Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 72953: 1992-009-00 EXP WDFW SCR O&M, YAK, UCR, LCR
Project Number:
Title:
Yakima Phase II Fish Screens Operations and Maintenance (O&M) with Washington Department of Fish and Wildlife (WDFW)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Yakima 100.00%
Contract Number:
72953
Contract Title:
1992-009-00 EXP WDFW SCR O&M, YAK, UCR, LCR
Contract Continuation:
Previous: Next:
69630: 1992-009-00 EXP WDFW SCR O&M, YAK, UCR, LCR
Contract Status:
Closed
Contract Description:
Task 1 - Inspection, operation, and maintenance of two fishways and twenty-four fish screens located on upper and mid-Columbia River tributaries.

Task 2 - Provide ongoing fishway operation and maintenance for 15 lower Columbia River fishways.

Task 3 - Cost-share with other proponents for the funds for fish passage and screening.
Account Type(s):
Expense
Contract Start Date:
07/01/2016
Contract End Date:
06/30/2017
Current Contract Value:
$137,626
Expenditures:
$137,626

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Documentation and assistance to support BPA's Environmental Compliance Group B: 165. Obtain ESA Compliance for O&M Activities 06/30/2017 06/30/2017
All administrative tasks fulfilled with timely quality products C: 119. Manage and administer project 06/30/2017 06/30/2017
Inspect and maintain Upper and mid-Columbia R screens D: 186. Maintain upper + mid-Columbia screens/fishways (Task #1) 06/30/2017 06/30/2017
O&M Lower Columbia River tributary fishway E: 186. Maintain Lower Columbia River passage (Task #2) 06/30/2017 06/30/2017
Provide pre-fabricated fish screens and fish screening materials F: 69. Screen placeholder #1 Provide materials to support install of fish screen (Task #3) 06/30/2017
Provide pre-fabricated fish screens and fish screening materials G: 69. Screen placeholder #2 Provide materials to support install of fish screen (Task #3) 06/30/2017
Provide pre-fabricated fish screens and fish screening materials H: 69. Screen placeholder #3 Provide materials to support install of fish screen (Task #3) 06/30/2017
Provide pre-fabricated fish screens and fish screening materials I: 69. Screen placeholder #4 Provide materials to support install of fish screen (Task #3) 06/30/2017
Provide pre-fabricated fish screens and fish screening materials J: 69. Screen placeholder #5 Provide materials to support install of fish screen (Task #3) 06/30/2017

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 5 instances of WE 69 Install Fish Screen
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 07/01/2016
B 165 Obtain ESA Compliance for O&M Activities 07/01/2016
C 119 Manage and administer project 07/01/2016
D 186 Maintain upper + mid-Columbia screens/fishways (Task #1) 07/31/2017
E 186 Maintain Lower Columbia River passage (Task #2) 07/31/2017
F 69 Screen placeholder #1 Provide materials to support install of fish screen (Task #3)
G 69 Screen placeholder #2 Provide materials to support install of fish screen (Task #3)
H 69 Screen placeholder #3 Provide materials to support install of fish screen (Task #3)
I 69 Screen placeholder #4 Provide materials to support install of fish screen (Task #3)
J 69 Screen placeholder #5 Provide materials to support install of fish screen (Task #3)
K 132 Support Annual reporting 07/01/2016