Contract 70741: 2007-396-00 EXP WALLA WALLA BASINWIDE TRIB PASSAGE
Project Number:
Title:
Walla Walla Basinwide Tributary Passage and Flow
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Walla Walla 100.00%
Contract Number:
70741
Contract Title:
2007-396-00 EXP WALLA WALLA BASINWIDE TRIB PASSAGE
Contract Continuation:
Previous: Next:
67282: 2007-396-00 EXP WALLA WALLA BASINWIDE TRIB PASSAGE
  • 74306: 2007-396-00 EXP WALLA WALLA BASINWIDE TRIB PASSAGE
Contract Status:
Closed
Contract Description:
A three-mile segment of the Walla Walla River near Milton-Freewater, Oregon, was dewatered each summer for the last century creating the need for fish rescues.  The rescues have not been necessary the last eleven years after aggressive irrigation efficiency programs and new wells now maintain at least 27 cfs instream throughout the spring and 25 cfs instream throughout the summer.  However, half of these bypass flows are created by an increase in supplemental well use at unsustainable rates.  Additional irrigation conservation practices, combined with winter/spring groundwater recharge, will allow irrigators to reduce their demand on the river, reduce negative impacts to groundwater, and protect the conserved water as instream water rights. Projects planned under this contract will help WWBWC and the Walla Walla Basin continue their efforts to increase water in the Walla Walla River, its tributaries, and the shallow aquifer in order to ensure viable fish habitat in the basin.
Account Type(s):
Expense
Contract Start Date:
11/01/2015
Contract End Date:
10/31/2016
Current Contract Value:
$895,869
Expenditures:
$895,869

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Jonathan Goodman Bonneville Power Administration Yes Env. Compliance Lead jdgoodman@bpa.gov (503) 230-4764
Wendy Harris Walla Walla Basin Watershed Council Yes Contract Manager wendy.harris@wwbwc.org (541) 938-2170
Douglas Knapp Bonneville Power Administration No Technical Contact ddknapp@bpa.gov (503) 230-3285
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Amber MacLachlan Bonneville Power Administration Yes Contracting Officer almcmahon@bpa.gov (503) 230-3983
Brian Wolcott Walla Walla Basin Watershed Council No Supervisor brian.wolcott@wwbwc.org (541) 938-2170
Tracey Yerxa Bonneville Power Administration Yes COR tyerxa@bpa.gov (503) 230-4738


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
All administrative tasks fulfilled with timely quality products A: 119. Admin oversight for Exp Activities 10/31/2016 10/31/2016
Environmental Compliance complete B: 165. Environmental Compliance Documentation for all Exp actions 10/31/2016 10/31/2016
Surface Water Data collected for recharge projects and water monitoring C: 157. Collect Surface Water Data for Recharge project and Water monitoring 10/31/2016 10/31/2016
Groundwater Data collected for recharge projects and water monitoring D: 157. Collect Groundwater Data for Recharge project and Water monitoring 10/31/2016 10/31/2016
Produce accessible, error-checked datasets E: 157. Collect Water Temperature Data for Recharge project and Water monitoring 10/31/2016 10/31/2016
Updated WWBWC Database F: 160. Maintain Surface Water Database for Recharge project and Water monitoring 10/31/2016 10/31/2016
Maintain Groundwater Database G: 160. Maintain Groundwater Database for Recharge project and Water monitoring 10/31/2016 10/31/2016
Maintain water temperature database H: 160. Maintain Water Temperature Database for Recharge project and Water monitoring 10/31/2016 10/31/2016
Results on the success of the Recharge Project, On-farm Efficiency, and Water Management I: 162. Analyze Surface Water Data for Recharge Project 10/31/2016 10/31/2016
Results on the success of the Recharge Project, On-farm Efficiency, and Water Management J: 162. Analyze Groundwater Data for Recharge Project 10/31/2016 10/31/2016
Results on the success of the Recharge Project, On-farm Efficiency, and Water Management K: 162. Analyze Water Temperature Data for Recharge Project 10/31/2016 10/31/2016
Education and Outreach L: 99. Irrigation Efficiency and Aquifer Recharge project 10/31/2016 10/31/2016
Flow meters installed N: 148. Fruitvale Water Users Association Water Management Flow Meters - Phase 4 10/31/2016 10/31/2016
Walla Walla River Diversion Telemetry Installed O: 148. Walla Walla River Diversion Flow Telemetry 10/31/2016 10/31/2016
White Ditch Phase 1 Seepage Assessment Data Collected P: 115. White Ditch Phase 1 Seepage Analysis 10/31/2016 10/31/2016
County Road Aquifer Recharge Designs Q: 175. County Road Aquifer Recharge Design 10/31/2016 10/31/2016
Gallagher Aquifer Recharge Designs R: 175. Gallagher Aquifer Recharge Design 10/31/2016 10/31/2016
Triangle Station Aquifer Recharge Designs S: 175. Triangle Station Aquifer Recharge Design 10/31/2016 10/31/2016
Triangle Road Aquifer Recharge Designs T: 175. Triangle Road Aquifer Recharge Design 10/31/2016 10/31/2016
Locust Road Sprinkler System Installed U: 203. Locust Road Sprinkler Project 10/31/2016 10/31/2016
Construct recharge site V: 205. Locust Road Dual Purpose Bulge 10/31/2016 10/31/2016
White Ditch Phase 1 Section 3 piped W: 203. White Ditch Piping Project Phase 1, Section 3 10/31/2016 10/31/2016
WWRID Water Right Legal Notices Complete X: 154. In-stream Water Right Transactions for LWW 10/31/2016 10/07/2016
Youth and Adult Presentations Y: 99. Youth and adult presentations 08/31/2016 08/31/2016
Pre-Acquisition Activities Completed AA: 172. Johnson Cherry Orchard Acquisition 10/31/2016

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 2 instances of WE 203 Install Water Conservation Measure
  • 1 instance of WE 205 Aquifer Recharge
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 4 instances of WE 175 Produce Design
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 3 instances of WE 162 Analyze/Interpret Data
  • 2 instances of WE 148 Install Flow Measuring Device
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 2 instances of WE 203 Install Water Conservation Measure
  • 1 instance of WE 205 Aquifer Recharge
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 4 instances of WE 175 Produce Design
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 3 instances of WE 162 Analyze/Interpret Data
  • 2 instances of WE 148 Install Flow Measuring Device
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction
Trout, Bull (S. confluentus) (Threatened)
  • 2 instances of WE 203 Install Water Conservation Measure
  • 1 instance of WE 205 Aquifer Recharge
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 4 instances of WE 175 Produce Design
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 3 instances of WE 162 Analyze/Interpret Data
  • 2 instances of WE 148 Install Flow Measuring Device
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Admin oversight for Exp Activities 11/01/2015
B 165 Environmental Compliance Documentation for all Exp actions 11/01/2015
C 157 Collect Surface Water Data for Recharge project and Water monitoring 11/01/2015
D 157 Collect Groundwater Data for Recharge project and Water monitoring 11/01/2015
E 157 Collect Water Temperature Data for Recharge project and Water monitoring 11/01/2015
F 160 Maintain Surface Water Database for Recharge project and Water monitoring 11/01/2015
G 160 Maintain Groundwater Database for Recharge project and Water monitoring 11/01/2015
H 160 Maintain Water Temperature Database for Recharge project and Water monitoring 11/01/2015
I 162 Analyze Surface Water Data for Recharge Project 11/01/2015
J 162 Analyze Groundwater Data for Recharge Project 11/01/2015
K 162 Analyze Water Temperature Data for Recharge Project 11/01/2015
L 99 Irrigation Efficiency and Aquifer Recharge project 11/01/2015
M 132 Annual Progress Report (11-1-14 to 10-31-15) 11/01/2015
N 148 Fruitvale Water Users Association Water Management Flow Meters - Phase 4 03/21/2016
O 148 Walla Walla River Diversion Flow Telemetry 11/01/2015
P 115 White Ditch Phase 1 Seepage Analysis 11/01/2015
Q 175 County Road Aquifer Recharge Design 11/01/2015
R 175 Gallagher Aquifer Recharge Design 11/01/2015
S 175 Triangle Station Aquifer Recharge Design 11/01/2015
T 175 Triangle Road Aquifer Recharge Design 11/01/2015
U 203 Locust Road Sprinkler Project 03/21/2016
V 205 Locust Road Dual Purpose Bulge 03/21/2016
W 203 White Ditch Piping Project Phase 1, Section 3 11/01/2015
X 154 In-stream Water Right Transactions for LWW 11/01/2015
Y 99 Youth and adult presentations 11/01/2015
Z 185 Periodic Status Reports for BPA 11/01/2015
AA 172 Johnson Cherry Orchard Acquisition 11/01/2015