Contract 76826 REL 1: 2002-011-00 EXP KOOTENAI RIVER OPS MITIGATION & EVALUATION
Project Number:
Title:
Kootenai River Floodplain Ecosystem Operational Loss Assessment, Protection, Mitigation and Rehabilitation Project
Stage:
Implementation
Area:
Province Subbasin %
Mountain Columbia Kootenai 100.00%
Contract Number:
76826 REL 1
Contract Title:
2002-011-00 EXP KOOTENAI RIVER OPS MITIGATION & EVALUATION
Contract Continuation:
Previous: Next:
74469: 2002-011-00 EXP KOOTENAI RIVER OPS MITIGATION & EVALUATION
  • 76826 REL 8: 2002-011-00 EXP KOOTENAI RIVER OPS MITIGATION & EVALUATION
Contract Status:
Closed
Contract Description:
Under this contract, the Kootenai Tribe of Idaho and Montana Fish, Wildlife and Parks will continue to apply the Operational Loss Assessment and the Kootenai River Operational Mitigation and Evaluation Plan by identifying, designing, and implementing management actions that offset wildlife impacts caused by the operation of Libby Dam. Restoration planning and implementation activities conducted by KTOI are divided between three projects: 2002-011-00, 2002-008-00, and 1992-061-00. Additionally, this project coordinates and subcontracts with Montana Fish, Wildlife and Parks to mitigate wildlife impacts in the Montana section of the Kootenai River floodplain. Many of the restoration activities in Montana are occurring in cooperation with the Army Corps of Engineers.

The original name of this project was the “Kootenai River Floodplain Ecosystem Operational Loss Assessment, Protection, Mitigation and Rehabilitation Project”, which was originally shortened to Kootenai River Operational Loss Assessment for the contract title.  In FY2016, the project and contract title was changed to “Kootenai River Ops Mitigation and Evaluation (KROME)” to more accurately reflect the scope of the contract. The title changes reflect the project’s evolution over time from a RM&E focused contract to one that focuses on planning and implementation of on-the-ground mitigation/restoration activities to offset operational impacts.
Account Type(s):
Expense
Contract Start Date:
12/01/2017
Contract End Date:
11/30/2018
Current Contract Value:
$733,712
Expenditures:
$733,712

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Edward Gresh Bonneville Power Administration Yes Env. Compliance Lead esgresh@bpa.gov (503) 230-5756
Heidi Haak Bonneville Power Administration No Interested Party hlhaak@bpa.gov (541) 922-6856
Sue Ireland Kootenai Tribe Yes Supervisor ireland@kootenai.org (208) 267-3620
Norm Merz Kootenai Tribe Yes Contract Manager merz@kootenai.org (208) 267-3620x555
Christopher Roper Bonneville Power Administration No CO Assistant cproper@bpa.gov (503) 230-3514
Edna Runyan Kootenai Tribe Yes Administrative Contact edna@kootenai.org (208) 267-3620
Tybee Sheidler Bonneville Power Administration No CO Assistant tasheidler@bpa.gov (503) 230-3820
Scott Soults Kootenai Tribe Yes Supervisor soults@kootenai.org (208) 267-3620
Virgil Watts III Bonneville Power Administration Yes COR vlwatts@bpa.gov (503) 230-4625
Dorothy Welch Bonneville Power Administration Yes F&W Approver dwwelch@bpa.gov (503) 230-5479
Elham Zolmajd-Haghighi Bonneville Power Administration Yes Contracting Officer ezolmajd-haghighi@bpa.gov (503) 230-7414


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Project Administration B: 119. Oversight and administer Planning and Design and new project activities 11/30/2018 11/30/2018
Reports Documenting Coordination Meetings C: 189. Planning, Design & Coordination of Existing & New Projects 11/30/2018 11/30/2018
Operational Loss Relational Database D: 160. Operational Loss Relational Database 11/30/2018 11/30/2018
Produce accessible, error-checked datasets E: 157. Monitor biological communities in the floodplain and within project areas 11/30/2018 11/30/2018
Design restoration projects in the canyon reach of the Kootenai River F: 175. Restoration opportunity identification and design - canyon reach (FWP) 11/30/2018 11/30/2018
Design restoration project along the Meander Reach of the Kootenai River G: 175. Restoration opportunity identification and design - Meander Reach 11/30/2018 11/30/2018
EC compliance H: 165. Complete EC and permitting for Meander Reach Projects (WE 175) 11/30/2018 11/30/2018
Summary of project implementation and pictures I: 181. Implementation of Phase 2 of Nimz Central Quad 11/30/2018 11/30/2018
EC compliance (WE 47) J: 165. Complete EC for Riparian Planting (WE 47) 11/30/2018 11/30/2018
Completed Riparian Plantings K: 47. Plant riparian vegetation (FWP) 11/30/2018 11/30/2018
Propose New Protection Projects to BPA L: 114. Identify potential protection mitigation purchases 11/30/2018 11/30/2018
Completed Work Related to Property Pre-Acquisition M: 172. Potential Land Acquisition Tasks and Evaluations 11/30/2018 11/30/2018
Annual Report N: 132. Produce Annual Progress Report 11/30/2018 11/30/2018

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Wildlife
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 181 Create, Restore, and/or Enhance Wetland
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 114 Identify and Select Projects
  • 2 instances of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 12/01/2017
B 119 Oversight and administer Planning and Design and new project activities 12/01/2017
C 189 Planning, Design & Coordination of Existing & New Projects 12/01/2017
D 160 Operational Loss Relational Database 12/01/2017
E 157 Monitor biological communities in the floodplain and within project areas 12/01/2017
F 175 Restoration opportunity identification and design - canyon reach (FWP) 12/01/2017
G 175 Restoration opportunity identification and design - Meander Reach 12/01/2017
H 165 Complete EC and permitting for Meander Reach Projects (WE 175) 12/01/2017
I 181 Implementation of Phase 2 of Nimz Central Quad 12/01/2017
J 165 Complete EC for Riparian Planting (WE 47) 12/01/2017
K 47 Plant riparian vegetation (FWP) 01/02/2018
L 114 Identify potential protection mitigation purchases 12/01/2017
M 172 Potential Land Acquisition Tasks and Evaluations 12/01/2017
N 132 Produce Annual Progress Report 12/01/2017