Contract 68536: 1984-021-00 EXP JOHN DAY HABITAT ENHANCEMENT
Project Number:
Title:
John Day Habitat Enhancement
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau John Day 100.00%
Contract Number:
68536
Contract Title:
1984-021-00 EXP JOHN DAY HABITAT ENHANCEMENT
Contract Continuation:
Previous: Next:
65076: 1984-021-00 EXP JOHN DAY HABITAT ENHANCEMENT
  • 71856: 1984-021-00 EXP JOHN DAY HABITAT ENHANCEMENT
Contract Status:
Closed
Contract Description:
This project was initiated on July 1, 1984 under the BPA contract and allows for initial landowner contacts, agreement development, project design, budgeting, and implementation for anadromous fish habitat improvement on privately owned lands within the John Day Basin.  

The purpose of the John Day Fish Habitat Enhancement Program is to enhance production of indigenous wild stocks of spring chinook and summer steelhead within the sub basin through habitat protection, enhancement and fish passage improvements.

In work period 3-1-2015 thru 2-29-2016 the fish habitat program will construct approximately 14.5.0 miles of riparian protection fence, 145 acres and 8.50 miles of creeks protected, coordination with4 landowners (Heideman, ODFW, Ecotrust, and Hansen).  The actual number of stream miles protected is probably higher, due to sinuosity and ground truthing this summer will correct any missed judgments.  Construction will include approximately 3.5 miles of riparian fence on8 mile Creek/Heideman property tributary to the Middle Fork John Day River, 3.5 miles of riparian fence on ODFW property on South Fork Murderers Creek tributary of the South Fork John Day River, 5.0 miles riparian fence on Desolation Creek on Ecotrust property tributary of the North Fork John Day River, and 4.0 miles riparian fence on the Fox Creek on Randy Hansen property tributary of the North Fork John Day River.  There will be approximately 35 gates and 20 watergaps constructed on riparian fence project sites.
Account Type(s):
Expense
Contract Start Date:
03/01/2015
Contract End Date:
02/29/2016
Current Contract Value:
$567,846
Expenditures:
$567,846

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
EC for the Fish Habitat Program A: 165. Environmental Compliance 09/30/2015 09/30/2015
Select Project Sites B: 114. Select Project Sites 02/28/2016 02/28/2016
Riparian Fence Installation C: 40. ODFW Property - South Fork Murderers Creek 11/28/2015 11/28/2015
Riparian Fence Installation D: 40. Ecotrust Property - Desolation Creek 09/01/2015 09/01/2015
Riparian Fence Installation E: 40. Hansen Property - Fox Creek 12/30/2015 12/30/2015
Riparian Fence Installation F: 40. Heideman Property - 8 Mile Creek 10/15/2015 10/15/2015
Riparian Fence Installation G: 40. New Fence Placeholder Approximately 2 Miles (Location Unknown Placeholder) 10/24/2015 10/24/2015
15 Year Cooperative Agreement on ODFW Property - South Fork Murderers Creek H: 92. ODFW Property - South Fork Murderers Creek 04/01/2015 04/01/2015
15 Year Cooperative Agreement on Ecotrust Property - Desolation Creek I: 92. Ecotrust Property - Desolation Creek 04/15/2015 04/15/2015
15 Year Cooperative Agreement on Hansen Property - Fox Creek J: 92. Hansen Property - Fox Creek 03/31/2015 03/31/2015
15 Year Cooperative Agreement on Heideman Property - 8 Mile Creek K: 92. Heideman Property - 8 Mile Creek 04/03/2015 04/03/2015
15 Year Cooperative Agreement- John Day River Basin L: 92. New Place Holder - John Day River Basin 03/31/2015 03/31/2015
Maintenance of Riparian Projects M: 186. Maintain Terrestrial Structures 02/28/2016 02/28/2016
Herbicide Application N: 198. Herbicide Application 09/30/2015 09/30/2015
Progress Report has Been Published O: 132. Submit Progress Report for the Period (March 1, 2014) to (February 28, 2015) 08/15/2015 08/15/2015
Program Management and Project Prioritization Q: 119. Program Management 02/29/2016 02/29/2016

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 5 instances of WE 40 Install Fence
  • 5 instances of WE 92 Lease Land
  • 1 instance of WE 114 Identify and Select Projects
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 5 instances of WE 40 Install Fence
  • 5 instances of WE 92 Lease Land
  • 1 instance of WE 114 Identify and Select Projects

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance 03/01/2015
B 114 Select Project Sites 03/01/2015
C 40 ODFW Property - South Fork Murderers Creek 08/28/2015
D 40 Ecotrust Property - Desolation Creek 08/28/2015
E 40 Hansen Property - Fox Creek 08/28/2015
F 40 Heideman Property - 8 Mile Creek 08/28/2015
G 40 New Fence Placeholder Approximately 2 Miles (Location Unknown Placeholder) 12/29/2015
H 92 ODFW Property - South Fork Murderers Creek 03/01/2015
I 92 Ecotrust Property - Desolation Creek 03/01/2015
J 92 Hansen Property - Fox Creek 03/01/2015
K 92 Heideman Property - 8 Mile Creek 03/01/2015
L 92 New Place Holder - John Day River Basin 03/01/2015
M 186 Maintain Terrestrial Structures 03/01/2015
N 198 Herbicide Application 07/27/2015
O 132 Submit Progress Report for the Period (March 1, 2014) to (February 28, 2015) 03/01/2015
P 185 Periodic Status Reports for BPA 03/01/2015
Q 119 Program Management 03/01/2015