Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 83308: 2003-013-01 EXP. WATER ENTITIY - CBWTP
Project Number:
Title:
Water Entity - CBWTP
Stage:
Implementation
Area:
Province Subbasin %
Basinwide - 100.00%
Contract Number:
83308
Contract Title:
2003-013-01 EXP. WATER ENTITIY - CBWTP
Contract Continuation:
Previous: Next:
80638: 2002-013-01 EXP NFWF WATER ENTITY - CBWTP
  • 86032: 2002-013-01 EXP WATER ENTITY - CBWTP
Contract Status:
Closed
Contract Description:
The primary focus of the CBWTP is to fund water transactions that restore streamflow on ecologically-significant Columbia Basin tributaries.  The CBWTP is administered through a cooperative agreement between BPA and the National Fish and Wildlife Foundation (NFWF).  
Subbasin plans and other habitat assessments throughout the Columbia Basin cite inadequate streamflows as a key factor limiting the productivity of both anadromous and resident fish species.  Water transactions provide an effective and appropriate response to this key limiting factor.  Restored streamflow benefit multiple fish species, particularly Chinook salmon, Steelhead and Bull trout.  
The CBWTP works through ten qualified local entities (QLEs).  The QLEs include four state water agencies and six nonprofit organizations.  These QLEs receive funds to implement and monitor water transactions in multiple priority watersheds throughout the Columbia Basin.  
Since 2002, over 12 million acre feet has been dedicated instream through transactions. These transactions have included a number of innovative methods, including split-season leases, source switches, permanent purchases and water produced through significant capital investments in irrigation efficiency projects.  The term of these deals has varied from short-term to permanent.  
Account Type(s):
Expense
Contract Start Date:
10/01/2019
Contract End Date:
09/30/2020
Current Contract Value:
$3,137,305
Expenditures:
$3,137,305

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
CRB
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Outreach completed B: 99. NFWF - Public Presentations 09/30/2020 09/30/2020
Work with contractors complete C: 119. NFWF - Subcontracting 09/30/2020 09/30/2020
Annual and monthly invoices issued and recorded D: 119. NFWF - Task Invoicing and Recordkeeping 09/30/2020 09/30/2020
Transactions review per procedures E: 122. NFWF - Transaction Proposals, Solicitation, and Recommendation 09/30/2020 09/30/2020
Completed Reports F: 132. NFWF - Annual Progress Reports 09/30/2020 09/30/2020
Reports completed G: 141. Other Reports for BPA 09/30/2020 09/30/2020
Data collected, captured, created and/or validated H: 157. NFWF - Collect, Generate, and Validate field Data for Water Transactions 09/30/2020 09/30/2020
Maintenance complete I: 160. NFWF - Proposal and Data Management Tool and Website Maintenance 09/30/2020 09/30/2020
Compliance assistance complete J: 165. NFWF & QLEs - Environmental Compliance 09/30/2020 09/30/2020
Coordination Completed K: 189. NFWF - Qualified Local Entity Coordination and Support 09/30/2020 09/30/2020
Presentations and outreach completed L: 99. QLEs - Outreach and Education 09/30/2020 09/30/2020
Administrative tasks completed M: 119. QLEs - Manage and Administer Projects 09/30/2020 09/30/2020
Gauges installed N: 148. QLEs - Install Flow Measuring Device 09/30/2020 09/30/2020
Data collected, captured, created and generated O: 157. QLEs - Collect, Generate, and Validate Field Data for Water Transactions 09/30/2020 09/30/2020
Planning completed P: 174. QLEs - Strategic planning 09/30/2020 09/30/2020
Meetings completed Q: 189. QLEs - Regional coordination and learning 09/30/2020 09/30/2020
Local coordination R: 191. QLEs - Local watershed coordination 09/30/2020 09/30/2020
Identify and select water transactions for development S: 114. CFC - Identify and Select Water Transactions for FY2019 Development 09/30/2020 09/30/2020
Water transactions proposed and/or completed T: 154. QLEs - Develop water transactions for implementation 09/30/2020 09/30/2020
Identify and select water transactions for development U: 114. DRC - Identify and Select Water Transactions for FY2019 Development 09/30/2020 09/30/2020
Identify and select water transactions for development V: 114. IDWR - Identify and Select Water Transactions for FY2019 Development 09/30/2020 09/30/2020
Identify and select water transactions for development W: 114. TFT - Identify and Select Water Transactions for FY12019 Development 09/30/2020 09/30/2020
Identify and select water transactions for development X: 114. TU-MWP - Identify and Select Water Transactions for FY2019 Development 09/30/2020 09/30/2020
Identify and select water transactions for development Y: 114. TU-WWP - Identify and Select Water Transactions for FY2019 Development 09/30/2020 09/30/2020
Identify and select water transactions for development Z: 114. WWT - Identify and Select Water Transactions for FY2019 Development 09/30/2020 09/30/2020
Transaction Complete AA: 164. NFWF/Main -- Water Transactions TBD 09/30/2020 09/30/2020
Transaction Complete AB: 164. 263d-12 TFT (Jacobs / Roberts Cr Coop) 09/30/2020 09/01/2020
Transaction complete AC: 164. 438f-19 TFT (2019-Fifteenmile Creek-Leasing) 09/30/2020 05/01/2020
Transaction complete AD: 164. 426d-19 TFT (2018-Reynolds Creek-DG) 09/30/2020 05/01/2020
Transaction Complete AE: 164. 386d-15 (Sauerkraut 20 Yr Lease_2018_2037) 09/30/2020 09/30/2020
Transaction Complete AF: 164. 445c-17 TFT (UJD_BeechCrk_BPT_2018-2027) 09/30/2020 05/01/2020
Submit Monthly invoices as necessary AG: 119. (Umatilla) Umatilla QLE - Manage and Administer Projects as part of CBWTP 09/30/2020 09/30/2020
Identify and select water transactions for development AH: 114. (Umatilla) WWT - Umatilla QLE - Identify and Select Water Transactions for Development 09/30/2020 09/30/2020
Data collected, captured, created and/or validated AI: 157. (Umatilla) Umatilla QLE - Collect/Generate/Validate Field Data for Water 09/30/2020 09/30/2020
Water transactions proposed and/or completed AJ: 154. (Umatilla) Umatilla QLE - Develop and Negotiate Water Right Transactions 09/30/2020 09/30/2020
Planning completed AK: 174. (Umatilla) Umatilla QLE - Strategic Planning 09/30/2020 09/30/2020
Meetings completed AL: 189. (Umatilla) Umatilla QLE - Regional Coordination 09/30/2020 09/30/2020
Local coordination AM: 191. (Umatilla) Umatilla QLE - Local watershed coordination 09/30/2020 09/30/2020
Presentations and outreach completed AN: 99. (Umatilla) Umatilla QLE - Provide outreach and education - event/conference 09/30/2020 09/30/2020
Gauges installed AO: 148. (Umatilla) Umatilla QLE - Install flow measuring device at [name specific location] 09/30/2020 09/30/2020
Transaction Complete AP: 164. (Umatilla) 330f-19 TFT (2019-Umatilla River-McKay Reservoir_JM) 09/30/2020 09/30/2020
Transaction Complete AR: 164. (Umatilla) 464c-18 WWT (Walla Walla River No. 2 (5-Year Lease)) 09/30/2020 09/01/2020
Transaction complete AS: 164. (Umatilla) 468b-18 TFT (UGR_CatherineCrk_RH_2018-2022) 09/30/2020 02/18/2020
Transaction complete AT: 164. (Umatilla) 467-17 TFT (WW_NFWallaWalla_LS_2017) 09/30/2020 07/15/2020
Transaction Complete AU: 164. (Umatilla) 441d-17 TFT (UM_McKayReservoir_LeasingProgram_2017a (5yr)) 09/30/2020 09/30/2020
Transaction complete AV: 164. (Umatilla) 317e-16 TFT (UGR_CatherineCrk_JS_2017) 09/30/2020 02/18/2020
Administrative tasks completed AW: 119. (Umatilla) State Agency - Manage and Administer Projects 09/30/2020 09/30/2020
Identify and select water transactions for development AX: 114. (Umatilla) TU-WWP - Umatilla QLE - Identify and Select Water Transactions for Development 09/30/2020 09/30/2020
Work with contractors complete AY: 119. (Umatilla) Umatilla - NFWF Subcontracting 09/30/2020 09/30/2020
Reports completed AZ: 141. Other Reports for BPA 09/30/2020 09/30/2020
Transaction Complete BA: 164. NFWF/Umatilla -- Water Transactions TBD 09/30/2020 09/30/2020
Transaction Complete BB: 164. 449-16 (TU-WWP-2016-McCartney Creek -NC) 09/30/2020 09/02/2020
Transaction Complete BC: 164. 461-16 (WWT-2016-Wilson Creek-Wilson Creek No. 1 -Moore) 09/30/2020 05/21/2020
Transaction Complete BD: 164. 285b-17 (IWRB-2020-Big Timber Creek-LLP) 09/30/2020 09/30/2020
Transaction Complete BE: 164. 381e-17 (WWT-2017-Big Creek-1a option agreement) 09/30/2020 06/22/2020
Transaction Complete BF: 164. 477-18 (IWRB-2019-Teton River-TWUA) 09/30/2020 09/30/2020
Transaction Complete BG: 164. 484b-20 (TFT-2020-Catherine Creek-TM) 09/30/2020 07/15/2020
Transaction Complete BH: 164. 505-20 (TU-MWP-2019-Ninemile Creek -AP) 09/30/2020 05/07/2020
Transaction Complete BI: 164. 72p-19 (IWRB-2020-Lemhi River-annual 2020_2022) 09/30/2020 09/30/2020
Transaction Complete BJ: 164. 127i-19 (IWRB-2020-Morgan Creek -RJ-DH) 09/30/2020 09/30/2020
Transaction Complete BK: 164. 482-18 (IWRB-2018-Knapp Creek-KnappCreek HH Acquisition) 09/30/2020 04/15/2020
Transaction Complete BL: 164. 161b-19 (CFC-2019-Lolo Creek-KH Acquisition) 09/30/2020 05/15/2020
Transaction Complete BM: 164. 92i-20 (TFT-2020-Lostine River -MFA 2020-2021) 09/30/2020 09/30/2020
Transaction Complete BN: 164. 492b-20 (TFT-2020-Bear creek-LeaseBank) 09/30/2020 09/01/2020
Transaction Complete BO: 164. 447f-20 (TFT-2020-Lostine -WW 2020-2023) 09/30/2020 08/03/2020
Transaction Complete BP: 164. (Umatilla) 502-20 (TU-WWP-2020-Wallowa River-WH) 09/30/2020 09/30/2020
Transaction Complete BQ: 164. 501-20 (IWRB-2019-Canyon Creek-CCCC - Teton Basin) 09/30/2020 09/30/2020
Transaction Complete BR: 164. 71q-20 (DRC-2020-Middle Deschutes River and Tributaries-AWLP) 09/30/2020 09/30/2020
Transaction Complete BS: 164. (Umatilla) 483c-20 (TFT-2020-Catherine Creek-RF) 09/30/2020 07/15/2020
Transaction Complete BT: 164. 438g-20 (TFT-2019-Fifteenmile Creek-DP) 09/30/2020 07/15/2020
Transaction Complete BU: 164. (Umatilla) 242i-20 (TU-WWP-2020-Birch Creek-Lease-JW) 09/30/2020 09/30/2020
Transaction Complete BV: 164. (Umatilla) 488b-20 (TFT-2020-Catherine Creek-BuffaloPeak) 09/30/2020 08/03/2020
Transaction Complete BW: 164. 491b-20 (DRC-2020-Trout Creek-JH) 09/30/2020 09/30/2020
Transaction Complete BX: 164. (Umatilla) 316e-20 (TFT-2020-Catherine Creek-TM-Pivot) 09/30/2020 07/15/2020
Transaction Complete BY: 164. (Umatilla) 481d-20 (TU-WWP-2020-Birch Creek-AND-TJ) 09/30/2020 09/30/2020
Transaction Complete BZ: 164. 511-20 (TU-MWP-2020-Harvey Creek-HCR) 09/30/2020 09/30/2020
Transaction Complete CA: 164. (Umatilla) 457f-20 (TU-WWP-2020-Walla Walla River-WWRID) 09/30/2020 09/30/2020
Transaction Complete CB: 164. 503-20 (TFT-2020-Lostine -AD-2020) 09/30/2020 08/03/2020
Transaction Complete CC: 164. 512-20 (TFT-2020-Wallowa River-SW) 09/30/2020 09/01/2020
Transaction Complete CD: 164. 437f-20 (TFT-2019-Rock Creek-AR) 09/30/2020 09/30/2020
Transaction Complete CE: 164. 428c-20 (TFT-2019-Reynolds Creek-MH) 09/30/2020 07/15/2020
Transaction complete CF: 164. 489-19 (TFT-2019-Lostine river-SSL_BJ) 09/30/2020 09/01/2020

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Deschutes River Summer/Fall ESU
  • 1 instance of WE 164 Acquire Water Instream
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 2 instances of WE 114 Identify and Select Projects
  • 2 instances of WE 174 Produce Plan
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 10 instances of WE 164 Acquire Water Instream
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened)
  • 1 instance of WE 114 Identify and Select Projects
  • 2 instances of WE 174 Produce Plan
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 2 instances of WE 114 Identify and Select Projects
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 19 instances of WE 164 Acquire Water Instream
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 2 instances of WE 174 Produce Plan
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 164 Acquire Water Instream
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU
  • 2 instances of WE 174 Produce Plan
Coho (O. kisutch) - Unspecified Population
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 6 instances of WE 164 Acquire Water Instream
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 3 instances of WE 114 Identify and Select Projects
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 2 instances of WE 174 Produce Plan
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 19 instances of WE 164 Acquire Water Instream
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 2 instances of WE 114 Identify and Select Projects
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 18 instances of WE 164 Acquire Water Instream
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 2 instances of WE 174 Produce Plan
  • 1 instance of WE 164 Acquire Water Instream
Lamprey, Pacific (Entosphenus tridentata)
  • 2 instances of WE 174 Produce Plan
  • 8 instances of WE 164 Acquire Water Instream
Cutthroat Trout, Westslope (O. c. lewisi)
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 2 instances of WE 148 Install Flow Measuring Device
  • 3 instances of WE 164 Acquire Water Instream
Cutthroat Trout, Yellowstone (O. c. bouvieri)
  • 2 instances of WE 164 Acquire Water Instream
Trout, Brook (Salvelinus fontinalis)
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 2 instances of WE 148 Install Flow Measuring Device
Trout, Bull (S. confluentus) (Threatened)
  • 4 instances of WE 114 Identify and Select Projects
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 2 instances of WE 148 Install Flow Measuring Device
  • 2 instances of WE 154 Develop and Negotiate Water Right Transaction
  • 2 instances of WE 164 Acquire Water Instream
Trout, Rainbow (Oncorhynchus mykiss)
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 2 instances of WE 148 Install Flow Measuring Device
Trout, Interior Redband (O. mykiss gairdnerii)
  • 1 instance of WE 164 Acquire Water Instream

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 99 NFWF - Public Presentations
C 119 NFWF - Subcontracting
D 119 NFWF - Task Invoicing and Recordkeeping
E 122 NFWF - Transaction Proposals, Solicitation, and Recommendation
F 132 NFWF - Annual Progress Reports
G 141 Other Reports for BPA
H 157 NFWF - Collect, Generate, and Validate field Data for Water Transactions 10/28/2020
I 160 NFWF - Proposal and Data Management Tool and Website Maintenance
J 165 NFWF & QLEs - Environmental Compliance
K 189 NFWF - Qualified Local Entity Coordination and Support
L 99 QLEs - Outreach and Education
M 119 QLEs - Manage and Administer Projects
N 148 QLEs - Install Flow Measuring Device 10/28/2020
O 157 QLEs - Collect, Generate, and Validate Field Data for Water Transactions 10/28/2020
P 174 QLEs - Strategic planning 10/28/2020
Q 189 QLEs - Regional coordination and learning
R 191 QLEs - Local watershed coordination
S 114 CFC - Identify and Select Water Transactions for FY2019 Development
T 154 QLEs - Develop water transactions for implementation
U 114 DRC - Identify and Select Water Transactions for FY2019 Development
V 114 IDWR - Identify and Select Water Transactions for FY2019 Development
W 114 TFT - Identify and Select Water Transactions for FY12019 Development
X 114 TU-MWP - Identify and Select Water Transactions for FY2019 Development
Y 114 TU-WWP - Identify and Select Water Transactions for FY2019 Development
Z 114 WWT - Identify and Select Water Transactions for FY2019 Development
AA 164 NFWF/Main -- Water Transactions TBD 10/28/2020
AB 164 263d-12 TFT (Jacobs / Roberts Cr Coop) 10/28/2020
AC 164 438f-19 TFT (2019-Fifteenmile Creek-Leasing) 10/28/2020
AD 164 426d-19 TFT (2018-Reynolds Creek-DG) 10/28/2020
AE 164 386d-15 (Sauerkraut 20 Yr Lease_2018_2037) 10/28/2020
AF 164 445c-17 TFT (UJD_BeechCrk_BPT_2018-2027) 10/28/2020
AG 119 (Umatilla) Umatilla QLE - Manage and Administer Projects as part of CBWTP
AH 114 (Umatilla) WWT - Umatilla QLE - Identify and Select Water Transactions for Development
AI 157 (Umatilla) Umatilla QLE - Collect/Generate/Validate Field Data for Water 10/28/2020
AJ 154 (Umatilla) Umatilla QLE - Develop and Negotiate Water Right Transactions
AK 174 (Umatilla) Umatilla QLE - Strategic Planning 10/28/2020
AL 189 (Umatilla) Umatilla QLE - Regional Coordination
AM 191 (Umatilla) Umatilla QLE - Local watershed coordination
AN 99 (Umatilla) Umatilla QLE - Provide outreach and education - event/conference
AO 148 (Umatilla) Umatilla QLE - Install flow measuring device at [name specific location] 10/28/2020
AP 164 (Umatilla) 330f-19 TFT (2019-Umatilla River-McKay Reservoir_JM) 10/28/2020
AQ 164 (Umatilla) 420f-19 TFT (2019-Catherine Creek-GS) 10/28/2020
AR 164 (Umatilla) 464c-18 WWT (Walla Walla River No. 2 (5-Year Lease)) 10/28/2020
AS 164 (Umatilla) 468b-18 TFT (UGR_CatherineCrk_RH_2018-2022) 10/28/2020
AT 164 (Umatilla) 467-17 TFT (WW_NFWallaWalla_LS_2017) 10/28/2020
AU 164 (Umatilla) 441d-17 TFT (UM_McKayReservoir_LeasingProgram_2017a (5yr)) 10/28/2020
AV 164 (Umatilla) 317e-16 TFT (UGR_CatherineCrk_JS_2017) 10/28/2020
AW 119 (Umatilla) State Agency - Manage and Administer Projects
AX 114 (Umatilla) TU-WWP - Umatilla QLE - Identify and Select Water Transactions for Development
AY 119 (Umatilla) Umatilla - NFWF Subcontracting
AZ 141 Other Reports for BPA
BA 164 NFWF/Umatilla -- Water Transactions TBD 10/28/2020
BB 164 449-16 (TU-WWP-2016-McCartney Creek -NC) 10/28/2020
BC 164 461-16 (WWT-2016-Wilson Creek-Wilson Creek No. 1 -Moore) 10/28/2020
BD 164 285b-17 (IWRB-2020-Big Timber Creek-LLP) 10/28/2020
BE 164 381e-17 (WWT-2017-Big Creek-1a option agreement) 10/28/2020
BF 164 477-18 (IWRB-2019-Teton River-TWUA) 10/28/2020
BG 164 484b-20 (TFT-2020-Catherine Creek-TM) 10/28/2020
BH 164 505-20 (TU-MWP-2019-Ninemile Creek -AP) 10/28/2020
BI 164 72p-19 (IWRB-2020-Lemhi River-annual 2020_2022) 10/28/2020
BJ 164 127i-19 (IWRB-2020-Morgan Creek -RJ-DH) 10/28/2020
BK 164 482-18 (IWRB-2018-Knapp Creek-KnappCreek HH Acquisition) 10/28/2020
BL 164 161b-19 (CFC-2019-Lolo Creek-KH Acquisition) 10/28/2020
BM 164 92i-20 (TFT-2020-Lostine River -MFA 2020-2021) 10/28/2020
BN 164 492b-20 (TFT-2020-Bear creek-LeaseBank) 10/28/2020
BO 164 447f-20 (TFT-2020-Lostine -WW 2020-2023) 10/28/2020
BP 164 (Umatilla) 502-20 (TU-WWP-2020-Wallowa River-WH) 10/28/2020
BQ 164 501-20 (IWRB-2019-Canyon Creek-CCCC - Teton Basin) 10/28/2020
BR 164 71q-20 (DRC-2020-Middle Deschutes River and Tributaries-AWLP) 10/28/2020
BS 164 (Umatilla) 483c-20 (TFT-2020-Catherine Creek-RF) 10/28/2020
BT 164 438g-20 (TFT-2019-Fifteenmile Creek-DP) 10/28/2020
BU 164 (Umatilla) 242i-20 (TU-WWP-2020-Birch Creek-Lease-JW) 10/28/2020
BV 164 (Umatilla) 488b-20 (TFT-2020-Catherine Creek-BuffaloPeak) 10/28/2020
BW 164 491b-20 (DRC-2020-Trout Creek-JH) 10/28/2020
BX 164 (Umatilla) 316e-20 (TFT-2020-Catherine Creek-TM-Pivot) 10/28/2020
BY 164 (Umatilla) 481d-20 (TU-WWP-2020-Birch Creek-AND-TJ) 10/28/2020
BZ 164 511-20 (TU-MWP-2020-Harvey Creek-HCR) 10/28/2020
CA 164 (Umatilla) 457f-20 (TU-WWP-2020-Walla Walla River-WWRID) 10/28/2020
CB 164 503-20 (TFT-2020-Lostine -AD-2020) 10/28/2020
CC 164 512-20 (TFT-2020-Wallowa River-SW) 10/28/2020
CD 164 437f-20 (TFT-2019-Rock Creek-AR) 10/28/2020
CE 164 428c-20 (TFT-2019-Reynolds Creek-MH) 10/28/2020
CF 164 489-19 (TFT-2019-Lostine river-SSL_BJ) 10/28/2020