Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 83750: 2007-396-00 EXP WALLA WALLA BASINWIDE TRIB PASSAGE
Project Number:
Title:
Walla Walla Basinwide Tributary Passage and Flow
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Walla Walla 100.00%
Contract Number:
83750
Contract Title:
2007-396-00 EXP WALLA WALLA BASINWIDE TRIB PASSAGE
Contract Continuation:
Previous: Next:
80649: 2007-396-00 EXP WALLA WALLA BASINWIDE TRIB PASSAGE
  • 86499: 2007-396-00 EXP WALLA WALLA BASINWIDE TRIB PASSAGE
Contract Status:
Closed
Contract Description:
This contract will work to improve stream flows and reduce fish passage barriers in the Walla Walla Basin for the migration and rearing of summer steelhead, spring Chinook salmon, and bull trout. Limited stream flows and fish passage barriers are two primary limiting factors for aquatic species in the Walla Walla Basin. Under this contract the Walla Walla Basin Watershed Council (WWBWC) will address several fish passage issues with the construction of the Lampson Habitat Side Channel Entrance Construction, development of final designs and permitting for two North Fork Walla Walla Push Up Dams alternatives, an alternatives assessment and preliminary designs for the Upper Couse Creek Fish Passage at Blue Mountain Stations issue, and the Upper Walla Walla River ground-based Habitat Assessment.

The WWBWC identified these projects through staff conversations with basin partners, working with property owners, and referring to fish recovery plans. WWBWC held a basin-wide meeting which included representatives from BPA, CTUIR, ODFW, WDFW, USFWS, NOAA, OWRD, local irrigation districts, and other interested parties to review identified projects. These projects were identified as priorities and selected for BPA funded implementation.

WWBWC and the partners mentioned above will begin adding their most current, summarized empirical biological and physical habitat data sets to a GIS platform, such as Arc GIS Online, to determine prioritiy areas and actions at the watershed level.  Areas that contain focal fish species and life stages will be the highest priority.  Specific habitat improvement actions will be prioritized based on their ability to meet the life stage specific needs of the fish species, such as holding, spawning, summer rearing, winter rearing, and juvenile emigration.

The FY 2021 contract will include a structured approach, based on the available empirical biological and physical habitat data, to collaboratively analyze the data to determine priority areas and actions.  This evidence based prioritization approach will be attached to the contract and modified over time as new data become available and as projects are implemented.
Account Type(s):
Expense
Contract Start Date:
11/01/2019
Contract End Date:
10/31/2020
Current Contract Value:
$662,171
Expenditures:
$662,171

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
All administrative tasks fulfilled with timely quality products B: 119. Oversight of Project Activities 10/31/2020 10/30/2020
Environmental Compliance complete C: 165. Environmental Compliance Documentation for all Exp actions 10/31/2020 10/30/2020
Annual Progress Report D: 132. Annual Progress Report (11-1-18 to 10-31-19) 07/31/2020 07/30/2020
Youth and Adult Presentations E: 99. Youth and adult presentations 10/31/2020
Upper Walla Walla Ground-based Habitat Assessment Complete F: 115. Upper Walla Walla River ground-based Habitat Assessment 10/31/2020 10/30/2020
North Fork WW Push Up Dams Fish Passage Final Designs, Wetlands Delineations, and Permitting - NF7 G: 175. North Fork WW Push Up Dams Fish Passage Final Designs, Wetlands Delineations, and Permitting - NF7 10/31/2020 10/30/2020
North Fork WW Push Up Dams Fish Passage Final Designs, Wetlands Delineations, and Permitting - NF8 H: 175. North Fork WW Push Up Dams Fish Passage Final Designs, Wetlands Delineations, and Permitting - NF8 10/31/2020 10/31/2020
Upper Couse Creek Fish Passage at Blue Mountain Station Road Alternatives Assessment/Initial Design I: 175. Upper Couse Creek Fish Passage at Blue Mountain Station Road Alternatives Assessment/Initial Design 10/31/2020 10/30/2020
Completed channel construction J: 30. Lampson Habitat Side Channel Entrance Construction - Side channels construction 10/30/2020 10/30/2020
Complete aquatic complexity installation K: 29. Lampson Habitat Side Channel Entrance Construction - aquatic complexity installation 10/30/2020 10/30/2020
Surface Water Data collected for fish passage and habitat water monitoring L: 157. Collect Surface Water Data for Fish Passage and Flow Restoration 10/31/2020 10/30/2020
Produce accessible, error-checked datasets M: 157. Collect Water Temperature Data for Fish Passage and Flow Restoration 10/31/2020 10/30/2020
Updated WWBWC Database N: 160. Maintain Surface Water Database for Water Monitoring 10/31/2020 10/30/2020
Maintain water temperature database O: 160. Maintain Water Temperature Database for Fish Habitat Monitoring 10/31/2020 10/30/2020
Results on the success of the Recharge Project, On-farm Efficiency, and Water Management P: 162. Analyze Surface Water Data for Fish Habitat Monitoring 10/31/2020 10/30/2020
Results on the success of the Recharge Project, On-farm Efficiency, and Water Management Q: 162. Analyze Water Temperature Data for Fish Habitat Monitoring 10/31/2020 10/30/2020
Evidence Based Prioritization Approach R: 191. Walla Walla basin watershed coordination 10/31/2020 10/30/2020
Evidence Based Prioritization Approach S: 114. Identify and select projects for Walla Walla Basin 06/15/2020 06/30/2020

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 3 instances of WE 175 Produce Design
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 2 instances of WE 162 Analyze/Interpret Data
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 114 Identify and Select Projects
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 3 instances of WE 175 Produce Design
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 2 instances of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 114 Identify and Select Projects
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 3 instances of WE 175 Produce Design
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 2 instances of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 119 Oversight of Project Activities
C 165 Environmental Compliance Documentation for all Exp actions
D 132 Annual Progress Report (11-1-18 to 10-31-19)
E 99 Youth and adult presentations
F 115 Upper Walla Walla River ground-based Habitat Assessment 07/02/2020
G 175 North Fork WW Push Up Dams Fish Passage Final Designs, Wetlands Delineations, and Permitting - NF7 07/02/2020
H 175 North Fork WW Push Up Dams Fish Passage Final Designs, Wetlands Delineations, and Permitting - NF8 07/02/2020
I 175 Upper Couse Creek Fish Passage at Blue Mountain Station Road Alternatives Assessment/Initial Design 07/02/2020
J 30 Lampson Habitat Side Channel Entrance Construction - Side channels construction 07/27/2020
K 29 Lampson Habitat Side Channel Entrance Construction - aquatic complexity installation 07/27/2020
L 157 Collect Surface Water Data for Fish Passage and Flow Restoration 07/02/2020
M 157 Collect Water Temperature Data for Fish Passage and Flow Restoration 07/02/2020
N 160 Maintain Surface Water Database for Water Monitoring
O 160 Maintain Water Temperature Database for Fish Habitat Monitoring
P 162 Analyze Surface Water Data for Fish Habitat Monitoring
Q 162 Analyze Water Temperature Data for Fish Habitat Monitoring
R 191 Walla Walla basin watershed coordination
S 114 Identify and select projects for Walla Walla Basin