Obtain & Submit EC |
A: 165. Produce Environmental Compliance Documentation |
|
06/30/2017 |
06/30/2017 |
Install, Maintain, & Remove RSTs in WSR for Fall & Spring Out-Migration Periods |
B: 70. O. mykiss & Spring Chinook: Install, Maintain, & Remove Warm Springs River Rotary Screw Traps |
|
06/30/2017 |
06/30/2017 |
PIT Tag up to 3,000 Juvenile Spring Chinook Salmon at WSR RSTs |
C: 158. Spring Chinook: PIT Tag Spring Chinook at Warm Springs River Rotary Screw Traps |
|
06/30/2017 |
06/30/2017 |
PIT Tag up to 1,000 Juvenile O. mykiss at WSR RSTs |
D: 158. O. mykiss: PIT Tag O. mykiss at Warm Springs River Rotary Screw Traps |
|
06/30/2017 |
06/30/2015 |
Operate WSR RSTs during Spring and Fall Out-Migration Periods |
E: 157. O. mykiss & Spring Chinook: Operate Warm Springs River Rotary Screw Trap |
|
06/30/2017 |
06/30/2017 |
Install, Maintain & Remove RST in SC for Fall & Spring Out-Migration Periods |
F: 70. O. mykiss & Spring Chinook: Install, Maintain, & Remove Shitike Creek Rotary Screw Trap |
|
06/30/2017 |
06/30/2017 |
Operate SC RST during Spring & Fall Out-Migration Periods |
G: 157. O. mykiss & Spring Chinook: Operate Shitike Creek Rotary Screw Trap |
|
06/30/2017 |
06/30/2017 |
PIT Tag 1,000 Juvenile Spring Chinook Salmon at SC RST |
H: 158. Spring Chinook: PIT Tag Spring Chinook at Shitike Creek Rotary Screw Trap |
|
06/30/2017 |
06/30/2017 |
PIT Tag 2,000 Juvenile O. mykiss at SC RST |
I: 158. O. mykiss: PIT Tag O. mykiss at Shitike Creek Rotary Screw Trap |
|
06/30/2017 |
06/30/2016 |
Collect and Upload PIT Tag Detection Data from FDX PIT Tag Antennae in WSR, SC, and Sherar's Fall |
J: 157. O. mykiss & Spring Chinook: Collect and Upload Data at WSR, SC and Sherars Falls Full Duplex Arrays |
|
06/30/2017 |
06/30/2017 |
Collect CHS PBT Samples |
K: 157. Spring Chinook: Collect Tissue Samples from BY 2015 Spring Chinook Salmon at RSTs |
|
06/30/2017 |
06/30/2017 |
Upload PIT Tagging Data to PTAGIS Database |
L: 159. O. mykiss & Spring Chinook: Upload PIT Tagging Data into PTAGIS |
|
06/30/2017 |
06/30/2017 |
Analyze Juvenile Outmigration Data |
M: 162. Analyze Spring Chinook and Steelhead Juvenile Outmigration |
|
06/30/2017 |
06/30/2017 |
Operate RBW in Shitike Creek |
N: 157. Spring Chinook & Steelhead: Operate Resistance Board Weir in Shitike Creek |
|
06/30/2017 |
06/30/2017 |
Conduct Steelhead Redd Counts on Established Index Reaches in Reservation Streams |
O: 157. Steelhead: Conduct Redd Counts in Established Index Reaches |
|
06/30/2017 |
06/30/2017 |
Select & Survey 20% of Non-Index Reaches in Reservation Streams for Steelhead Redds |
P: 157. Steelhead: Conduct Redd Counts Based on Rotating Panel Design |
|
06/30/2017 |
06/30/2017 |
Conduct Redd Counts/Spawning Ground Surveys in Reservation Streams |
Q: 157. Spring Chinook: Conduct Redd Counts in Established Index Reaches |
|
06/30/2017 |
06/30/2017 |
Select & Survey 20% of Non-Index Reaches in Reservation Streams for Spring Chinook Redds |
R: 157. Spring Chinook: Conduct Redd Counts Based on Rotating Panel Design |
|
06/30/2017 |
06/30/2017 |
Analyze and Report Adult Spring Chinook and Steelhead Escapement and Redd Count Data |
S: 162. Analyze Spring Chinook and Steelhead Adult Returns and Spawning Escapement |
|
06/30/2017 |
06/30/2017 |
Spring Chinook & Steelhead: Determine Upper Distribution of Fish |
T: 157. Spring Chinook & Steelhead: Determine Upper Distribution of Anandromous Fish |
|
06/30/2017 |
06/30/2017 |
Collect and Archive Tissue Samples from O. mykiss in Reservation Headwaters |
U: 157. O. Mykiss: Collect Genetic Tissue Samples from O. mykiss in Headwater Streams |
|
06/30/2017 |
06/30/2017 |
Survey Lower WSR for Species Assemblage |
V: 157. Multiple Species: Determine Species Assemblage in Lower Warm Springs River |
|
06/30/2017 |
06/30/2016 |
Analyze Salmonid Distribution Data |
W: 162. Analyze Salmonid Distribution in Reservation Streams |
|
06/30/2017 |
06/30/2017 |
Completed Annual Report |
X: 132. Prepare and Submit Progress Report for the Period January 2015 to December 31, 2015 |
|
03/31/2017 |
|
Completed Annual Report |
Y: 132. Prepare and Submit Progress Report for the Period January 2016 to December 31, 2016 |
|
05/15/2017 |
|
All Administrative Tasks Fulfilled with Timely Quality Products |
AA: 119. Manage Project |
|
06/30/2017 |
06/30/2017 |