Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 70630: 2002-060-00 EXP NEZ PERCE HARVEST MONITORING
Project Number:
Title:
Nez Perce Harvest Monitoring on Snake and Clearwater Rivers
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 50.00%
Upper Snake Snake Upper 50.00%
Contract Number:
70630
Contract Title:
2002-060-00 EXP NEZ PERCE HARVEST MONITORING
Contract Continuation:
Previous: Next:
67113: 2002-060-00 EXP NEZ PERCE HARVEST MONITORING
  • 74325: 2002-060-00 EXP NEZ PERCE HARVEST MONITORING
Contract Status:
Closed
Contract Description:
This project describes the Nez Perce Tribe's efforts to monitor currently ongoing NPT fisheries.  Sampling strategies are designed to provide greater data precision in treaty catch reports and exploitation rates during select Nez Perce fishery seasons.  Harvest management is intertwined with all Columbia Basin artificial production programs and affects the status of naturally produced stocks as well.  The Nez Perce Tribe has monitored its fisheries primarily by funding sources outside the Northwest Power Planning Council (NPPC) process.  However, the subbasin planning process has documented the need to incorporate this very important aspect of fisheries management within the existing Fish and Wildlife Program.  

The current SOW has three major areas of activity.  Tribal Management Plans and Fishery Implementation Plans will be prepared to assure both incidental and direct take of ESA listed species does not jeopardize their existence.  The bulk of the work of the SOW in involved in actual on the ground harvest monitoring in Snake, Salmon and Clearwater rivers and their tributaries and in the Zone 6 fishery (Bonneville Dam to McNary Dam, including some Below Bonneville fishing).  In addition, there will be work to design and verify the monitoring techniques and disseminate the monitoring data to cooperating agencies on a regular basis.
Account Type(s):
Expense
Contract Start Date:
12/01/2015
Contract End Date:
11/30/2016
Current Contract Value:
$317,191
Expenditures:
$317,191

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Arleen Henry Nez Perce Tribe Yes Administrative Contact arleenh@nezperce.org (208) 621-3833
David Johnson Nez Perce Tribe No Supervisor davej@nezperce.org (208) 621-3736
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Amber MacLachlan Bonneville Power Administration Yes Contracting Officer almcmahon@bpa.gov (503) 230-3983
Joseph Oatman Nez Perce Tribe Yes Contract Manager joeo@nezperce.org (208) 843-7320x3730
David Roberts Bonneville Power Administration Yes COR daroberts@bpa.gov (503) 230-4511
Gregory Smith Bonneville Power Administration Yes Env. Compliance Lead gmsmith@bpa.gov (503) 230-5049
Dave Statler Nez Perce Tribe Yes Technical Contact daves@nezperce.org (208) 621-3575


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Environmental Compliance Documentation A: 165. Produce Environmental Compliance Documentation 11/30/2016 11/30/2016
Submit BiOp RPA Report in Taurus B: 202. BiOp RPA Report for CY 2014 04/20/2016 04/21/2016
BA's for tribal harvest and TMT's for selected subbasins C: 174. Prepare Annual Tribal Mmanagement Plans and Fishery Implementation Plans 11/30/2016 11/30/2016
Develop Harvest Monitoring Methodology D: 156. Develop annual harvest monitoring methodology 11/30/2016 11/30/2016
Implement Harvest Monitoring Methodology and Produce accessible, error-checked datasets E: 157. Implement harvest monitoring methodology and disseminate harvest monitoring results (Creel Sur 11/30/2016 11/30/2016
Implement Harvest Monitoring Methodology and Produce accessible, error-checked datasets F: 157. Implement Harvest Monitoring Methodology and Disseminate Harvest Monitoring results (In-season 11/30/2016 11/30/2016
Implement Harvest Monitoring Methodology and Produce accessible, error-checked datasets G: 157. Implement Harvest Monitoring Methodology and Disseminate Harvest Monitoring Results (Post-seas 11/30/2016 11/30/2016
Implement Harvest Monitoring Methodology and Produce accessible, error-checked datasets H: 157. Implement Harvest Monitoring methodology and Disseminate Harvest Monitoring Results (Gill net) 11/30/2016 11/30/2016
Completed Annual Report I: 132. Submit Progress Report for the period Jan 2014 to Dec 2014 04/30/2016
Project Management, Planning and Budgetary Processes K: 119. Project Management & Planning plus Budgetary Processes 11/30/2016 11/30/2016

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened)
  • 1 instance of WE 174 Produce Plan
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 174 Produce Plan
  • 4 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 1 instance of WE 174 Produce Plan
  • 4 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Produce Environmental Compliance Documentation 12/01/2015
B 202 BiOp RPA Report for CY 2014
C 174 Prepare Annual Tribal Mmanagement Plans and Fishery Implementation Plans 12/01/2015
D 156 Develop annual harvest monitoring methodology 12/01/2015
E 157 Implement harvest monitoring methodology and disseminate harvest monitoring results (Creel Sur 12/01/2015
F 157 Implement Harvest Monitoring Methodology and Disseminate Harvest Monitoring results (In-season 12/01/2015
G 157 Implement Harvest Monitoring Methodology and Disseminate Harvest Monitoring Results (Post-seas 12/01/2015
H 157 Implement Harvest Monitoring methodology and Disseminate Harvest Monitoring Results (Gill net) 12/01/2015
I 132 Submit Progress Report for the period Jan 2014 to Dec 2014 12/01/2015
J 185 Periodic Status Reports for BPA 12/01/2015
K 119 Project Management & Planning plus Budgetary Processes 12/01/2015