| Environmental Compliance completed |
A: 165. Environmental Compliance Documentation |
|
09/29/2006 |
09/29/2006 |
| Interplanted up to 25 acres |
B: 47. Smith field restoration |
|
09/30/2006 |
09/29/2006 |
| 80 acres treated |
C: 47. Dormaier - restore abandoned fields |
|
09/30/2006 |
09/29/2006 |
| 100 acres summer fallowed |
D: 47. Sagebrush Flat unit - restore 100 acre field |
|
09/30/2006 |
09/29/2006 |
| 0.5 miles of riparian miles planted and prepared |
E: 47. Enhance riparian habitat |
|
09/30/2006 |
09/29/2006 |
| Treat weeds on up to 150 acres. |
F: 22. Weed control on all units of Sagebrush Flat Wildlife Area |
|
09/30/2006 |
09/29/2006 |
| 110 acres maintained |
G: 22. Maintain grouse habitat |
|
09/30/2006 |
09/29/2006 |
| Up to 30 acres and 1.5 mile of riparian habitat maintained |
H: 22. Maintain riparian habitat |
|
09/30/2006 |
09/29/2006 |
| 15 miles of firebreaks maintained |
I: 22. Maintain habitat at Sagebrush Flat |
|
09/30/2006 |
09/29/2006 |
| Debris removed |
J: 27. Remove fence and other debris |
|
09/30/2006 |
09/29/2006 |
| Maintained and repaired up to 12 road miles, 10 parking areas, 5 culverts and numerouse signs |
K: 188. Maintain roads, culverts, parking areas and related informational signs |
|
09/30/2006 |
09/29/2006 |
| 40 miles of fence and gates |
L: 186. Maintain fence |
|
09/30/2006 |
09/29/2006 |
| Counted X number of grouse at lek sites |
M: 157. Monitor sage and sharp-tailed grouse leks |
|
09/30/2006 |
04/30/2006 |
| X number of hours and acres spent searching |
N: 157. Search for new or satellite leks on or adjacent to wildlife area |
|
09/30/2006 |
04/30/2006 |
| Conducted searches |
O: 157. Search for pygmy rabbits and Washington ground squirrels |
|
06/30/2006 |
04/30/2006 |
| Contacted X numbers of hunters and non-hunters using area |
P: 157. Monitor public use of area |
|
09/30/2006 |
09/29/2006 |
| Data summarized, analyzed and interpretation complete |
Q: 162. Compile and interpret lek, pygmy rabbit, WA ground squirrel and public use data |
|
09/30/2006 |
09/29/2006 |
| Tranlocated sharp-tailed grouse |
R: 98. Translocate sharp-tailed grouse to the Bridgeport Unit |
|
09/30/2006 |
04/30/2006 |
| Plan and update completed |
S: 174. Complete Area Management Plan and annual update |
|
09/30/2006 |
09/29/2006 |
| Participant sign-in records |
T: 99. Attend CAG and public meetings as needed. Conduct field trips as needed |
|
09/30/2006 |
09/29/2006 |
| SOW, buget and other reports |
U: 119. General Project administration |
|
09/30/2006 |
09/29/2006 |
| Interplanted up to 25 acres |
V: 132. Produce annual project report |
|
09/30/2006 |
09/29/2006 |
| 15 acres summer fallowed. |
X: 47. Summer fallow contour and mound areas within Sagebrush Flat CRP field |
|
09/30/2006 |
09/29/2006 |