Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 83815: 1992-061-03 EXP IDFG ADMIN ALBENI FALLS
Project Number:
Title:
Albeni Falls Wildlife Mitigation-Idaho Department of Fish and Game (IDFG)
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Pend Oreille 100.00%
Contract Number:
83815
Contract Title:
1992-061-03 EXP IDFG ADMIN ALBENI FALLS
Contract Continuation:
Previous: Next:
80586: 1992-061-03 EXP IDFG ALBENI FALLS WILDLIFE ADMIN
  • 86316: 1992-061-03 EXP ALBENI FALLS WILDLIFE MITIGATION - IDFG
Contract Status:
Closed
Contract Description:
Implementation of the Northern Idaho Memorandum of Agreement between The State of Idaho and Bonneville Power Administration for Wildlife Habitat Stewardship and Restoration, signed August 30, 2018.  
Account Type(s):
Expense
Contract Start Date:
10/01/2019
Contract End Date:
09/30/2020
Current Contract Value:
$4,285,637
Expenditures:
$4,285,637

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Evan DeHamer Idaho Department of Fish and Game (IDFG) Yes Contract Manager evan.dehamer@idfg.idaho.gov (208) 407-9434
Lisa Dexter Bonneville Power Administration Yes Contracting Officer lldexter@bpa.gov (503) 230-3893
Minda Donnelly Department of Energy - IGE No Interested Party minda.donnelly@doe.gov (702) 295-0874
David Kaplowe Bonneville Power Administration Yes F&W Approver djkaplowe@bpa.gov (503) 230-5365
Claire McClory Bonneville Power Administration No Env. Compliance Lead cdmcclory@bpa.gov (503) 230-5922
Norm Merz Idaho Department of Fish and Game (IDFG) Yes Contract Manager norm.merz@idfg.idaho.gov (208) 691-7176
Crystal Miller Department of Energy - IGE No Interested Party crystal.miller@doe.gov (702) 295-0779
Virgil Watts III Bonneville Power Administration Yes COR vlwatts@bpa.gov (503) 230-4625
Emily Wiegert Department of Energy - IGE No Interested Party emily.wiegert@doe.gov (123) 456-7890
Jae Woo Department of Energy - IGE No Interested Party jae.woo@doe.gov (702) 295-0874


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Completed Documentation Pertaining to Environmental Compliance A: 165. Environmental Compliance 09/30/2020 09/30/2020
Albeni Falls Lands Project Management and WMA Equipment Purchase B: 119. Develop/Maintain IDFG Budgets, Manage/Maintain Contracts & Inventory Records & IDFG Spending 09/30/2020 09/30/2020
Completed Post Pole Storage Barn C: 201. Pole Barn Construction in Cooperation with ACOE at Clark Fork Drift Yard 09/30/2020 09/30/2020
Transfer of IDFG Albeni Falls LMP's to BPA Template with Updates as Needed D: 193. Review & Update Existing Land Management Plans Covering Albeni Falls Wildlife Mitigation Properties 09/30/2020 09/30/2020
Regional Wildlife Meeting Attendance E: 189. If and When Needed Coordinate/Develop Albeni Falls Wildlife Mitigation Presentations to the Wildlife Caucus 09/30/2020 09/30/2020
Inform and Recruit Interested Entities in the Mitigation Efforts F: 189. Build relationships with entities interested in wildlife mitigation 09/30/2020 09/30/2020
Education and Outreach for Community affected by the Albeni Falls Hydroelectric facility. G: 99. Coordinate/Implement Info Education Program for Albeni Falls Wildlife Mitigation Project 09/30/2020 09/30/2020
90% Engineered Design completed for Phase I, Areas 7 and 11 H: 175. Prepare designs and plans to protect and restore delta and shorelines in Phase I, Areas 7 and 11 affected by the operations of the Albeni Falls Dam 09/30/2020 09/30/2020
Vegetation Management Plan and Comprehensive Monitoring Plan I: 174. Develop Site-specific management actions for restored areas of the Clark Fork River Delta 09/30/2020 09/30/2020
Complete the construction and vegetation work for the Clark Fork River Delta Restoration Project J: 181. Complete Restoration Objectives on the Clark Fork River Delta 09/30/2020 09/29/2020
Completion of Touch up Restoration Activities at Area 3 Peninsula. K: 181. Staging and implementation of touch up of Phase 1, Area 3 09/30/2020 09/29/2020
Annual Summary Report of Monitoring Information L: 157. Coordinate and Conduct Wildlife and Vegetation Monitoring Surveys for the Clark Fork Delta 09/30/2020 09/30/2020
Monitoring for Aquatic Invertebrate diversity M: 157. Coordinate, collect and generate field data on Aquatic micro- and macro-invertebrates in the Clark Fork River delta 09/30/2020 09/30/2020
Completed Annual N. Idaho Wildlife Mitigation Report O: 132. Submit Progress Report for the period (October 1 2019) to (September 30, 2020) 09/30/2020 09/30/2020

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Wildlife
  • 1 instance of WE 193 Produce Land Management Plan
  • 2 instances of WE 181 Create, Restore, and/or Enhance Wetland
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 175 Produce Design
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance
B 119 Develop/Maintain IDFG Budgets, Manage/Maintain Contracts & Inventory Records & IDFG Spending
C 201 Pole Barn Construction in Cooperation with ACOE at Clark Fork Drift Yard 07/02/2020
D 193 Review & Update Existing Land Management Plans Covering Albeni Falls Wildlife Mitigation Properties
E 189 If and When Needed Coordinate/Develop Albeni Falls Wildlife Mitigation Presentations to the Wildlife Caucus
F 189 Build relationships with entities interested in wildlife mitigation
G 99 Coordinate/Implement Info Education Program for Albeni Falls Wildlife Mitigation Project
H 175 Prepare designs and plans to protect and restore delta and shorelines in Phase I, Areas 7 and 11 affected by the operations of the Albeni Falls Dam
I 174 Develop Site-specific management actions for restored areas of the Clark Fork River Delta 07/02/2020
J 181 Complete Restoration Objectives on the Clark Fork River Delta 12/09/2019
K 181 Staging and implementation of touch up of Phase 1, Area 3 07/02/2020
L 157 Coordinate and Conduct Wildlife and Vegetation Monitoring Surveys for the Clark Fork Delta 07/02/2020
M 157 Coordinate, collect and generate field data on Aquatic micro- and macro-invertebrates in the Clark Fork River delta 07/02/2020
N 185 Periodic Status Reports for BPA
O 132 Submit Progress Report for the period (October 1 2019) to (September 30, 2020)