Contract 74314 REL 51: 2010-070-00 EXP WA ESTUARY MOA PROJECT DEVELOPMENT
Project Number:
Title:
Lower Columbia River Estuary Scoping & Implementation
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia River Estuary Columbia Estuary 100.00%
Contract Number:
74314 REL 51
Contract Title:
2010-070-00 EXP WA ESTUARY MOA PROJECT DEVELOPMENT
Contract Continuation:
Previous: Next:
74314 REL 16: 2010-070-00 EXP WA ESTUARY MOA PROJECT SCOPING
  • 74314 REL 84: 2010-070-00 EXP WA ESTUARY MOA PROJECT DEVELOPMENT
Contract Status:
Closed
Contract Description:
The federal Action Agencies that operate the Federal Columbia River Power System (FCRPS) have asked the state of Washington to join in a partnership to expedite habitat restoration efforts for salmon and steelhead in the Columbia River Estuary below Bonneville Dam. On September 16, 2009 the Washington Governor and Director of Washington Department of Fish and Wildlife (WDFW) signed the Estuary Habitat Memorandum of Agreement (Estuary MOA) with the Action Agencies. The Estuary MOA established a nine-year funding arrangement for habitat restoration in the lower
Columbia River and tidally influenced tributaries – from Bonneville Dam to the mouth of the Columbia River where it flows into the Pacific Ocean.

During this contract period, WDFW will: coordinate tasks for the South Unit Shillapoo and Buckmire Slough Restoration Project, partner with the Washington Department of Natural Resources on development of the South Bachelor Island Restoration Project, continue support of restoration projects previously completed, and evaluate additional projects if the opportunities arise. Key tasks include concept design, permitting, AEMR, maintaining fish access to restoration projects, public involvement, and evaluation of project needs.
Account Type(s):
Expense
Contract Start Date:
09/01/2018
Contract End Date:
08/31/2019
Current Contract Value:
$329,384
Expenditures:
$329,384

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
All administrative tasks fulfilled with timely quality products A: 119. Manage and Administer WDFW Project 2010-070-00 08/31/2019 08/30/2019
Environmental Compliance Documentation will be provided for all feasibility projects moving to construction. C: 165. Environmental Compliance 08/31/2019 08/30/2019
Construction Management Complete D: 100. Construction oversight for the South Bachelor Island restoration project. 08/31/2019 08/30/2019
Maintain habitat conditions at Chinook estuary E: 186. Chinook Habitat Conditions Management 08/31/2019 08/30/2019
Develop or update (out-year) prioritized Habitat Project list: upload to Pisces F: 114. Evaluate potential estuary restoration projects 08/31/2019 08/30/2019
Produce accessible, error-checked datasets and deliver to LCEP G: 157. Perform AEMR for existing and future MOA Estuary Projects 08/31/2019 08/30/2019
MOA Portion of Planning and Project Development H: 174. South Unit Shillapoo Project Development 08/31/2019 08/30/2019
Completed Annual Report I: 132. Submit Progress Report for the period 9/1/2017 to 8/31/2018 08/31/2019 08/30/2019

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 100 Construction Management
Chum (Oncorhynchus keta) - Columbia River ESU (Threatened)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 100 Construction Management
Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 100 Construction Management
Coho (O. kisutch) - Unspecified Population
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 100 Construction Management

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Manage and Administer WDFW Project 2010-070-00 09/01/2018
B 185 Periodic Status Reports for BPA 09/01/2018
C 165 Environmental Compliance 09/01/2018
D 100 Construction oversight for the South Bachelor Island restoration project. 09/01/2018
E 186 Chinook Habitat Conditions Management 09/01/2018
F 114 Evaluate potential estuary restoration projects 09/01/2018
G 157 Perform AEMR for existing and future MOA Estuary Projects 09/01/2018
H 174 South Unit Shillapoo Project Development 09/01/2018
I 132 Submit Progress Report for the period 9/1/2017 to 8/31/2018 09/01/2018