Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 56662 REL 281: 1997-056-00 EXP YAKAMA SOUTHERN TERRITORIES HABITAT PROJECT
Project Number:
Title:
Yakama Southern Territories Habitat Project (STHP)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Gorge Klickitat 100.00%
Contract Number:
56662 REL 281
Contract Title:
1997-056-00 EXP YAKAMA SOUTHERN TERRITORIES HABITAT PROJECT
Contract Continuation:
Previous: Next:
56662 REL 259: 1997-056-00 EXP KLICKITAT WATERSHED ENHANCEMENT
  • 94306: 1997-056-00 EXP YAKAMA SOUTHERN TERRITORIES HABITAT PROJECT
Contract Status:
Issued
Contract Description:
SOUTHERN TERRITORIES HABITAT PROJECT

The overall goal of the Southern Territories Habitat Project (STHP) is to restore watershed processes to aid the recovery of salmonid stocks in the Mid-Columbia Region.  The Yakama Nation Fisheries Program and Yakima-Klickitat Fisheries Project (YKFP) work throughout the Yakama Reservation, usual-and-accustomed and ceded areas, managing harvest, habitat, and hatcheries, and conducting research, monitoring and evaluation around salmon, steelhead, lamprey, sturgeon, bridgelip suckers and other fish of tribal and ecological importance.  The long-term and landscape-scale view of resource management held by Yakama people—that everything is connected— is reflected in the approach to protecting and restoring healthy and resilient habitats and is succinctly stated as a “watershed” or “ridgetop to ridgetop” approach. The proposed expansion of the geographic scope of this project is a reflection of the YN’s landscape level approach and a recognition that species of concern span administrative and watershed boundaries and thus recovery efforts benefit from a larger spatial scope.

STHP is sub-project within the YKFP.  The YKFP is a joint project of the Yakama Nation (lead entity) and the Washington State Department of Fish and Wildlife and is sponsored in large part by the Bonneville Power Administration with oversight and guidance from the Northwest Power and Conservation Council. The goal of the YKFP is to restore sustainable and harvestable populations of salmon, steelhead and other at-risk species that were historically present within Yakama Territories. In addition, to habitat protection and restoration work, YKFP pursues hatchery supplementation or reintroduction strategies to achieve the project goals.

PROJECT GOALS

To achieve the broad goal of restoring watershed processes to aid salmonid recovery, STHP utilizes a three prong approach:
- Assess watershed, habitat and fish conditions/status to inform the prioritization of restoration activities.
- Protect, restore, and enhance priority watershed and reaches.
- Provide educational opportunities and public outreach related to salmon, habitat, and water quality and watershed health.

Project Prioritization:

In 2021 the Klickitat Lead Entity Technical Committee collaboratively analyzed the most current biological and physical habitat data to prioritize areas and actions for habitat restoration at the watershed level. The Salmon Recovery Strategy Prioritization Framework determined tier A, B, and C priority areas and prioritized potential restoration projects within the Klickitat, White Salmon and Rock Ck basins. The Prioritization Framework and results can be found at: https://klickitatcounty.org/243/Salmon-Habitat-Recovery.

The Tepee Creek LTPBR reach is located within the White Creek Subwatershed which is a high ranking Tier A subwatershed. The
Tepee Creek LTPBR project will address high priority limiting habitat factors as defined by the prioritization framework, to benefit the limiting life stages for steelhead (rearing and spawning) by adding small diameter wood to increase channel roughness and increase pool frequency. Implementation will result in reducing channel downcutting, improved channel complexity, increasing pool frequency, floodplain reconnection, and sediment deposition and sorting.

The Swale Creek LTPBR reach is located within the Swale Creek Subwatershed which is a high ranking Tier B subwatershed. The
Swale Creek LTPBR project will address high priority limiting habitat factors as defined by the prioritization framework, to benefit the limiting life stages for steelhead (rearing and spawning) by adding small diameter wood to increase channel roughness and increase pool frequency. Implementation will result in enhancing floodplain and riparian function.

The Rattlesnake Gulch Road x-ing project reach is located within the Swale Creek Subwatershed which is a high ranking Tier B subwatershed. The Rattlesnake Gulch Road x-ing LTPBR project will address high priority limiting habitat factors as defined by the prioritization framework, to benefit the limiting life stages for steelhead (rearing and spawning) by reconnecting ~3 miles of steelhead habitat and restoring natural sediment, water, and drainage patterns, especially at tributary mouths.

Project Design:

Tepee Creek LTPBR  - Anabranch Solutions, 2021, IGC 56662 REL 235

Swale Creek LTPBR  - Anabranch Solutions, 2021, IGC 56662 REL 235

Rattlesnake Gulch Road x-ing - Parr Excellence, 2021-2022, IGC 56662 REL 235 and 259

Howard Lake 32 Rd/Upper Klickitat Floodplain Enhancement - Parr Excellence, 2022-2023, IGC 56662 REL 259

White Creek LWD Replenishment Phase 2 - YN, 2022-2023, IGC 56662 REL 259

Lower Snyder Creek Restoration - Inter-Fluve, 2022-2024, IGC 56662 REL 259

Project Construction:

Tepee Creek LTPBR (year 2 implementation - design (Anabranch Solutions, 2021) and permitting complete.  Construction will be conducted by YN staff and partners.

Swale Creek LTPBR (year 1 implementation) -  the design (Anabranch Solutions, 2021)  is complete and permitting nearly complete (SEC 106 in-progress).  Construction will be conducted by YN staff, subcontracted stewardship crew and partners.

Rattlesnake Gulch Road x-ing (Swale Ck trib) - the design is complete (Parr Excellence 2021-2022) and permitting in progress.  The construction will be subcontracted, and RFP will be issued spring 2023.
Account Type(s):
Expense
Contract Start Date:
04/01/2023
Contract End Date:
03/31/2024
Current Contract Value:
$1,250,650
Expenditures:
$1,000,520

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
David Lindley Yakama Confederated Tribes Yes Contract Manager dlindley@ykfp.org (509) 369-3565
Tiffany Petersen Yakama Confederated Tribes Yes Interested Party tpetersen@ykfp.org (509) 790-8798
Jessica Power Bonneville Power Administration Yes CO Assistant jdpower@bpa.gov (503) 230-4023
Bill Sharp Yakama Confederated Tribes Yes Supervisor Bill_Sharp@yakama.com (509) 865-5121x6355
Carolyn Sharp Bonneville Power Administration No Env. Compliance Lead casharp@bpa.gov (503) 230-5206
John Skidmore Bonneville Power Administration Yes F&W Approver jtskidmore@bpa.gov (503) 230-5494
Morgan Tynan Yakama Confederated Tribes No Interested Party morgan_tynan@yakama.com (509) 945-6083x6352
Adrienne Wilson Yakama Confederated Tribes No Administrative Contact Adrienne_Wilson@Yakama.com (509) 865-5121x6306
Jesse Wilson Bonneville Power Administration Yes COR jcwilson@bpa.gov (503) 230-4506
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Effective implementation management and timely contract administration A: 119. BPA and SRFB Project Management and Administration 03/31/2024 03/31/2024
Prepare Necessary Documentation for Various Environmental Compliance Needs B: 165. Prepare Necessary Documentation for Various Environmental Compliance Needs 03/31/2024 03/31/2024
YKFP Watershed Coordination C: 191. Coordination of YKFP Restoration 03/31/2024 03/31/2024
Salmon Education and Habitat Education/Outreach D: 99. Project Outreach 03/31/2024 03/31/2024
Develop or update (out-year) prioritized Habitat Project list: Upload to CBFish E: 114. Select, Prioritize, and Begin to Develop Projects for Implementation Over the Next 2-3 Years 03/31/2024 03/31/2024
Attend Technical Meetings F: 122. Assist Planning Activities - Technical Review 03/31/2024 03/31/2024
Complete Final Design for Howard Lake Road/Upper Klickitat Floodplain Enhancement G: 175. Klickitat: Produce Design - Howard Lake Road/Upper Klickitat Floodplain Enhancement 03/31/2024 03/31/2024
Complete final design and permitting for White Creek LWD Phase 2. H: 175. Klickitat: Produce Design - White Creek LWD Phase 2 03/31/2024 03/31/2024
Submit Conceptual Designs for lower Snyder Creek and Confluence. I: 175. Klickitat: Snyder Creek Confluence and Klickitat Side Channel 03/31/2024 03/31/2024
LTPBR treatments completed on 2.0 miles of Tepee Creek J: 29. Klickitat: LTPBR - Tepee Creek RM 0.0-2.0 - Small Diameter Wood Placement 10/31/2023 11/17/2023
LTPBR treatments completed on 1.0 miles of Swale Creek. K: 29. Klickitat: LTPBR - Lower Swale Creek RM 1.0-2.0 - Small Diameter Wood Placement 10/31/2023 10/27/2023
Remove Fish Passage Barrier - Rattlesnake Gulch Ck (Swale Ck Tributary) L: 85. Rattlesnake Gulch Ck (Swale Ck Tributary) - Replace two culverts with bridges to resolve two partial fish passage barriers 12/31/2023 10/10/2023
Fish passage partial barrier removed M: 85. Rattlesnake Gulch Ck (Swale Ck Tributary) - Remove small dam to resolve full fish passage barrier 10/01/2023 09/29/2023
Aquatic and floodplain complexity actions completed N: 29. Rattlesnake Gulch Ck (Swale Ck Tributary) - Complexity 10/31/2023 09/29/2023
Manage Native Nursery at Klickitat Field Office. O: 47. Klickitat: Manage Native Nursery 03/31/2024 03/31/2024
Removal of invasive vegetation at past project sites will allow for the establishment of native vegetation and prevent simplification of plant communities due to invasive species. P: 198. Klickitat Watershed - Past Restoration Project Sites 11/15/2023 11/15/2023
Monitoring of Past Projects Q: 157. Klickitat: Habitat Enhancement Project Monitoring 03/31/2024 11/10/2023
Project Monitoring Data Analysis R: 162. Klickitat: Summarize/Analyze Habitat Enhancement Monitoring Data 03/31/2024 03/31/2024
Streamflow Monitoring Data for 9 Sites S: 157. Klickitat: Streamflow Monitoring 03/31/2024 03/31/2024
Streamflow Data Analysis T: 162. Klickitat: Summarize/Analyze Streamflow Monitoring Data 03/31/2024 03/31/2024
Administer 200 acre Lease U: 92. Rock Creek: Lease 200 Acres of Land for Fisheries Conservation and Enhancement 03/31/2024 03/31/2024
Obtain lease on 480 acres in Walaluuks Creek for the salmon habitat protection and restoration. V: 92. Rock Creek: Lease 480 acres of Land for Fisheries Conservation and Enhancement 03/31/2024
Non- native, invasive, or encroaching species removed for habitat W: 198. Rock Creek: Invasive Weed Control at Eight Riparian Restoration Sites 11/30/2023 11/30/2023
Plant 200 native trees and shrubs at Shiike II site X: 47. Rock Creek: Plant Vegetation at Shike II site RM 19 03/31/2024 03/31/2024
Riparian plants installed at Gasline, Simcoe, and Milk Creek sites Y: 47. Rock Creek: Plant Riparian Vegetation at Gasline, Simcoe, and Milk Creek 03/31/2024
PIT tag Juvenile Fish in Rock Creek Z: 158. Rock Creek: PIT Tag Juvenile Steelhead 11/30/2023 11/03/2023
PIT Tag 50-500 coho AA: 158. Rock Creek: PIT Tag Juvenile Coho 11/30/2023 11/30/2023
Collect 500 samples from juvenile steelhead for genetic analysis AB: 115. Rock Creek: Genotyping of Juvenile Steelhead and Coho Fin-Clip Samples 03/31/2024 03/31/2024
Conduct juvenile steelhead population and low flow habitat surveys and collect genetic samples AC: 157. Rock Creek: Conduct Juvenile Steelhead Population Surveys 03/31/2024 03/31/2024
Final report of Rock Creek steelhead life histories based from fish PIT tag interrogation AD: 157. Rock Creek: Conduct Adult and Juvenile Steelhead PIT Tag Monitoring 03/31/2024 03/31/2024
Spawning Surveys: Rock Creek database with results presented in Annual Report AE: 157. Rock Creek: Spawning Ground Surveys (redd counts) and Scale Collection 03/31/2024 03/31/2024
Compilation of error checked data and summary report AF: 162. Rock Creek: Analyze Population Monitoring Information 03/31/2024 03/31/2024
Water Monitoring: Rock Creek Data AG: 157. Rock Creek: Water Quality and Temperature 03/31/2024 03/31/2024
Completed Annual Report AH: 132. STHP: Submit Progress Report for the Period (1/1/2021) to (12/31/22) 03/31/2024
Completed Annual Report AI: 132. Rock Creek: Submit Progress Report for the Period (1/1/2021) to (12/31/22) 03/31/2024

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 2 instances of WE 162 Analyze/Interpret Data
Coho (O. kisutch) - Unspecified Population
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals
  • 1 instance of WE 162 Analyze/Interpret Data
Steelhead (Oncorhynchus mykiss) - All Populations
  • 2 instances of WE 47 Plant Vegetation
  • 1 instance of WE 115 Produce Inventory or Assessment
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 2 instances of WE 198 Maintain Vegetation
  • 3 instances of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 47 Plant Vegetation
  • 2 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 2 instances of WE 92 Lease Land
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 3 instances of WE 175 Produce Design
  • 6 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals
  • 3 instances of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 BPA and SRFB Project Management and Administration
B 165 Prepare Necessary Documentation for Various Environmental Compliance Needs
C 191 Coordination of YKFP Restoration
D 99 Project Outreach
E 114 Select, Prioritize, and Begin to Develop Projects for Implementation Over the Next 2-3 Years
F 122 Assist Planning Activities - Technical Review
G 175 Klickitat: Produce Design - Howard Lake Road/Upper Klickitat Floodplain Enhancement 03/02/2023
H 175 Klickitat: Produce Design - White Creek LWD Phase 2 03/02/2023
I 175 Klickitat: Snyder Creek Confluence and Klickitat Side Channel 03/02/2023
J 29 Klickitat: LTPBR - Tepee Creek RM 0.0-2.0 - Small Diameter Wood Placement 04/19/2023
K 29 Klickitat: LTPBR - Lower Swale Creek RM 1.0-2.0 - Small Diameter Wood Placement 08/28/2023
L 85 Rattlesnake Gulch Ck (Swale Ck Tributary) - Replace two culverts with bridges to resolve two partial fish passage barriers 06/21/2023
M 85 Rattlesnake Gulch Ck (Swale Ck Tributary) - Remove small dam to resolve full fish passage barrier 06/21/2023
N 29 Rattlesnake Gulch Ck (Swale Ck Tributary) - Complexity 06/21/2023
O 47 Klickitat: Manage Native Nursery 04/19/2023
P 198 Klickitat Watershed - Past Restoration Project Sites 04/19/2023
Q 157 Klickitat: Habitat Enhancement Project Monitoring 04/19/2023
R 162 Klickitat: Summarize/Analyze Habitat Enhancement Monitoring Data
S 157 Klickitat: Streamflow Monitoring 04/19/2023
T 162 Klickitat: Summarize/Analyze Streamflow Monitoring Data
U 92 Rock Creek: Lease 200 Acres of Land for Fisheries Conservation and Enhancement 07/17/2023
V 92 Rock Creek: Lease 480 acres of Land for Fisheries Conservation and Enhancement 07/17/2023
W 198 Rock Creek: Invasive Weed Control at Eight Riparian Restoration Sites 04/19/2023
X 47 Rock Creek: Plant Vegetation at Shike II site RM 19 10/30/2023
Y 47 Rock Creek: Plant Riparian Vegetation at Gasline, Simcoe, and Milk Creek 07/19/2023
Z 158 Rock Creek: PIT Tag Juvenile Steelhead 04/19/2023
AA 158 Rock Creek: PIT Tag Juvenile Coho 04/19/2023
AB 115 Rock Creek: Genotyping of Juvenile Steelhead and Coho Fin-Clip Samples 04/19/2023
AC 157 Rock Creek: Conduct Juvenile Steelhead Population Surveys 04/19/2023
AD 157 Rock Creek: Conduct Adult and Juvenile Steelhead PIT Tag Monitoring 04/19/2023
AE 157 Rock Creek: Spawning Ground Surveys (redd counts) and Scale Collection 04/19/2023
AF 162 Rock Creek: Analyze Population Monitoring Information
AG 157 Rock Creek: Water Quality and Temperature 04/19/2023
AH 132 STHP: Submit Progress Report for the Period (1/1/2021) to (12/31/22)
AI 132 Rock Creek: Submit Progress Report for the Period (1/1/2021) to (12/31/22)
AJ 185 Periodic Status Reports for BPA