Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 84370: 1996-077-02 EXP LOLO CREEK WATERSHED RESTORATION
Project Number:
Title:
Lolo/Selway River Watershed Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
84370
Contract Title:
1996-077-02 EXP LOLO CREEK WATERSHED RESTORATION
Contract Continuation:
Previous: Next:
74017 REL 41: 1996-077-02 EXP LOLO CREEK WATERSHED RESTORATION
  • 87084: 1996-077-02 EXP LOLO CREEK WATERSHED RESTORATION
Contract Status:
Closed
Contract Description:
The Lolo Creek Watershed Restoration project (1996-077-02) has been an on-going project of the Nez Perce Tribe Fisheries Watershed Program and BPA since 1996. This unique and successful restoration partnership is implemented through agreements between the Nez Perce - Clearwater National Forests (NPCNFs), Nez Perce Tribe (NPT), and Bonneville Power Administration (BPA). The ultimate goal of the project is to restore the physical and biological characteristics of the watershed to provide quality habitat for anadromous and resident fish species that support the historical, cultural, and economic practices of the Nez Perce Tribe. In 2016, the Lolo Creek project was combined with the Selway River project, a newly funded BiOp effort initiated in 2011 to perform high priority watershed restoration actions in the Selway River watershed.

The Lolo Creek watershed contains proposed critical habitat for listed steelhead trout, potential critical habitat for bull trout, and has moderate habitat potential for Spring Chinook salmon. Restoration in this watershed focuses on restoring riparian processes by addressing increased water temperatures, increased sedimentation, cattle grazing effects, fish passage barriers, and noxious weed infestations. Fish passage and habitat connectivity actions are prioritized primarily at road/stream crossings on both private and federal land, and native riparian revegetation and continuous riparian protection are also high priority actions.

The Selway River Watershed contains critical habitat for listed steelhead trout, potential critical habitat for bull trout, and has moderate habitat potential for Spring Chinook salmon. Restoration follows a ridge top to ridge top approach with implementation focused on restoring riparian processes by addressing increased water temperatures, increased sedimentation, cattle grazing effects, aquatic habitat connectivity, and exotic, invasive plant encroachment. The cost share for this project has been contributed by the Nez Perce - Clearwater National Forests who provides approximately 20% match including cash and in-kind contributions. Project planning and implementation responsibilities are also shared with the Nez Perce - Clearwater National Forests.

Completed contract work in the Lolo Watershed includes culvert prioritization and assessment, installation of an off-site water source, 29 culvert replacements, 11 culvert removals, 2600 ft. of stream bank stabilization, 14 large wood structures, 108.5 miles of road decommissioning, 23 miles of fence installation and maintenance, and over 24,000 native riparian trees and shrubs planted.

Completed contract work in the Selway Watershed includes culvert prioritization and assessment, installation of 10 culvert replacements, and 41 miles road decommissioning surveys.  

The following agencies and entities will collaborate with local partners to identify the highest priority locations and a corresponding suite of restorations actions to address critical limiting factors in the Lolo Creek Watershed: BPA, NPT, Nez Perce-Clearwater National Forests, IDFG, IDL, Potlatch Corp., BLM, NRCS, and the county SWCD. This collaborative, inclusive, evidence-based, and strategic process has
been ongoing for several years, leading to the development of an Atlas prioritization framework in 2019. The Lolo Atlas framework contains a prioritized list of areas and specific restoration actions to be implemented over the next 10 years or more. The Atlas framework is a living document and is managed adaptively and modified as projects are implemented and as new data and research evidence becomes available to inform restoration.

Projects that have been considered and prioritized through the Atlas process, and that are planned for implementation this contract period, include: addressing fish passage barriers in Nevada, White, and Mike White creeks; removing an irrigation diversion and improving wetland habitat at Musselshell Meadows; increasing habitat complexity at Musselshell Creek and lower Lolo Creek; design work at the Selway irrigation diversion; and fencing, riparian planting, and invasive plants treatment.
Account Type(s):
Expense
Contract Start Date:
02/01/2020
Contract End Date:
01/31/2021
Current Contract Value:
$623,217
Expenditures:
$623,217

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Marcie Carter Nez Perce Tribe Yes Supervisor marciec@nezperce.org (208) 621-3534
Elizabeth Eastman Nez Perce Tribe No Technical Contact elizabethe@nezperce.org (208) 621-3558
Desmond Gelman Bonneville Power Administration No CO Assistant dxgelman@bpa.gov (503) 230-4960
Arleen Henry Nez Perce Tribe No Administrative Contact arleenh@nezperce.org (208) 621-3833
David Kaplowe Bonneville Power Administration Yes F&W Approver djkaplowe@bpa.gov (503) 230-5365
Jennifer Lord Bonneville Power Administration Yes COR jklord@bpa.gov (503) 230-5192
Ed Main Nez Perce Tribe No Technical Contact edwardm@nezperce.org (208) 621-3539
Justin Peterson Nez Perce Tribe Yes Contract Manager justinp@nezperce.org (208) 621-3545
Robert Shull Bonneville Power Administration Yes Env. Compliance Lead rwshull@bpa.gov (503) 230-3962
Emmit Taylor, Jr. Nez Perce Tribe No Supervisor emmitt@nezperce.org (208) 621-3544
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental Compliance Documentation Submitted to BPA A: 165. Environmental Compliance for Projects on Forest Service Lands 01/31/2021 12/31/2020
Develop or update (out-year) prioritized Habitat Project list: upload to Pisces B: 114. Use ATLAS Matrix to Prioritize and Select Projects 01/31/2021 12/31/2020
Finalize project completion C: 85. Nevada Creek Barrier Replacement 11/30/2020 10/15/2020
Finalize project completion D: 85. White Creek Barrier Replacement 11/30/2020 10/15/2020
Finalize installation of beaver dam analogs and monitor their effectiveness H: 29. Construct Beaver Dam Analogs on Musselshell Creek 11/30/2020 08/13/2020
Finalize Designs for irrigation improvements at up to 2 diversion structures J: 175. Selway Irrigation Diversion Design 01/31/2021 12/31/2020
Fence Maintained K: 186. Maintain Fence 01/31/2021 07/01/2020
Riparian Planting on previous project sites in the Lolo Creek watershed L: 47. Riparian Planting 12/31/2020 10/22/2020
Treat Exotic Invasive Species M: 199. Treat Exotic Invasive Species on USFS and Private Lands 01/31/2021 11/30/2020
Complete surveys/Complete UAV monitoring flights and submit flight logs N: 115. Collect stream, meadow, road data/Project monitoring and inventory via UAV (i.e., drone) to develop and prioritize future projects 12/31/2020 12/31/2020
Review of Partner Projects O: 122. Review and Technical Assistance for Proposed Partner Actions 01/31/2021 12/31/2020
Watershed Coordination P: 191. Coordinate with Regional Partners 01/31/2021 12/31/2020
Manage Projects and Administrative duties Q: 119. Manage Projects and Administrative duties 01/31/2021 12/31/2020
Attach 2019 Annual Report S: 132. Annual Report February 2020 - January 2021 01/31/2021 12/31/2020
Completed Annual Report T: 132. Submit Progress Report for the period February 2019 - January 2020 01/31/2021 12/31/2020

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 199 Remove Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 181 Create, Restore, and/or Enhance Wetland
  • 1 instance of WE 84 Remove/Install Diversion
  • 3 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 175 Produce Design
Lamprey, Pacific (Entosphenus tridentata)
  • 2 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 181 Create, Restore, and/or Enhance Wetland
  • 1 instance of WE 84 Remove/Install Diversion
  • 3 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 175 Produce Design
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance for Projects on Forest Service Lands
B 114 Use ATLAS Matrix to Prioritize and Select Projects
C 85 Nevada Creek Barrier Replacement 04/22/2020
D 85 White Creek Barrier Replacement 04/22/2020
E 85 Mike White Creek Barrier Replacement 04/22/2020
F 84 Musselshell Meadow Irrigation Diversion Removal
G 181 Musselshell Meadow Wetland Improvements
H 29 Construct Beaver Dam Analogs on Musselshell Creek 04/22/2020
I 29 Lower Lolo Creek Large Wood Installation
J 175 Selway Irrigation Diversion Design 11/19/2019
K 186 Maintain Fence 07/02/2020
L 47 Riparian Planting 04/22/2020
M 199 Treat Exotic Invasive Species on USFS and Private Lands 07/02/2020
N 115 Collect stream, meadow, road data/Project monitoring and inventory via UAV (i.e., drone) to develop and prioritize future projects 11/19/2019
O 122 Review and Technical Assistance for Proposed Partner Actions
P 191 Coordinate with Regional Partners
Q 119 Manage Projects and Administrative duties
R 185 Periodic Status Reports for BPA
S 132 Annual Report February 2020 - January 2021
T 132 Submit Progress Report for the period February 2019 - January 2020