Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 84063 REL 10: 2010-072-00 EXP UPPER SALMON BASIN HABITAT RESTORATION
Project Number:
Title:
Upper Salmon Basin Habitat Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
84063 REL 10
Contract Title:
2010-072-00 EXP UPPER SALMON BASIN HABITAT RESTORATION
Contract Continuation:
Previous: Next:
84063 REL 3: 2010-072-00 EXP UPPER SALMON BASIN RESTORATION
  • CR-373772: 2010-072-00 EXP UPPER SALMON BASIN HABITAT RESTORATION
Contract Status:
Issued
Contract Description:
This contract covers 2024-2025 actions by Idaho Department of Fish and Game (IDFG), Lemhi Soil and Water Conservation District (Lemhi SWCD), and Trout Unlimited (TU).

IDFG:
Lower Lemhi Eagle Valley Ranch Subreach 1 (phases 2, 3 & 4)
Lower Lemhi Eagle Valley Ranch Subreach 4
Middle Lemhi Henry Reach Phase 2 project
Middle Lemhi River - Hayden Reach Phase 2
Bohannon #3 Diversion Rehabilitation and Rebuild
Wells on McNeal Property
Beyeler Ranch Irrigation System
University of Idaho Student Internship
Upper Patterson Big Springs Riparian Planting Habitat Improvement
Last Chance Upper Pahsimeroi Phase 2
North Fork Salmon River Ty Cole Property
Page BDA and IDL Project Adaptive Management
Hanging T Pahsimeroi Project
Pahsimeroi Projects Revegetation
Sq. Creek Culvert to Bridge Project
Tower Creek East Fork Road Culvert Removal Design
Kinnikinic Creek Culvert to Bridge Design
Poison Creek Culvert to Bridge Design

Lemhi SWCD:  
Lemhi River and Kenney Creek Design
Lemhi River L-45 Restoration and Diversion Design
Ball Springs Habitat Improvement Project
Bar 20 to BLM Hayden Creek Design

TU:
Beyeler Adaptive Management
Deep Creek Hilwig Flood Plain Restoration
Bar G Muddy Springs Habitat Phase 1
Account Type(s):
Expense
Contract Start Date:
02/01/2024
Contract End Date:
01/31/2025
Current Contract Value:
$5,016,254
Expenditures:
$2,252,251

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Daniel Affonso Bonneville Power Administration Yes Contracting Officer dxaffonso@bpa.gov (503) 230-5918
Gavin Aguilar Idaho Governor's Office of Species Conservation Yes Technical Contact gavin.aguilar@osc.idaho.gov (612) 719-0383
Matt Belnap Idaho Department of Fish and Game (IDFG) Yes Technical Contact matt.belnap@idfg.idaho.gov (208) 569-1283
Daniel Bertram Idaho Governor's Office of Species Conservation Yes Contract Manager daniel.bertram@osc.idaho.gov (208) 756-6322
Karma Bragg Custer Soil and Water Conservation District (SWCD) Yes Technical Contact cswcd@custertel.net (208) 879-4428
Jessica Buelow Idaho Department of Fish and Game (IDFG) Yes Technical Contact jessica.buelow@idfg.idaho.gov (208) 756-2271
Sharon Clark Idaho Department of Fish and Game (IDFG) Yes Interested Party sharon.clark@idfg.idaho.gov (208) 287-2784
Becky Coffey Lemhi Soil and Water Conservation District (SWCD) Yes Administrative Contact lswcd@hotmail.com (208) 756-3211x101
Dominique Cota Idaho Governor's Office of Species Conservation Yes Administrative Contact dominique.cota@osc.idaho.gov (208) 332-1550
Hunter Distad Idaho Governor's Office of Species Conservation Yes Technical Contact hunter.distad@osc.idaho.gov (208) 993-0497
Mike Edmondson Idaho Governor's Office of Species Conservation No Supervisor mike.edmondson@osc.idaho.gov (208) 334-2189
Steve Fisher Lemhi Soil and Water Conservation District (SWCD) Yes Technical Contact lemhi.swcd.pm@gmail.com (208) 833-7274
Graham Freeman Idaho Governor's Office of Species Conservation Yes Supervisor graham.freeman@osc.idaho.gov (208) 332-1555
Abbie Gongloff Idaho Governor's Office of Species Conservation Yes Interested Party abbie.gongloff@osc.idaho.gov (208) 756-6322
Andy Gregory Trout Unlimited (TU) Yes Technical Contact andy.gregory@tu.org (208) 360-8629
Megan Heller Idaho Department of Fish and Game (IDFG) Yes Technical Contact megan.heller@idfg.idaho.gov (208) 867-1069
Amy Hines Idaho Governor's Office of Species Conservation Yes Contract Manager amy.hines@osc.idaho.gov (208) 332-1557
David Kaplowe Bonneville Power Administration Yes F&W Approver djkaplowe@bpa.gov (503) 230-5365
Eric Leitzinger Bonneville Power Administration Yes COR ejleitzinger@bpa.gov (503) 230-3534
Bob Minton Lemhi Soil and Water Conservation District (SWCD) Yes Technical Contact bobminton@hotmail.com (208) 756-4262
Jessica Power Bonneville Power Administration No CO Assistant jdpower@bpa.gov (503) 230-4023
Justin Saydell Idaho Governor's Office of Species Conservation Yes Technical Contact justin.saydell@osc.idaho.gov (208) 756-6322
Robert Shull Bonneville Power Administration Yes Env. Compliance Lead rwshull@bpa.gov (503) 230-3962
Joe Stewart Trout Unlimited (TU) Yes Technical Contact joseph.stewart@tu.org (206) 909-3188
Caselle Wood Trout Unlimited (TU) Yes Technical Contact caselle.wood@tu.org (208) 390-2028


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Effective implementation management and timely contract administration A: 119. OSC: Routine/daily administration of work elements 01/31/2025
Complete all required EC and obtain permits prior to implementation of project work B: 165. Produce Environmental Compliance Documentation 01/31/2025
Completed Annual Report D: 132. Submit 84063 Rel 3 Progress Report for the period February 2023 to January 2024 11/29/2024
Effective implementation management and timely contract administration E: 119. IDFG: Upper Salmon Basin Manage and Administer Project 01/31/2025
Develop or update (out-year) prioritized Habitat Project list: Upload to CBFish F: 114. IDFG: Upper Salmon Basin Project Development 01/31/2025
Imagery Stored and Shared G: 161. IDFG: Maintain cloud-based repository for habitat project imagery and geo referenced maps for project planning and cooperator use. 01/31/2025
Construction Management Complete H: 100. IDFG-Lemhi-Construction Oversight and Management 01/31/2025
Adaptive management phase complete. I: 29. IDFG-Lemhi: Lower Lemhi Eagle Valley Ranch Subreach 1 Adaptive Management Phase 1. 01/31/2025
Complete Lower Lemhi River Subreach 1 Phase 2 Restoration J: 29. IDFG-Lemhi: Lower Lemhi Eagle Valley Ranch Subreach 1 Phase 2 Implementation 09/30/2024 03/15/2024
Project reseeded and plants potted. K: 47. IDFG-Lemhi- Revegetation of Eagle Valley Ranch sub reach 1 phase 2. 01/31/2025
Complete construction of Lower Lemhi Rehabilitation Subreach 1 Phase 3. L: 29. IDFG-Lemhi: Lower Lemhi Eagle Valley Ranch Subreach 1 Phase 3 Implementation 01/31/2025
Revegetate Lower Lemhi River Rehabilitation Subreach 1 Phase 3 project. M: 47. IDFG-Lemhi- Revegetation of Eagle Valley Ranch sub reach 1 phase 3. 12/31/2024
Fence constructed. N: 40. IDFG-Lemhi- Eagle Valley Subreach 1 Phases 3 fencing 11/30/2024
Pivot installed. O: 208. IDFG-Lemhi-Pivot for EVR subreach 1 phase 3. 01/31/2025 08/01/2024
Implement subreach 1 phase 4 construction. P: 29. IDFG-Lemhi: Lower Lemhi Eagle Valley Ranch Subreach 1 Phase 4 Implementation 01/31/2025
Revegetate Lower Lemhi Rehabilitation Subreach 1 Phase 4 project. Q: 47. IDFG-Lemhi- Revegetation of Eagle Valley Ranch sub reach 1 phase 4. 01/31/2025
Complete subreach 4 completion phase. R: 29. IDFG-Lemhi: Lower Lemhi Eagle Valley Ranch Subreach 4 01/31/2025
Subreach 1 vegetation maintained across all phases. S: 198. IDFG-Lemhi-Maintain Vegetation EVR Subreach 1 Phases 1, 2, 3, and 4. 01/31/2025 09/30/2024
Final Design for Henry Phase 2 T: 175. IDFG-Lemhi- Middle Lemhi Henry Reach Phase 2 Design 07/31/2024 07/15/2024
Henry property, phase 2, restoration project completed. U: 29. IDFG-Lemhi- Middle Lemhi Henry Reach Phase 2. 01/31/2025
Fence constructed. V: 40. IDFG-Lemhi- Middle Lemhi Henry Reach Phase 2 Fencing 12/31/2024
Henry Reach Phase 2 revegetation complete. W: 47. IDFG-Lemhi- Middle Lemhi Henry Reach Phase 2 Revegetation 11/30/2024
Final design for Hayden Phase 2 X: 175. IDFG-Lemhi- Middle Lemhi River-Hayden Reach Phase 2 Design 01/31/2025
New Configuration for Bohannon 3 efficiency project complete. Y: 208. IDFG-Lemhi- Reconstruct the Bohannon Creek Diversion #3 10/31/2024 09/30/2024
Wells drilled and installed. Z: 208. IDFG- Lemhi- McNeal Wells 07/31/2024
Design complete for Beyeler Irrigation. AA: 175. IDFG - Lemhi: Beyeler Ranch Irrigation System Design 01/31/2025
Irrigation pipeline complete. AB: 208. IDFG - Lemhi: Beyeler Ranch Irrigation System Purchase of Pipeline 01/31/2025
Outreach materials for Lemhi River Projects developed and distributed to public. AC: 99. IDFG-Lemhi-Outreach and Education 01/31/2025
Habitat projects maintained. AD: 186. IDFG: Perform Unscheduled Maintenance of Habitat Project Sites in the Upper Salmon Basin 01/31/2025
Effective implementation management and timely contract administration AE: 119. Lemhi SWCD: Project Implementation: Manage and Administer 01/31/2025
Construction Management Complete AF: 100. Lemhi SWCD Project Implementation: Provide Project Implementation Support & Construction Oversight 01/31/2025
Develop or update (out-year) prioritized Habitat Project list: Upload to CBFish AG: 114. Lemhi SWCD Project Implementation: Identify and Select Projects 01/31/2025
Treat noxious weeds at identified project locations and submit completed HUFs to BPA AH: 199. Lemhi SWCD: Lemhi Vegetation: Initial treatment 01/31/2025
Treat noxious species in the Pahsimeroi and submit completed HUFs to BPA. AI: 199. Lemhi SWCD: Pahsimeroi Vegetation: Initial treatment 01/31/2025
Treat noxious weed species and submit completed HUFs for on-going treatments. AJ: 198. Lemhi SWCD: Lemhi Vegetation: Ongoing treatment 01/31/2025
Treat noxious weeds and submit completed HUFs to BPA. AK: 198. Lemhi SWCD: Pahsimeroi Vegetation: Ongoing treatment 01/31/2025
Complete seeding and planting on projects in the Lemhi subbasin. AL: 47. Lemhi SWCD: Lemhi Vegetation Management: Rehabilitate Project Sites, Initial Treatment 01/31/2025
Complete seeding and planting in the Pahsimeroi subbasin. AM: 47. Lemhi SWCD: Pahsimeroi Vegetation Management: Rehabilitate Project Sites, Initial Treatment. 01/31/2025
Final Design AN: 175. Lemhi SWCD: Lemhi River and Kenney Creek Jackson Project Design 01/31/2025
Final Design Planset and BDR AO: 175. Lemhi SWCD: L-45 Diversion and Restoration Design 01/31/2025
Final Design Planset, cost estimate, and bid documents ready for implementation contractor bid AS: 175. Lemhi SWCD: Bar 20 to BLM 01/31/2025
Project Repair/Maintenance Complete AT: 186. TU: Beyeler Upper Mainstem/Springs Adaptive Management 01/31/2025
30% Design Complete AU: 175. TU: Deep Creek Hilwig Flood Plain Restoration Design 01/31/2025
Construction Management Complete AV: 100. IDFG-Pahsimeroi-Construction Oversight and Management 01/31/2025
Big Springs project revegetated AW: 47. IDFG- Pahsimeroi-Revegetation of Big Springs 11/30/2024 08/31/2024
Fence constructed. AX: 40. IDFG- Pahsimeroi-Big Springs Fencing 11/30/2024
Last Chance Ranch phase 2 constructed. AY: 29. IDFG-Pahsimeroi-Last Chance Ranch Upper Pahsimeroi Phase 2 01/31/2025
Complete revegetation of restoration project. AZ: 47. IDFG-Pahsimeroi-Last Chance Ranch-Upper Pahsimeroi Phase 2 Revegetation 01/30/2025
Riparian fencing completed. BA: 40. IDFG-Pahsimeroi-Last Chance Ranch-Upper Pahsimeroi Phase 2 Fencing 12/31/2024
Restoration project completed. BB: 29. IDFG-North Fork Salmon River-Ty Cole Property 01/31/2025 08/15/2024
Restoration project revegetated. BC: 47. IDFG-North Fork Salmon River-Ty Cole Property Revegetation 01/31/2025
Ty Cole Design Complete BD: 175. IDFG-North Fork-Produce Ty Cole Property Design 07/01/2024 06/30/2024
IDL and Page property adaptive BDA/ PAL complete. BE: 29. IDFG-Pahsimeroi-Page BDA and IDL BDA Project Adaptive Management 01/31/2025
Hanging T Ranch design complete. BF: 175. IDFG-Pahsimeroi-Hanging T Ranch Ranch Plan Design 01/31/2025
Revegetate Pahsimeroi restoration contracts. BG: 47. IDFG-Pahsimeroi- Pahsimeroi Implementation Project Revegetation 12/31/2024
Fence constructed. BH: 40. IDFG-Pahsimeroi- Pahsimeroi Implementation Project Fencing 12/31/2024
Double culvert to bridge replacement complete. BI: 184. IDFG-Upper Salmon-Bia Po’i Naokwaide (SQ) Creek double culvert to bridge project 12/31/2024
Design for SQ Creek complete. BJ: 175. IDFG-Upper Salmon-Bia Po’i Naokwaide (SQ) Creek culvert to bridge design 08/30/2024
Design for East Tower Road culvert complete. BK: 175. IDFG-Tower Creek- East Fork Tower Creek Road-Culvert Removal Design 01/31/2025
Kinnikinic Bridge designed. BL: 175. IDFG-Upper Salmon-Kinnikinic Creek Culvert to Bridge Design 01/31/2025
Poison Creek Bridge Designed. BM: 175. IDFG-Upper Salmon-Poison Creek Culvert to Bridge Design 01/31/2025
Final Design Completed for Bar-G Muddy Springs Habitat Phase 2 BN: 175. TU: Bar G Muddy Springs Design 2024 01/31/2025
Water Delivery and Fencing Completed to protect water and habitat BO: 208. TU: Bar-G Muddy Spring Habitat Phase 1 - Irrigation infrastructure construction 01/31/2025
Bridge Purchase BP: 184. Custer SWCD: Purchase Bridge for Road Creek 10/31/2024
Completed construction of the project BQ: 29. IDFG-Lemhi: Lower Lemhi Eagle Valley Ranch Subreach 1 Adaptive Management Phase 2 01/31/2025
Completed project construction BR: 29. IDFG-Lemhi- Middle Lemhi River-Hayden Reach Phase 2 Implementation 01/31/2025
Completed construction BS: 29. IDFG-Pahsimeroi-Last Chance Ranch Upper Pahsimeroi Phase 1 Modification 01/31/2025
Conceptual 15% design complete. BT: 175. IDFG-Pahsimeroi-River Valley Ranch Design and Spring Connection 11/30/2024
TNC ranch management and restoration plan uploaded to CBfish BU: 174. TNC-Lemhi River Ranch Management and Restoration Plan 01/31/2025
Jack Fence Constructed BV: 186. TU: Bar-G Muddy Springs Culvert Replacement - fence construction 01/31/2025
Construction bridge acquired. BW: 184. IDFG: River Valley Ranch Construction Bridge 01/31/2025

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 3 instances of WE 198 Maintain Vegetation
  • 2 instances of WE 199 Remove Vegetation
  • 3 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 13 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 34 Develop Alternative Water Source
  • 6 instances of WE 40 Install Fence
  • 10 instances of WE 47 Plant Vegetation
  • 2 instances of WE 184 Install Fish Passage Structure
  • 2 instances of WE 114 Identify and Select Projects
  • 1 instance of WE 174 Produce Plan
  • 15 instances of WE 175 Produce Design
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results
  • 3 instances of WE 100 Construction Management
  • 5 instances of WE 208 Irrigation Infrastructure Construction or Replacement
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 1 instance of WE 184 Install Fish Passage Structure
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 3 instances of WE 198 Maintain Vegetation
  • 2 instances of WE 199 Remove Vegetation
  • 3 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 13 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 34 Develop Alternative Water Source
  • 6 instances of WE 40 Install Fence
  • 10 instances of WE 47 Plant Vegetation
  • 3 instances of WE 184 Install Fish Passage Structure
  • 2 instances of WE 114 Identify and Select Projects
  • 1 instance of WE 174 Produce Plan
  • 15 instances of WE 175 Produce Design
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results
  • 3 instances of WE 100 Construction Management
  • 4 instances of WE 208 Irrigation Infrastructure Construction or Replacement
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 OSC: Routine/daily administration of work elements
B 165 Produce Environmental Compliance Documentation
C 185 Periodic Status Reports for BPA
D 132 Submit 84063 Rel 3 Progress Report for the period February 2023 to January 2024
E 119 IDFG: Upper Salmon Basin Manage and Administer Project
F 114 IDFG: Upper Salmon Basin Project Development
G 161 IDFG: Maintain cloud-based repository for habitat project imagery and geo referenced maps for project planning and cooperator use.
H 100 IDFG-Lemhi-Construction Oversight and Management
I 29 IDFG-Lemhi: Lower Lemhi Eagle Valley Ranch Subreach 1 Adaptive Management Phase 1. 12/29/2023
J 29 IDFG-Lemhi: Lower Lemhi Eagle Valley Ranch Subreach 1 Phase 2 Implementation 12/29/2023
K 47 IDFG-Lemhi- Revegetation of Eagle Valley Ranch sub reach 1 phase 2. 12/29/2023
L 29 IDFG-Lemhi: Lower Lemhi Eagle Valley Ranch Subreach 1 Phase 3 Implementation 12/29/2023
M 47 IDFG-Lemhi- Revegetation of Eagle Valley Ranch sub reach 1 phase 3. 12/29/2023
N 40 IDFG-Lemhi- Eagle Valley Subreach 1 Phases 3 fencing 12/29/2023
O 208 IDFG-Lemhi-Pivot for EVR subreach 1 phase 3. 12/29/2023
P 29 IDFG-Lemhi: Lower Lemhi Eagle Valley Ranch Subreach 1 Phase 4 Implementation 12/29/2023
Q 47 IDFG-Lemhi- Revegetation of Eagle Valley Ranch sub reach 1 phase 4. 12/29/2023
R 29 IDFG-Lemhi: Lower Lemhi Eagle Valley Ranch Subreach 4 12/29/2023
S 198 IDFG-Lemhi-Maintain Vegetation EVR Subreach 1 Phases 1, 2, 3, and 4. 12/29/2023
T 175 IDFG-Lemhi- Middle Lemhi Henry Reach Phase 2 Design 12/29/2023
U 29 IDFG-Lemhi- Middle Lemhi Henry Reach Phase 2. 08/13/2024
V 40 IDFG-Lemhi- Middle Lemhi Henry Reach Phase 2 Fencing 08/13/2024
W 47 IDFG-Lemhi- Middle Lemhi Henry Reach Phase 2 Revegetation 08/13/2024
X 175 IDFG-Lemhi- Middle Lemhi River-Hayden Reach Phase 2 Design 12/29/2023
Y 208 IDFG-Lemhi- Reconstruct the Bohannon Creek Diversion #3 12/29/2023
Z 208 IDFG- Lemhi- McNeal Wells
AA 175 IDFG - Lemhi: Beyeler Ranch Irrigation System Design 12/29/2023
AB 208 IDFG - Lemhi: Beyeler Ranch Irrigation System Purchase of Pipeline 12/29/2023
AC 99 IDFG-Lemhi-Outreach and Education
AD 186 IDFG: Perform Unscheduled Maintenance of Habitat Project Sites in the Upper Salmon Basin 12/29/2023
AE 119 Lemhi SWCD: Project Implementation: Manage and Administer
AF 100 Lemhi SWCD Project Implementation: Provide Project Implementation Support & Construction Oversight
AG 114 Lemhi SWCD Project Implementation: Identify and Select Projects
AH 199 Lemhi SWCD: Lemhi Vegetation: Initial treatment 05/21/2024
AI 199 Lemhi SWCD: Pahsimeroi Vegetation: Initial treatment 05/21/2024
AJ 198 Lemhi SWCD: Lemhi Vegetation: Ongoing treatment 05/21/2024
AK 198 Lemhi SWCD: Pahsimeroi Vegetation: Ongoing treatment 05/21/2024
AL 47 Lemhi SWCD: Lemhi Vegetation Management: Rehabilitate Project Sites, Initial Treatment 05/21/2024
AM 47 Lemhi SWCD: Pahsimeroi Vegetation Management: Rehabilitate Project Sites, Initial Treatment. 05/21/2024
AN 175 Lemhi SWCD: Lemhi River and Kenney Creek Jackson Project Design 12/29/2023
AO 175 Lemhi SWCD: L-45 Diversion and Restoration Design 12/29/2023
AP 29 Lemhi SWCD: Ball Springs Implementation
AQ 40 Lemhi SWCD: Ball Springs Implementation - fence construction
AR 34 Lemhi SWCD: Ball Springs Implementation - stockwater development
AS 175 Lemhi SWCD: Bar 20 to BLM 12/29/2023
AT 186 TU: Beyeler Upper Mainstem/Springs Adaptive Management 12/29/2023
AU 175 TU: Deep Creek Hilwig Flood Plain Restoration Design 12/29/2023
AV 100 IDFG-Pahsimeroi-Construction Oversight and Management
AW 47 IDFG- Pahsimeroi-Revegetation of Big Springs 12/29/2023
AX 40 IDFG- Pahsimeroi-Big Springs Fencing 12/29/2023
AY 29 IDFG-Pahsimeroi-Last Chance Ranch Upper Pahsimeroi Phase 2
AZ 47 IDFG-Pahsimeroi-Last Chance Ranch-Upper Pahsimeroi Phase 2 Revegetation
BA 40 IDFG-Pahsimeroi-Last Chance Ranch-Upper Pahsimeroi Phase 2 Fencing
BB 29 IDFG-North Fork Salmon River-Ty Cole Property 07/01/2024
BC 47 IDFG-North Fork Salmon River-Ty Cole Property Revegetation 07/01/2024
BD 175 IDFG-North Fork-Produce Ty Cole Property Design 12/29/2023
BE 29 IDFG-Pahsimeroi-Page BDA and IDL BDA Project Adaptive Management 06/19/2024
BF 175 IDFG-Pahsimeroi-Hanging T Ranch Ranch Plan Design 12/29/2023
BG 47 IDFG-Pahsimeroi- Pahsimeroi Implementation Project Revegetation 12/29/2023
BH 40 IDFG-Pahsimeroi- Pahsimeroi Implementation Project Fencing 12/29/2023
BI 184 IDFG-Upper Salmon-Bia Po’i Naokwaide (SQ) Creek double culvert to bridge project
BJ 175 IDFG-Upper Salmon-Bia Po’i Naokwaide (SQ) Creek culvert to bridge design 12/29/2023
BK 175 IDFG-Tower Creek- East Fork Tower Creek Road-Culvert Removal Design 12/29/2023
BL 175 IDFG-Upper Salmon-Kinnikinic Creek Culvert to Bridge Design 12/29/2023
BM 175 IDFG-Upper Salmon-Poison Creek Culvert to Bridge Design 12/29/2023
BN 175 TU: Bar G Muddy Springs Design 2024 12/29/2023
BO 208 TU: Bar-G Muddy Spring Habitat Phase 1 - Irrigation infrastructure construction
BP 184 Custer SWCD: Purchase Bridge for Road Creek 06/18/2024
BQ 29 IDFG-Lemhi: Lower Lemhi Eagle Valley Ranch Subreach 1 Adaptive Management Phase 2 12/29/2023
BR 29 IDFG-Lemhi- Middle Lemhi River-Hayden Reach Phase 2 Implementation
BS 29 IDFG-Pahsimeroi-Last Chance Ranch Upper Pahsimeroi Phase 1 Modification 05/15/2024
BT 175 IDFG-Pahsimeroi-River Valley Ranch Design and Spring Connection 06/18/2024
BU 174 TNC-Lemhi River Ranch Management and Restoration Plan 06/18/2024
BV 186 TU: Bar-G Muddy Springs Culvert Replacement - fence construction 09/17/2024
BW 184 IDFG: River Valley Ranch Construction Bridge 06/25/2024