Contract 11926: 2002-025-01 YAKIMA TRIBUTARY ACCESS & HABITAT PROGRAM PHASE 2
Project Number:
Title:
Yakima Tributary Access and Habitat Program (YTAHP)
Stage:
Closed
Area:
Province Subbasin %
Columbia Plateau Yakima 100.00%
Contract Number:
11926
Contract Title:
2002-025-01 YAKIMA TRIBUTARY ACCESS & HABITAT PROGRAM PHASE 2
Contract Continuation:
Previous: Next:
n/a
  • 24722: 2002-025-01 CAP YAKIMA TRIBUTARY ACCESS AND HABITAT 2
Contract Status:
History
Contract Description:
Account Type(s):
Capital
Contract Start Date:
10/01/2002
Contract End Date:
09/30/2005
Current Contract Value:
$1,869,361
Expenditures:
$1,869,361

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Edgar Harrell Washington Resource Conservation and Development Yes Technical Contact ytahp@nwinfo.old (509) 454-5736x128
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Jay Marcotte Bonneville Power Administration Yes COR jgmarcotte@bpa.gov (503) 230-3943
Elida Monroe Bonneville Power Administration Yes Contracting Officer emonroe@bpa.gov (503) 230-3821
Dave Myra Washington Resource Conservation and Development No Administrative Contact ytahp@scwrcd.org (509) 454-5736x128
Shannon Stewart Bonneville Power Administration No Env. Compliance Lead scstewart@bpa.gov (503) 230-5928


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Deliverable complete A: 119. Manage YTAHP Program 09/19/2005
Deliverable complete B: 132. YTAHP Annual Report 09/08/2005
Deliverable complete C: 141. Quarterly Status Reports 09/26/2005
Deliverable complete D: 174. Develop Monitoring and Evaluation Plan 09/08/2005
Deliverable Complete E: 165. Obtain Permits (Various projects) 09/30/2005
Deliverable complete F: 114. Identify, prioritize and select potential projects 09/30/2005 09/08/2005
Deliverable complete G: 160. Produce pertinent project maps 09/30/2005 09/19/2005
Deliverable complete H: 175. Engineering
Deliverable complete I: 99. Outreach and Education 09/19/2005
Deliverable complete J: 119. Subcontractor Admin. and Management 09/08/2005
Deliverable complete K: 184. Garretson barrier removal 09/19/2005
Deliverable complete L: 69. Install new Garretson gravity screen 09/19/2005
Deliverable complete M: 69. Install new Llamas pump screen
Deliverable complete N: 84. Llamas diversion removal
Deliverable complete O: 84. Riley diversion removal
Deliverable complete P: 69. Install new Riley pump screen
Deliverable complete Q: 29. Thornton Habitat 09/19/2005
Deliverable complete R: 40. Thornton Fencing 09/08/2005
Deliverable complete S: 47. Thornton Vegetation
Deliverable complete T: 175. Specifications for individual pump screens 09/26/2005
Deliverable complete U: 69. Pump Screen Site 1 09/30/2005 09/08/2005
Deliverable complete V: 69. Pump Screen Site 2 09/30/2005 09/08/2005
Deliverable complete W: 69. Pump Screen Site 3 09/30/2005 09/08/2005
Deliverable complete X: 69. Pump Screen Site 4 09/30/2005 09/08/2005
Deliverable complete Y: 69. Pump Screen Site 5 09/23/2005 09/08/2005
Deliverable complete Z: 149. Sorenson Piping 10/26/2004 09/19/2005
Deliverable complete AA: 82. Fogarty Ring Well - Acheson
Deliverable complete AB: 82. Fogarty Ring Well - Payne
Deliverable complete AC: 22. Maintain Vegetation 09/19/2005
Deliverable complete AD: 118. YTID / Cowiche Water Users Group Agreement
Deliverable complete AE: 84. Snow Mountain Ranch Diversion Removal
Deliverable complete AF: 115. Inventory and Assessment of various streams

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Manage YTAHP Program
B 132 YTAHP Annual Report
C 141 Quarterly Status Reports
D 174 Develop Monitoring and Evaluation Plan
E 165 Obtain Permits (Various projects)
F 114 Identify, prioritize and select potential projects
G 160 Produce pertinent project maps
H 175 Engineering
I 99 Outreach and Education
J 119 Subcontractor Admin. and Management
K 184 Garretson barrier removal
L 69 Install new Garretson gravity screen
M 69 Install new Llamas pump screen
N 84 Llamas diversion removal
O 84 Riley diversion removal
P 69 Install new Riley pump screen
Q 29 Thornton Habitat
R 40 Thornton Fencing
S 47 Thornton Vegetation
T 175 Specifications for individual pump screens
U 69 Pump Screen Site 1
V 69 Pump Screen Site 2
W 69 Pump Screen Site 3
X 69 Pump Screen Site 4
Y 69 Pump Screen Site 5
Z 149 Sorenson Piping
AA 82 Fogarty Ring Well - Acheson
AB 82 Fogarty Ring Well - Payne
AC 22 Maintain Vegetation
AD 118 YTID / Cowiche Water Users Group Agreement
AE 84 Snow Mountain Ranch Diversion Removal
AF 115 Inventory and Assessment of various streams
AG 185