Summary:
Temporal and spatial predator-prey overlap and consequential predatory impacts on juvenile anadromous salmonids is becoming a major source of their mortality in sections of the Columbia River (Erhardt et al. 2018; McMichael 2018). Currently, 51% of non-native species in the upper Columbia River are piscivores and have negative impacts on native salmonids and on the Columbia River food webs (ISAB 2011; Naiman et al. 2012). Currently, fish predator abundance and population trends, and juvenile salmonid consumption estimates upstream of McNary Dam are not well understood. The objective of this study is to determine the status and trend of non-native fish predator density and abundance upstream of McNary Dam in the mainstem Columbia River. Under an adaptive management approach, predator population abundance and growth rates will be monitored and used to evaluate the effectiveness of current (i.e., deregulating harvest) and future management actions designed to increase juvenile salmon survival, with the ability to identify significant changes in predator population status over time and space.
Proposer:
Proponent Orgs:
Washington Department of Fish and Wildlife (WDFW) (Govt - State)
Starting FY:
2020
Ending FY:
2024
BPA PM:
Stage:
Implementation - Project Status Report
Area:
Province Subbasin %
Mainstem - 100.00%
Purpose:
Predation
Emphasis:
RM and E
Focal Species:
Bass, Smallmouth
Chinook - All Populations
Chinook - Mid-Columbia River Spring ESU
Chinook - Snake River Fall ESU
Chinook - Snake River Spring/Summer
Chinook - Snake River Spring/Summer ESU
Chinook - Upper Columbia River Spring ESU
Chinook - Upper Columbia River Summer/Fall ESU
Chinook - Upper Willamette River ESU
Lamprey, Pacific
Other Resident
Shad, American
Sockeye - All Populations
Sockeye - Lake Wenatchee ESU
Sockeye - Okanogan River ESU
Sockeye - Snake River ESU
Steelhead - All Populations
Steelhead - Middle Columbia River DPS
Steelhead - Snake River DPS
Steelhead - Upper Columbia River DPS
Species Benefit:
Anadromous: 100.0%   Resident: 0.0%   Wildlife: 0.0%
Tags:
None
Special:
None
BiOp Association:
None

No photos have been uploaded yet for this Project.

Summary of Budgets

To view all expenditures for all fiscal years, click "Project Exp. by FY"

To see more detailed project budget information, please visit the "Project Budget" page

Decided Budget Transfers  (FY2023 - FY2025)

Acct FY Acct Type Amount Fund Budget Decision Date
FY2023 Expense $283,907 From: General FY23 SOY Budget Upload 06/01/2022
FY2024 Expense $296,399 From: General FY24 SOY Budget Upload 06/01/2023

Pending Budget Decision?  No


Actual Project Cost Share

Current Fiscal Year — 2024   DRAFT
Cost Share Partner Total Proposed Contribution Total Confirmed Contribution
There are no project cost share contributions to show.
Previous Fiscal Years
Fiscal Year Total Contributions % of Budget
2023 $100,000 26%
2022 $100,000 26%
2021 $100,000 17%
2020 $100,000 100%

Contracts

The table below contains contracts with the following statuses: Active, Closed, Complete, History, Issued.
* "Total Contracted Amount" column includes contracted amount from both capital and expense components of the contract.
Expense Contracts:
Number Contractor Name Title Status Total Contracted Amount Dates
74314 REL 120 SOW Washington Department of Fish and Wildlife (WDFW) 2020-001-00 EXP DEVELOP PROPOSAL/COLLECT DATA Closed $494,534 10/1/2020 - 6/30/2022
84042 REL 13 SOW Washington Department of Fish and Wildlife (WDFW) 2020-001-00 EXP PISCIVOROUS FISH STATUS & TRENDS ABOVE MCNARY Closed $283,907 7/1/2022 - 6/30/2023
84042 REL 44 SOW Washington Department of Fish and Wildlife (WDFW) 2020-001-00 PISCIVOROUS FISH STATUS AND TR Issued $283,907 7/1/2023 - 6/30/2024
CR-369601 SOW Washington Department of Fish and Wildlife (WDFW) 2020-001-00 EXP PISCIVOROUS FISH STATUS AND TR Pending $296,399 7/1/2024 - 6/30/2025



Annual Progress Reports
Expected (since FY2004):3
Completed:0
On time:0
Status Reports
Completed:14
On time:4
Avg Days Late:9

                Count of Contract Deliverables
Earliest Contract Subsequent Contracts Title Contractor Earliest Start Latest End Latest Status Accepted Reports Complete Green Yellow Red Total % Green and Complete Canceled
74314 REL 120 84042 REL 13, 84042 REL 44, CR-369601 2020-001-00 EXP PISCIVOROUS FISH STATUS AND TR Washington Department of Fish and Wildlife (WDFW) 10/01/2020 06/30/2025 Pending 13 15 7 0 12 34 64.71% 0
Project Totals 13 15 7 0 12 34 64.71% 0


The table content is updated frequently and thus contains more recent information than what was in the original proposal reviewed by ISRP and Council.

No assessments are available for this project.
Project Relationships: None

Name Role Organization
Matt Polacek Project Lead Washington Department of Fish and Wildlife (WDFW)
Dan Rawding Interested Party Washington Department of Fish and Wildlife (WDFW)
Edward Gresh Env. Compliance Lead Bonneville Power Administration
Joshua Ashline Project Manager Bonneville Power Administration