Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 74017 REL 104: 2002-068-00 EXP HABITAT RESTORATION RM&E
Project Number:
Title:
Evaluate Stream Habitat- Nez Perce Tribe Watershed Monitoring and Evaluation (M&E) Plan
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
74017 REL 104
Contract Title:
2002-068-00 EXP HABITAT RESTORATION RM&E
Contract Continuation:
Previous: Next:
74017 REL 85: 2002-068-00 EXP HABITAT RESTORATION RM&E
Contract Status:
Closed
Contract Description:
The primary objective of this contract is to complete project-scale monitoring activities in support of, and in collaboration with, a Programmatic Approach for Action Effectiveness Monitoring (AEM) developed by the Northwest Fisheries Science Center and the Bonneville Power Administration. Specifically, snorkel and channel-profile surveys will be conducted throughout treatment and control sites established for a partial passage-barrier removal project in Northeast Oregon to conclude current AEM field activities identified for monitoring and evaluation of partial passage barrier projects. Collaboration and support will be extended to AEM coordinators at Cramer Fish Sciences to analyze and interpret the data, as well as for the completion of associated reports for Programmatic AEM MBACI activities. As these surveys comprise the entirety of AEM field activities identified for CY22, additional habitat monitoring not associated with the AEM program is also to be conducted under this contract.

CY22 Implementation Summary

Habitat restoration projects identified for monitoring and evaluation or species and habitat surveys under this contract include:

• Lostine River Tulley-Hill Diversion AEM partial barrier project (implemented)
• Lostine River MP 5.7 floodplain and side-channel reconnection project (planned)
• Little Salmon River Zim's beaver dam analog project (planned)
• South Fork Clearwater River floodplain and side-channel reconnection project (planned)
• Red River large woody debris project (proposed)
• Newsome Creek large woody debris project (proposed)
• Lochsa River watershed (spatially distributed eDNA surveys)
• Lolo Creek watershed (spatially distributed electrofishing and eDNA surveys)
• Lapwai Creek watershed (spatially distributed habitat surveys)
Account Type(s):
Expense
Contract Start Date:
04/01/2022
Contract End Date:
03/31/2023
Current Contract Value:
$225,778
Expenditures:
$225,778

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration Yes Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Clint Chandler Nez Perce Tribe Yes Contract Manager clintc@nezperce.org (208) 621-3550
Lisa Dexter Bonneville Power Administration No Administrative Contact lldexter@bpa.gov (503) 230-3893
Arleen Henry Nez Perce Tribe No Interested Party arleenh@nezperce.org (208) 621-3833
Eric Leitzinger Bonneville Power Administration Yes F&W Approver ejleitzinger@bpa.gov (503) 230-3534
Jessica Power Bonneville Power Administration Yes CO Assistant jdpower@bpa.gov (503) 230-4023
Matthew Schwartz Bonneville Power Administration Yes COR mdschwartz@bpa.gov (503) 230-4225
Emmit Taylor, Jr. Nez Perce Tribe No Supervisor emmitt@nezperce.org (208) 621-3544
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Environmental compliance documentation submitted to BPA A: 165. Provide environmental compliance information to BPA 03/31/2023 09/14/2022
Effective implementation management and timely contract administration B: 119. Management, Coordination, and Communication 03/31/2023 03/31/2023
AEM MBACI Partial Barrier monitoring data C: 157. Partial Barrier data collection 03/31/2023 03/31/2023
Floodplain reconnection monitoring data D: 157. Floodplain Reconnection data collection 03/31/2023 03/31/2023
Single-pass electrofishing data E: 157. Backpack Electrofishing data collection 03/31/2023 03/31/2023
Environmental DNA field samples F: 157. eDNA data collection 03/31/2023 03/31/2023
In-channel wood placement monitoring data G: 157. In-Channel Wood Placement data collection 03/31/2023 03/31/2023
Aquatic habitat datasets H: 157. Aquatic Habitat data collection 03/31/2023 03/31/2023
Report out FY 2022 AEM project to Cramer Fish Sciences I: 132. Collaborate to Produce Annual AEM Program Report 03/31/2023 03/31/2023

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 6 instances of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Provide environmental compliance information to BPA
B 119 Management, Coordination, and Communication 09/14/2022
C 157 Partial Barrier data collection 09/14/2022
D 157 Floodplain Reconnection data collection 09/14/2022
E 157 Backpack Electrofishing data collection 09/14/2022
F 157 eDNA data collection 09/14/2022
G 157 In-Channel Wood Placement data collection 09/14/2022
H 157 Aquatic Habitat data collection 09/14/2022
I 132 Collaborate to Produce Annual AEM Program Report
J 185 Periodic Status Reports for BPA