISS study streams was also addressed in the updated study design.  Additional carcass collections were initiated to better quantify the magnitude of this unintended supplementation and will be continued throughout the remainder of the program.  We also developed a supplemental proposal to use microsatellite DNA parentage analyses to address the relative reproductive success of natural, supplementation, and general production fish in a subset of study streams.  However, this would represent a large and costly commitment by the region, and would require additional funds.


The Shoshone-Bannock Tribes have collected data from juvenile Chinook salmon at the East Fork Salmon River and Valley Creek of the Salmon River.  Chinook salmon redd counts have been conducted on Herd Creek (tributary to the East Fork Salmon River), the East Fork Salmon River, West Fork of the Yankee Fork, Valley Creek, and Bear Valley Creek.  Data collected from these streams are included in final analysis and production of the ISS completion report.
Account Type(s):
Expense
Contract Start Date:
01/01/2015
Contract End Date:
12/31/2015
Current Contract Value:
$29,849
Expenditures:
$29,849

* Expenditures data includes accruals and are based on data through 30-Apr-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration Yes Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
David Byrnes Bonneville Power Administration Yes COR dmbyrnes@bpa.gov (503) 230-3171
Chad Colter Shoshone-Bannock Tribes No Supervisor ccolter@sbtribes.com (208) 239-4553
Doug Taki Shoshone-Bannock Tribes Yes Contract Manager dtaki@sbtribes.com (208) 239-4568
Gaylene Turnage Shoshone-Bannock Tribes No Administrative Contact gturnage@sbtribes.com (208) 478-3821
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
David Venditti Idaho Department of Fish and Game (IDFG) No Interested Party david.venditti@idfg.idaho.gov (208) 465-8404x231
Pam Waterhouse Shoshone-Bannock Tribes No Administrative Contact pwaterhouse@sbtribes.com (208) 478-3819
Dorothy Welch Bonneville Power Administration Yes F&W Approver dwwelch@bpa.gov (503) 230-5479


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Draft funding package B: 119. (If Needed ONLY) Produce CY2016 SOW, budgets, AFS meeting and inventories 11/30/2015
Cooderation with other agencies and public. in at least 4 ISS prog C: 191. Coordination with agencies and public 11/30/2015 11/30/2015
Analyze and interpret comprehensive ISS supplementation data. E: 162. Analyze and interpret comprehensive ISS supplementation data. 06/30/2015 05/22/2015
Deliverable: A. Data and analysis products submitted to IDFG as needed for BiOp Report. F: 202. BiOp RPA Report for CY 2014 03/05/2015 01/23/2015

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 162 Analyze/Interpret Data
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 1 instance of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 01/01/2015
B 119 (If Needed ONLY) Produce CY2016 SOW, budgets, AFS meeting and inventories 01/01/2015
C 191 Coordination with agencies and public 01/01/2015
D 132 Produce Finalize ISS Cooperative Report for BY12 (period Aug 12 to June 14) 01/01/2015
E 162 Analyze and interpret comprehensive ISS supplementation data. 01/01/2015
F 202 BiOp RPA Report for CY 2014