Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 73854: 1998-021-00 EXP HOOD RIVER FISH HABITAT
Project Number:
Title:
Hood River Fish Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Gorge Hood 100.00%
Contract Number:
73854
Contract Title:
1998-021-00 EXP HOOD RIVER FISH HABITAT
Contract Continuation:
Previous: Next:
70046: 1998-021-00 EXP HOOD RIVER FISH HABITAT
  • 77168: 1998-021-00 EXP HOOD RIVER FISH HABITAT
Contract Status:
Closed
Contract Description:
ADMINISTRATIVE SUMMARY
The Confederated Tribes of the Warm Springs Reservation of Oregon
Hood River Production Program
6030 Dee Highway
Parkdale, Oregon 97041
Fisheries Program Manager:  Brad Houslet (541) 553-2039
Fiscal Officer: Arthur Mitchell (541) 553-3219
Hood River Production Program Coordinator:  Chris Brun (541) 352-3548
Contract Manager: Blayne Eineicher (541) 352-9326

FISCAL YEAR 2017

OBJECTIVE 1.  Provide coordination of all activities, administrative oversight, project planning and implementation activities

OBJECTIVE 2.  Coordinate and implement Hood River Watershed Action Plan.

OBJECTIVE 3. Implement West Fork Red Hill Phase II and Neal Creek large wood projects.

OBJECTIVE 4. Partner with Columbia Gorge Fruit Growers to evaluate pesticide spray drift vegetative buffers.

OBJECTIVE 5. Procure logs for out year LWD projects.

OBJECTIVE 6.  Pipe 2.5 mile of open irrigation ditch on EFID's Highline Canal and transfer water savings instream.

OBJECTIVE 7. Inspect previously implemented LWD project to determine if project goals have been met.

OBJECTIVE 8. Complete fourth year of EFID by-pass flow measurements to be used in minimum flow agreement.

OBJECTIVE 9. Maintain existing riparian exclosure fences.

OBJECTIVE 10. Evaluate City of The Dalles Dog River diversion and pipeline for water savings.

OBJECTIVE 11. Identify and develop stream restoration projects in the Hood River Fork watershed.

OBJECTIVE 12. Complete Evans Creek culvert replacement project.

OBJECTIVE 13. Facilitate completion of a  forbearance agreement with Farmers Irrigation District to leave water instream.
Account Type(s):
Expense
Contract Start Date:
10/01/2016
Contract End Date:
09/30/2017
Current Contract Value:
$352,360
Expenditures:
$352,360

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
All work complies with environmental regulations B: 165. Work with BPA on Environmental Compliance requirements. 09/30/2017 09/29/2017
Project administration requirements completed C: 119. Manage Project 09/30/2017 09/29/2017
Hood River Watershed Group support D: 114. Provide implementation support 09/29/2017 09/29/2017
Riparian fences maintained. E: 186. Maintain riparian fences 08/18/2017 07/14/2017
Riparian spray buffers inspected. F: 47. Inspect riparian spray buffer planting projects. 09/30/2017 09/29/2017
EFID by-pass reach instream flow maintained. G: 154. Record East Fork stream flows in the EFID by-pass reach 09/30/2017 09/29/2017
Progress towards a hydro water lease with an irrigation district. H: 154. Facilitate completion of forbearance agreement with FID to protect water instream. 09/30/2017
Powerdale water right transferred instream. I: 154. Powerdale instream water right transfer 09/30/2017 09/29/2017
Evaluation of Dog River pipeline for water loss. J: 154. Evaluate City of The Dalles Dog River diversion and pipeline for water savings. 09/30/2017
Eight LWD placement projects inspected. K: 186. Inspect large wood placement projects. 09/30/2017 09/29/2017
0.6 mile of fish habitat improved in West Fork Hood River L: 29. West Fork Red Hill Large Wood Placement – Phase II 09/29/2017 09/22/2017
300 logs procured and stockpiled. M: 29. Obtain logs for out year fish habitat restoration projects. 09/29/2017 09/29/2017
0.25 miles of fish habitat restored in Neal Creek N: 29. Neal Creek Large Wood Placement 09/29/2017
Maintain vegetation under Big Eddy Power to 4 ft. high where it crosses West Fork Hood River O: 198. BPA Powerline Vegetation Maintenance 08/11/2017 06/30/2017
Fish habitat project(s) developed for implementation in 2019. P: 114. Identify and develop instream fish habitat improvement projects in the Hood River watershed. 09/30/2017 09/29/2017
2.5 miles of open irrigation ditch piped. Q: 203. East Fork Irrigation District - Highline Lateral Canal Piping Project 09/29/2017 09/29/2017
72 ft. long open arch culvert installed underneath Hudson Rd. along Evans Creek. R: 184. Replace culvert in Evans Creek. 09/29/2017
FY 2016 Annual Progress Report complete S: 132. Prepare and submit annual report for FY 16 work 02/12/2017 02/09/2017

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 203 Install Water Conservation Measure
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 114 Identify and Select Projects
  • 4 instances of WE 154 Develop and Negotiate Water Right Transaction
Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 184 Install Fish Passage Structure
  • 2 instances of WE 114 Identify and Select Projects
  • 4 instances of WE 154 Develop and Negotiate Water Right Transaction
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened)
  • 1 instance of WE 198 Maintain Vegetation
  • 1 instance of WE 203 Install Water Conservation Measure
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 3 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 184 Install Fish Passage Structure
  • 2 instances of WE 114 Identify and Select Projects
  • 4 instances of WE 154 Develop and Negotiate Water Right Transaction
Lamprey, Pacific (Entosphenus tridentata)
  • 1 instance of WE 203 Install Water Conservation Measure
  • 1 instance of WE 47 Plant Vegetation
  • 3 instances of WE 154 Develop and Negotiate Water Right Transaction
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 10/01/2016
B 165 Work with BPA on Environmental Compliance requirements. 10/01/2016
C 119 Manage Project 10/01/2016
D 114 Provide implementation support 10/01/2016
E 186 Maintain riparian fences 10/03/2016
F 47 Inspect riparian spray buffer planting projects. 10/03/2016
G 154 Record East Fork stream flows in the EFID by-pass reach 10/01/2016
H 154 Facilitate completion of forbearance agreement with FID to protect water instream. 10/01/2016
I 154 Powerdale instream water right transfer 10/01/2016
J 154 Evaluate City of The Dalles Dog River diversion and pipeline for water savings. 10/01/2016
K 186 Inspect large wood placement projects. 10/03/2016
L 29 West Fork Red Hill Large Wood Placement – Phase II 10/03/2016
M 29 Obtain logs for out year fish habitat restoration projects. 10/03/2016
N 29 Neal Creek Large Wood Placement 08/08/2017
O 198 BPA Powerline Vegetation Maintenance 10/03/2016
P 114 Identify and develop instream fish habitat improvement projects in the Hood River watershed. 10/01/2016
Q 203 East Fork Irrigation District - Highline Lateral Canal Piping Project
R 184 Replace culvert in Evans Creek. 01/31/2017
S 132 Prepare and submit annual report for FY 16 work 10/01/2016