Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 73982 REL 2: 1988-022-00 EXP UMATILLA FISH PASSAGE OPERATIONS
Project Number:
Title:
Umatilla Fish Passage Operations
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Umatilla 100.00%
Contract Number:
73982 REL 2
Contract Title:
1988-022-00 EXP UMATILLA FISH PASSAGE OPERATIONS
Contract Continuation:
Previous: Next:
71454: 1988-022-00 EXP UMATILLA & WALLA WALLA FISH PASSAGE OPERATIONS
  • 73982 REL 29: 1988-022-00 EXP UMATILLA & WALLA WALLA FISH PASSAGE OPERATIONS
Contract Status:
Closed
Contract Description:
In 2011 Umatilla Fish Passage Operations project and Walla Walla Fish Passage Operations project were once again re-combined into one project to relieve administrative and contracting workloads.  These projects were historically one project and were split at the request of BPA prior to being able to track activities in separate basins.  With the Pisces management tool, work activities can be tracked by basin, therefore the need for the projects to be separated is no longer accurate.  For interim history of the Walla Walla work activities (2000 to 2010) please refer to project 2000-033-00.  



Umatilla Fish Passage Operations Project Activities:

BPA Project Number: 1988-022-00
Performance/Budget Period: January 1, 2012 - December 31, 2012
Technical Contacts:

Gary James, Fisheries Program Manager
Phone: (541) 429-7285
E-mail: garyjames@ctuir.com
Fax: (541) 429-7285

Brian Zimmerman, Fish Passage/Artificial Production Program Supervisor
Phone: (541) 429-7286
E-mail: brianzimmerman@ctuir.com
Fax: (541) 429-7286

Mike Richards, Project Leader
Phone: (541) 429-7276
E-mail: mikerichards@ctuir.com
Fax: (541) 429-7276

Administrative Contacts:

Michelle Thompson, Manager/Administrative Operations
Phone: (541) 429-7227
E-mail: michellethompson@ctuir.com
Fax: (541) 429-7277

E-mail: michellethompson@ctuir.com
Fax: (541) 429-7227

Julie Burke, Fish and Wildlife Administrative Manager
Phone: (541) 429-7292
E-mail: julieburke@ctuir.com
Fax: (541) 429-7292

Background

In the 1980's, CTUIR and ODFW began implementing the Umatilla Fisheries Restoration Plan.  An integral part of that effort was to address inadequate flow and migration conditions by constructing fish passage facilities, initiating a trap and haul program, and implementing the Umatilla Basin Project flow enhancement effort.  The Fish Passage Operations Project objective is to increase adult and juvenile migrant survival in the Umatilla Basin.  The project provides survival benefits for both hatchery and natural production by overseeing and making recommendations to the operation and maintenance of ladders, bypasses, screen sites, trap facilities, and hauling equipment and coordinating these operations with flow enhancement measures and diversion activities.  The project also provides valuable support to other projects by refining fish passage criteria, collecting return and migration data, and collecting and transporting broodstock. ODFW subcontracts on this project under IGA 45300785100-30.    

Project Goal

Increase survival of migrating juvenile and adult salmon and steelhead in the Umatilla Basin by operating passage facilities, flow enhancement measures, trapping facilities, and transport equipment to provide adequate passage conditions.  

Location of Project

Threemile Dam Facility on the lower Umatilla River near the town of Umatilla

McKay Reservoir on McKay Creek just south of the town of Pendleton

The project works in the entire Umatilla River Basin, primarily in the mainstem between river mile 1 and 55 Umatilla River.


NEW ADDITION:

Previous BPA Project Number:  2000-033-00
Previous BPA Project Title: Walla Walla Fish Passage Operations
Performance/Budget Period: January 1 - December 31

Project/Contract Goal:  The long term goal of the 2000-033-00 project, is to increase adult returns of spring Chinook salmon, summer steelhead, and bull trout to the Walla Walla River annually by increasing the survival of migrating juvenile and adult salmonids.  
Our approach is focused on three areas: 1) Monitoring of flow and passage conditions; 2) Operation of passage facilities, trapping facilities, and transport equipment; and 3) Coordination of passage and trapping facilities, transportation, and flow enhancement operations.  

Location of Project:  The project conducts operations primarily within the mainstem Walla Walla River basin and Mill Creek in both Washington and Oregon.  The major BPA facilities associated with the project are located at the Garden City/Lowden II Canal (river mile 31.0), Gardena Farms (formerly Burlingame) Canal (river mile 36.0), Nursery Bridge Dam (river mile 46.0), and Little Walla Walla River (river mile 47.0).  In addition, the project monitors additional sites in the lower Touchet River, Walla Walla River, and Mill Creek.
Account Type(s):
Expense
Contract Start Date:
01/01/2017
Contract End Date:
12/31/2017
Current Contract Value:
$549,245
Expenditures:
$549,245

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Fish counts and transport information B: 157. Adult Return and Transport Data-Umatilla Basin 12/31/2017 12/31/2017
Coordinate Passage Facility Operations-Umatilla Basin C: 191. Coordinate Passage Facility Operations-Umatilla Basin 12/31/2017 12/31/2017
Coordination on adequate migration conditions D: 191. Coordinate Umatilla Passage Program-McKay Release 12/31/2017 12/31/2017
Monitor Passage Conditions E: 186. Monitor Passage Conditions-Umatilla Basin 12/31/2017 12/31/2017
Provide broodstock for artificial propagation program. F: 66. Provide broodstock for artificial production program-Umatilla Basin 12/31/2017 12/31/2017
Safe transport of adult and juvenile fish G: 28. Transport of Upstream And Downstream Migrants-Umatilla Basin 12/31/2017 12/31/2017
Provide Transportation Assistance H: 66. Provide Transportation Assistance-Umatilla Basin 12/31/2017 12/31/2017
Provide technical comments for fish passage improvement efforts I: 122. Provide Facility Design Technical Review-Umatilla Basin 12/31/2017 12/31/2017
CTUIR Umatilla Basin Annual Report (10-1-16 to 9-30-17) J: 132. Umatilla Basin: CTUIR Annual Report (10-1-16 to 9-30-17 ) 12/31/2017
Environmental compliance documentation K: 165. Environmental Compliance 12/31/2017 12/31/2017
Coordinate passage facility operations L: 191. Coordinate Passage Facility Operations-Walla Walla Basin 12/31/2017 12/31/2017
Monitor and document passage conditions for upstream and downstream migrants M: 186. Monitor Passage Conditions-Walla Walla Basin 12/31/2017 12/31/2017
Safe transport of fish collected during salvage operations N: 28. Coordinate and complete salvage operations-Walla Walla Basin 12/31/2017 12/31/2017
Maintenance of adult and juvenile transportation equipment O: 61. Maintain & Operate Hauling Equipment-Umatilla & Walla Walla Basin 12/31/2017 12/31/2017
Finalize AOP for 2017-2018 operations and distribute to cooperators and BPA COTR P: 174. Fish Passage Annual Operating Plan (AOP)-Walla Walla Basin 09/30/2017 09/29/2017
Provide review and comment through project year. Q: 122. Provide Facility Design Technical Review-Walla Walla Basin 12/31/2017 12/31/2017
CTUIR Walla Walla Annual Report (10-1-16 to 9-30-17) R: 132. Walla Walla Basin: CTUIR Annual Report (10-1-16 to 9-30-17) 12/31/2017
BPA project administration requirements complete S: 119. Project Management 12/31/2017 12/31/2017
Provide Input/Information As Needed to ODFW for Umatilla Hatchery AOP T: 174. Provide Input/Information as needed for Umatilla Hatchery AOP 08/31/2017 08/31/2017
Submit BiOp RPA Report in Taurus U: 202. BiOp RPA Report for CY 2016 03/15/2017 03/15/2017
Monthly Status Reports V: 141. Other Reports for BPA 12/31/2017 12/31/2017
Implement Actions for Emergency Low Flows in the Walla Walla River W: 28. Salvage and Rescue Actions for Low Flow Emergency Walla Walla River Basin 06/30/2017 06/30/2017

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 3 instances of WE 28 Trap and Haul
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 2 instances of WE 122 Provide Technical Review and Recommendation
  • 2 instances of WE 174 Produce Plan
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU
  • 1 instance of WE 174 Produce Plan
Coho (O. kisutch) - Unspecified Population
  • 2 instances of WE 28 Trap and Haul
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 3 instances of WE 28 Trap and Haul
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 2 instances of WE 122 Provide Technical Review and Recommendation
  • 2 instances of WE 174 Produce Plan
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 01/01/2017
B 157 Adult Return and Transport Data-Umatilla Basin 01/01/2017
C 191 Coordinate Passage Facility Operations-Umatilla Basin 01/01/2017
D 191 Coordinate Umatilla Passage Program-McKay Release 01/01/2017
E 186 Monitor Passage Conditions-Umatilla Basin 01/01/2017
F 66 Provide broodstock for artificial production program-Umatilla Basin 01/01/2017
G 28 Transport of Upstream And Downstream Migrants-Umatilla Basin 01/01/2017
H 66 Provide Transportation Assistance-Umatilla Basin 01/01/2017
I 122 Provide Facility Design Technical Review-Umatilla Basin 01/01/2017
J 132 Umatilla Basin: CTUIR Annual Report (10-1-16 to 9-30-17 ) 01/01/2017
K 165 Environmental Compliance 01/01/2017
L 191 Coordinate Passage Facility Operations-Walla Walla Basin 01/01/2017
M 186 Monitor Passage Conditions-Walla Walla Basin 01/01/2017
N 28 Coordinate and complete salvage operations-Walla Walla Basin 01/01/2017
O 61 Maintain & Operate Hauling Equipment-Umatilla & Walla Walla Basin 01/01/2017
P 174 Fish Passage Annual Operating Plan (AOP)-Walla Walla Basin 01/01/2017
Q 122 Provide Facility Design Technical Review-Walla Walla Basin 01/01/2017
R 132 Walla Walla Basin: CTUIR Annual Report (10-1-16 to 9-30-17) 01/01/2017
S 119 Project Management 01/01/2017
T 174 Provide Input/Information as needed for Umatilla Hatchery AOP 01/01/2017
U 202 BiOp RPA Report for CY 2016
V 141 Other Reports for BPA 01/01/2017
W 28 Salvage and Rescue Actions for Low Flow Emergency Walla Walla River Basin 01/01/2017