Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 56065 REL 17: 1999-003-01 EXP PNNL TEMPERATURE MONITORING BELOW BONNEVILLE DAM
Project Number:
Title:
Evaluate Spawning of Fall Chinook and Chum Salmon Just Below the Four Lowermost Mainstem Dams
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Basinwide - 100.00%
Contract Number:
56065 REL 17
Contract Title:
1999-003-01 EXP PNNL TEMPERATURE MONITORING BELOW BONNEVILLE DAM
Contract Continuation:
Previous: Next:
56065 REL 12: 1999-003-01 EXP PNNL TEMPERATURE MONITORING BELOW BONNEVILLE DAM
  • 56065 REL 20: 1999-003-01 EXP CHUM SALMON SPAWNING BELOW 4 LOWER DAMS
Contract Status:
Closed
Contract Description:
During FY 2016 PNNL will continue to collect temperature and water surface elevation data in chum salmon spawning habitat within the Ives Island area. These data will be collected at the same locations where they were collected during FY 2015 at the T1LB, T2LB, and T2MC locations within the Ives Island chum salmon spawning complex.

These data will be collected using pre-existing piezometers that are screened to the subsurface at egg pocketdepth. Temperature and water level sensors will be placed inside the piezometers to record the egg pocket temperatures and water surface elevations at the site. Data from one of the locations (T2LB) will be made availableby connecting the sensors to a cellular modem at the surface using a tethered buoy that will remain floating. This system was previously developed and tested during FY 2014. Additionally, environmental permitting considerations were summarized in a BPA memo written by Chris Fryfield (see the attached PNNL buoy memo). The primary purpose of the monitoring effort is to provide BPA and the region with real-time data that can be used to evaluate chum salmon emergence timing and redd dewatering. Monitoring will occur from November 2015 through May 2015. The surface buoy will remain at the field site from November 2015 through August 2016. These data will allow BPA to conserve water, when appropriate, to aid other species when chum salmom embryos are no longer present within the Ives Island area. The data will be
compiled in an annual, calendar year report and provided to BPA electronically. The annual report will provide BPA with an electronic appendix of temperature and water surface elevation data, chum salmon emergence timing estimates, and a brief summary of mean temperature differences between the river and riverbed during both the chum salmon spawning and the chum salmon incubation time periods.

During FY 2016 PNNL will attempt to couple temperature data collected using the new real time buoy system with a pre existing chum salmon emergence timing model.  This will increase the utility of the temperature data collected by allowing for spatially distributed estimates of chum salmon emergence timing based on when and where spawning occurred.
Account Type(s):
Expense
Contract Start Date:
10/01/2015
Contract End Date:
09/30/2016
Current Contract Value:
$50,696
Expenditures:
$50,696

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental Compliance B: 165. Environmental Compliance 12/31/2015 12/31/2015
Temperature and water surface elevation data C: 157. Collect temperature and water surface elevation data in chum spawning areas 09/30/2016 09/30/2016
Completed Annual Report D: 132. Submit Progress Report for the period Jan 2015 through Dec 2015 08/01/2016 07/22/2016
All administrative tasks fulfilled with timely quality products E: 119. Manage and Administer Project 09/30/2016 09/30/2016

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chum (Oncorhynchus keta) - Columbia River ESU (Threatened)
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 10/01/2015
B 165 Environmental Compliance 10/01/2015
C 157 Collect temperature and water surface elevation data in chum spawning areas 10/01/2015
D 132 Submit Progress Report for the period Jan 2015 through Dec 2015 10/01/2015
E 119 Manage and Administer Project 10/01/2015