RSS Feed for updates to Project 1995-033-00 - Yakima Phase II Fish Screens Operations and Maintenance (O&M) with Bureau of Reclamation (BOR) Follow this via RSS feed. Help setting up RSS feeds?

Project Summary

Project 1995-033-00 - Yakima Phase II Fish Screens Operations and Maintenance (O&M) with Bureau of Reclamation (BOR)
Project Number:
1995-033-00
Title:
Yakima Phase II Fish Screens Operations and Maintenance (O&M) with Bureau of Reclamation (BOR)
Summary:
In accordance with the Pacific Northwest Electric Power Planning and Conservation Act, Bonneville is funding the operation and maintenance of fish protection, mitigation and enhancement facilities in the Yakima River Basin. Reclamation already operates and maintains similar facilities, and is willing to operate and maintain Bonneville's facilities at Bonneville's expense. Reclamation operations and maintains 5 sites exclusively and shares responsibility of 28 other fish screen sites with Washington State Department of Fish and Wildlife (WDFW).
Yakima Fish Screen Phase II O&M, project # 199503300 continues with Intergovernmental Contract #0004251 effective May 1, 2005. In 1994, a Memorandum of Agreement (MOA) between Bonneville, Reclamation, and WDFW was drafted and agreed upon (BOR# 1425-4-MA-10-00840, WDFW# 241-950010). This MOA, through the use of an Annual Work Plan (AWP), assigns specific duties to Reclamation for O&M of Phase II facilities and is funded by Bonneville through master contract #00000026-00001.
Proposer:
None
Proponent Orgs:
US Bureau of Reclamation (BOR) (Govt - Federal)
Starting FY:
1995
Ending FY:
2014
Stage:
Area:
Province Subbasin %
Columbia Plateau Yakima 100.00%
Purpose:
Habitat
Emphasis:
Restoration/Protection
Focal Species:
All Anadromous Fish
Bass, Smallmouth
Catfish
Chinook - All Populations
Chinook - Mid-Columbia River Spring ESU
Coho - Unspecified Population
Cutthroat Trout, Westslope
Freshwater Mussels
Kokanee
Lamprey, Pacific
Pikeminnow, Northern
Sockeye - All Populations
Steelhead - All Populations
Steelhead - Middle Columbia River DPS
Trout, Brook
Trout, Brown
Trout, Bull
Trout, Lake
Trout, Rainbow
Walleye
Whitefish, Mountain
Species Benefit:
Anadromous: 100.0%   Resident: 0.0%   Wildlife: 0.0%
Special:
None

No photos have been uploaded yet for this Project.

Summary of Budgets

To view all expenditures for all fiscal years, click "Project Exp. by FY"

To see more detailed project budget information, please visit the "Project Budget" page

No Decided Budget Transfers

Pending Budget Decision?  No


Actual Project Cost Share

Current Fiscal Year — 2024
Cost Share Partner Total Proposed Contribution Total Confirmed Contribution
There are no project cost share contributions to show.
Previous Fiscal Years
Fiscal Year Total Contributions % of Budget
2014
2013
2012
2011 $65,000 37%
2010 $125,000 30%
2009
2008
2007

Contracts

The table below contains contracts with the following statuses: Active, Closed, Complete, History, Issued.
* "Total Contracted Amount" column includes contracted amount from both capital and expense components of the contract.
Expense Contracts:
Number Contractor Name Title Status Total Contracted Amount Dates
2351 REL 1 SOW US Bureau of Reclamation (BOR) 1995-033-00 O&M OF YAKIMA RIVER BASIN FISH PROTECTION Terminated $75,602 2/1/1995 - 4/1/2001
4658 SOW US Bureau of Reclamation (BOR) 1995-033-00 O&M OF YAKIMA RIVER BASIN FISH PROTECTION Closed $16,911 4/30/2001 - 10/1/2001
6255 SOW US Bureau of Reclamation (BOR) 1995-033-00 O&M OF YAKIMA PHASE II FISH SCREENS Closed $152,221 8/14/2001 - 4/30/2003
14251 SOW US Bureau of Reclamation (BOR) 1995-033-00 -- O & M OF YAKIMA PHASE II SCREEN Closed $186,870 5/1/2003 - 4/30/2005
22866 SOW US Bureau of Reclamation (BOR) 1995-033-00 EXP YAKIMA PHASE II SCREEN O&M Closed $87,328 5/1/2005 - 4/30/2006
27195 SOW US Bureau of Reclamation (BOR) 1995-033-00 EXP YAKIMA PHASE II SCREEN O&M Closed $103,377 5/1/2006 - 4/30/2007
32813 SOW US Bureau of Reclamation (BOR) 1995-033-00 EXP O&M YAKIMA BASIN FISH SCREENS Closed $80,562 5/1/2007 - 4/30/2008
37516 SOW US Bureau of Reclamation (BOR) 1995-033-00 EXP O&M YAKIMA BASIN FISH SCREENS Closed $97,174 5/1/2008 - 4/30/2009
42838 SOW US Bureau of Reclamation (BOR) 1995-033-00 EXP O&M YAKIMA BASIN FISH SCREENS Closed $193,444 5/1/2009 - 6/30/2010
47426 SOW US Bureau of Reclamation (BOR) 1995-033-00 EXP O&M YAKIMA BASIN FISH SCREENS Closed $236,135 5/1/2010 - 4/30/2012
57192 SOW US Bureau of Reclamation (BOR) 1995-033-00 EXP O&M YAKIMA BASIN FISH SCREENS Closed $138,342 5/1/2012 - 4/30/2014



Annual Progress Reports
Expected (since FY2004):9
Completed:8
On time:8
Status Reports
Completed:47
On time:28
Avg Days Late:22

                Count of Contract Deliverables
Earliest Contract Subsequent Contracts Title Contractor Earliest Start Latest End Latest Status Accepted Reports Complete Green Yellow Red Total % Green and Complete Canceled
6255 14251, 22866, 27195, 32813, 37516, 42838, 47426, 57192 1995-033-00 EXP O&M YAKIMA BASIN FISH SCREENS US Bureau of Reclamation (BOR) 08/14/2001 04/30/2014 Closed 47 64 1 0 3 68 95.59% 0
Project Totals 47 64 1 0 3 68 95.59% 0


The table content is updated frequently and thus contains more recent information than what was in the original proposal reviewed by ISRP and Council.

Review: FY07-09 Solicitation Review

Council Recommendation

Assessment Number: 1995-033-00-NPCC-20090924
Project: 1995-033-00 - Yakima Phase II Fish Screens Operations and Maintenance (O&M) with Bureau of Reclamation (BOR)
Review: FY07-09 Solicitation Review
Approved Date: 10/23/2006
Recommendation: Fund
Comments:

Independent Scientific Review Panel Assessment

Assessment Number: 1995-033-00-ISRP-20060831
Project: 1995-033-00 - Yakima Phase II Fish Screens Operations and Maintenance (O&M) with Bureau of Reclamation (BOR)
Review: FY07-09 Solicitation Review
Completed Date: 8/31/2006
Final Round ISRP Date: None
Final Round ISRP Rating: Meets Scientific Review Criteria
Final Round ISRP Comment:
This proposal would continue O & M on Yakima basin screens, clearly an essential, routine component of the process. The proponents seem to have shown consistent improvement over the history of the project and have a track record of success and monitoring. Proposal 198506200 provides monitoring data using up-to-date technology for the performance of the screens. "A thorough review of O&M activities at one-fourth of all sites each year" is the target for the program. More rationale is needed to support the 25% sample rate as well as information on how the sites are chosen. It is possible that some problem sites are going unattended until it is their turn in the cycle?
Documentation Links:

Legal Assessment (In-Lieu)

Assessment Number: 1995-033-00-INLIEU-20090521
Project Number: 1995-033-00
Review: FY07-09 Solicitation Review
Completed Date: 10/6/2006
In Lieu Rating: Problems Exist
Cost Share Rating: None
Comment: O&M on Phase II Yakima screens; need confirmation that BPA has committed to O&M, otherwise this needs cost share or other remedy.

Capital Assessment

Assessment Number: 1995-033-00-CAPITAL-20090618
Project Number: 1995-033-00
Review: FY07-09 Solicitation Review
Completed Date: 2/27/2007
Capital Rating: Does Not Qualify for Capital Funding
Capital Asset Category: None
Comment: None

Project Relationships: None

Name Role Organization
Tom Leonard (Inactive) Supervisor US Bureau of Reclamation (BOR)
Scott Kline (Inactive) Interested Party US Bureau of Reclamation (BOR)
Peter Lofy Supervisor Bonneville Power Administration
Patrick Schille (Inactive) Interested Party Washington Department of Fish and Wildlife (WDFW)
Edward Gresh Env. Compliance Lead Bonneville Power Administration
Sandra Kobes Administrative Contact US Bureau of Reclamation (BOR)
Arden (BOR) Thomas (Inactive) Administrative Contact US Bureau of Reclamation (BOR)
Joel Hubble (Inactive) Project Lead US Bureau of Reclamation (BOR)
Michelle O'Malley Project Manager Bonneville Power Administration