Contract 85449: 2009-026-00 EXP WALLA WALLA JUVENILE AND ADULT PASSAGE IMP
Project Number:
Title:
Umatilla Tribe Ceded Area Juvenile & Adult Fish Passage Improvement
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Walla Walla 100.00%
Contract Number:
85449
Contract Title:
2009-026-00 EXP WALLA WALLA JUVENILE AND ADULT PASSAGE IMP
Contract Continuation:
Previous: Next:
81302: 2009-026-00 EXP MILL CREEK FISH PASSAGE IMPROVEMENTS
  • 89828: 2009-026-00 EXP MILL CREEK FISH PASSAGE IMPROVEMENTS
Contract Status:
Closed
Contract Description:
This contract will provide pre-construction fabrication of concrete "roughness panels" to improve fish passage in the Mill Creek flood control channel. Project construction on-site will occur in 2021. Fabrication needs to begin now due to the total number of panels needed (145), the rate at which they can be built (4 per week, max), and the fabrication facility is outdoors (winter weather negatively affects production).

Existing conditions in Mill Creek present depth and velocity barriers for returning summer steelhead, bull trout, and spring chinook. The roughness panels will replace some existing concrete in the channel. The roughness will create a zone of lower-velocity water, providing depths and velocities favorable to fish passage.
Account Type(s):
Expense
Contract Start Date:
07/01/2020
Contract End Date:
06/30/2021
Current Contract Value:
$150,000
Expenditures:
$150,000

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brian Burns Tri-State Steelheaders Yes Contract Manager brian.burns@tristatesteelheaders.com (509) 529-3543
Jay Chong Bonneville Power Administration Yes Contracting Officer jxchong@bpa.gov (503) 230-4007
Gary James Umatilla Confederated Tribes (CTUIR) No Supervisor garyjames@ctuir.org (541) 429-7285
Andre L'Heureux Bonneville Power Administration Yes Interested Party allheureux@bpa.gov (503) 230-4482
Cory McCaffrey Tri-State Steelheaders No Technical Contact cory@tristatesteelheaders.com (509) 529-3543
Claire McClory Bonneville Power Administration Yes Env. Compliance Lead cdmcclory@bpa.gov (503) 230-5922
John Skidmore Bonneville Power Administration Yes F&W Approver jtskidmore@bpa.gov (503) 230-5494
Corrie Veenstra Bonneville Power Administration Yes COR cxveenstra@bpa.gov (503) 230-3503


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Effective implementation management and timely contract administration B: 119. Project Administration will be completed in a timely manner 06/30/2021 06/29/2021
Completed Annual Report C: 132. Submit Progress Report for the period (July 1, 2020 to June 30, 2021) 06/30/2021 06/30/2021
Environmental Compliance Documentation D: 165. Environmental Compliance Documentation 06/30/2021 06/29/2021
Pre Fabricated roughness panels E: 184. Pre-fabrication of roughness panels. 06/30/2021 06/29/2021

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 184 Install Fish Passage Structure

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 119 Project Administration will be completed in a timely manner
C 132 Submit Progress Report for the period (July 1, 2020 to June 30, 2021)
D 165 Environmental Compliance Documentation
E 184 Pre-fabrication of roughness panels. 07/02/2020