Contract 73982 REL 57: 1988-022-00 EXP UMATILLA & WALLA WALLA FISH PASSAGE OPERATIONS
Project Number:
Title:
Umatilla Fish Passage Operations
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Umatilla 100.00%
Contract Number:
73982 REL 57
Contract Title:
1988-022-00 EXP UMATILLA & WALLA WALLA FISH PASSAGE OPERATIONS
Contract Continuation:
Previous: Next:
73982 REL 29: 1988-022-00 EXP UMATILLA & WALLA WALLA FISH PASSAGE OPERATIONS
  • 73982 REL 92: 1988-022-00 EXP UMATILLA FISH PASSAGE OPERATIONS
Contract Status:
Closed
Contract Description:
UPDATE FOR THIS CONTRACT

Project/Contract Goal:  The long term goal of the 2000-033-00 project, is to increase adult returns of spring Chinook salmon, summer steelhead, and bull trout to the Walla Walla River annually by increasing the survival of migrating juvenile and adult salmonids.  
Our approach is focused on three areas: 1) Monitoring of flow and passage conditions; 2) Operation of passage facilities, trapping facilities, and transport equipment; and 3) Coordination of passage and trapping facilities, transportation, and flow enhancement operations.  

Location of Project:  The project conducts operations primarily within the mainstem Walla Walla River basin and Mill Creek in both Washington and Oregon.  The major BPA facilities associated with the project are located at the Garden City/Lowden II Canal (river mile 31.0), Gardena Farms (formerly Burlingame) Canal (river mile 36.0), Nursery Bridge Dam (river mile 46.0), and Little Walla Walla River (river mile 47.0).  In addition, the project monitors additional sites in the lower Touchet River, Walla Walla River, and Mill Creek.
Account Type(s):
Expense
Contract Start Date:
01/01/2019
Contract End Date:
12/31/2019
Current Contract Value:
$528,132
Expenditures:
$528,132

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
BPA project administration requirements complete A: 119. Project Management 12/31/2019 12/31/2019
Environmental compliance documentation B: 165. Environmental Compliance 12/31/2019 12/31/2019
Coordinate Passage Facility Operations-Umatilla Basin D: 191. Coordinate Passage Facility Operations-Umatilla Basin 12/31/2019 12/31/2019
Fish counts and transport information. E: 157. Adult Return and Transport Data-Umatilla Basin 12/31/2019 12/31/2019
Coordination on adequate migration conditions F: 191. Coordinate Umatilla Passage Program-McKay Release 12/31/2019 12/31/2019
Provide Transportation Assistance G: 66. Provide Transportation Assistance-Umatilla Basin 12/31/2019 12/31/2019
Maintenance of adult and juvenile transportation equipment H: 61. Maintain and Operate Hauling Equipment-Umatilla and Walla Walla Basin 12/31/2019 12/31/2019
Provide technical comments for fish passage improvement efforts I: 122. Provide Facility Design Technical Review-Umatilla Basin 12/31/2019 12/31/2019
CTUIR Umatilla Basin Annual Report (10/01/2018 - 09/30/2019) J: 132. Umatilla Basin: CTUIR Annual Report (10-1-18 - 9-30-19) 12/31/2019 12/31/2019
Provide broodstock for artificial propagation programs. K: 66. Provide broodstock for artificial production program-Umatilla Basin 12/31/2019 12/31/2019
Safe transport of adult and juvenile fish L: 28. Transport of Upstream And Downstream Migrants-Umatilla Basin 12/31/2019 12/31/2019
Provide Input/Information As Needed to ODFW for Umatilla Hatchery AOP M: 174. Provide Input/Information as needed for Umatilla Hatchery AOP 09/30/2019 09/30/2019
Safe transport of fish collected during salvage operations N: 28. Coordinate and complete salvage operations-Walla Walla Basin 12/31/2019 12/31/2019
Coordinate passage facility operations O: 191. Coordinate Passage Facility Operations-Walla Walla Basin 12/31/2019 12/31/2019
Implement Actions for Emergency Low Flows in the Walla Walla River P: 28. Salvage and Rescue Actions for Low Flow Emergency Walla Walla River Basin 06/30/2019 06/30/2019
Finalize AOP for 2018-2019 operations and distribute to cooperators and BPA COR Q: 174. Fish Passage Annual Operating Plan (AOP)-Walla Walla Basin 09/30/2019 09/30/2019
Provide review and comment through project year. R: 122. Provide Facility Design Technical Review-Walla Walla Basin 12/31/2019 12/31/2019
CTUIR Walla Walla Annual Report (10/01/2018 - 09/30/2019) S: 132. Walla Walla Basin: CTUIR Annual Report (10-1-18 - 9-30-19) 12/31/2019 12/31/2019
Submit BiOp RPA Report in Taurus T: 202. BiOp RPA Report for CY 2019 03/15/2019 03/15/2019
Monthly Status Reports U: 141. Other Reports for BPA 12/31/2019 12/31/2019

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 3 instances of WE 28 Trap and Haul
  • 2 instances of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 2 instances of WE 122 Provide Technical Review and Recommendation
  • 2 instances of WE 174 Produce Plan
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU
  • 1 instance of WE 174 Produce Plan
Coho (O. kisutch) - Unspecified Population
  • 2 instances of WE 28 Trap and Haul
  • 2 instances of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 3 instances of WE 28 Trap and Haul
  • 2 instances of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 2 instances of WE 122 Provide Technical Review and Recommendation
  • 2 instances of WE 174 Produce Plan
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Project Management 01/01/2019
B 165 Environmental Compliance 01/01/2019
C 185 Periodic Status Reports for BPA 01/01/2019
D 191 Coordinate Passage Facility Operations-Umatilla Basin 01/01/2019
E 157 Adult Return and Transport Data-Umatilla Basin 11/01/2018
F 191 Coordinate Umatilla Passage Program-McKay Release 01/01/2019
G 66 Provide Transportation Assistance-Umatilla Basin 11/05/2018
H 61 Maintain and Operate Hauling Equipment-Umatilla and Walla Walla Basin 11/05/2018
I 122 Provide Facility Design Technical Review-Umatilla Basin 01/01/2019
J 132 Umatilla Basin: CTUIR Annual Report (10-1-18 - 9-30-19) 01/01/2019
K 66 Provide broodstock for artificial production program-Umatilla Basin 11/05/2018
L 28 Transport of Upstream And Downstream Migrants-Umatilla Basin 06/24/2019
M 174 Provide Input/Information as needed for Umatilla Hatchery AOP 01/01/2019
N 28 Coordinate and complete salvage operations-Walla Walla Basin 01/01/2019
O 191 Coordinate Passage Facility Operations-Walla Walla Basin 01/01/2019
P 28 Salvage and Rescue Actions for Low Flow Emergency Walla Walla River Basin 01/01/2019
Q 174 Fish Passage Annual Operating Plan (AOP)-Walla Walla Basin 01/01/2019
R 122 Provide Facility Design Technical Review-Walla Walla Basin 01/01/2019
S 132 Walla Walla Basin: CTUIR Annual Report (10-1-18 - 9-30-19) 01/01/2019
T 202 BiOp RPA Report for CY 2019
U 141 Other Reports for BPA 01/01/2019