Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 25047: 1999-015-00 RESTORE ANADROMOUS FISH HABITAT IN BIG/NICHOLS CANYON
Project Number:
Title:
Big Canyon Fish Habitat
Stage:
Closed
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
25047
Contract Title:
1999-015-00 RESTORE ANADROMOUS FISH HABITAT IN BIG/NICHOLS CANYON
Contract Continuation:
Previous: Next:
5268: 1999-015-00 RESTORE ANADROMOUS FISH HABITAT - NICHOLS CANYON
  • 26501: 1999-015-00 EXP BIG CANYON WATERSHED RESTORATION
Contract Status:
History
Contract Description:
CY05 Statement of Work

Background:
Big Canyon Creek historically provided quality spawning and rearing habitat for A-run wild summer steelhead in the Clearwater River subbasin.  However, high stream temperatures, excessive sediment and nutrient loads, low summer stream flows, and little instream cover have created anadromous fish habitat constraints for the stream.  The primary sources of these nonpoint source pollutants and habitat degradations are attributed to agricultural, livestock, and forestry practices.

The Clearwater Subbasin Summary states a primary limiting factor for resident salmonid populations is the impact of land management activities on hydrology, sedimentation, habitat distribution and complexity, and water quality.  In the Big Canyon Creek watershed, low stream flows and a lack of adequate multi-layered riparian vegetation have reduced the suitability of the stream and its tributaties as spawning and rearing habitat.  The project actions focus primarily on agricultural lands and the improvement of the limiting factors within these lands.

Reasonable and Prudent Alternative (RPA)
The Northwest Power and Planning Council 2000 Fish and Wildlife Program focuses on rebuilding healthy, naturally producing fish and wildlife populations by protecting, mitigating, and restoring habitats and the biological systems within them.  This project works toward accomplishing the vision and objectives of the program by protecting and restoring ecological functions and habitats of the Big Canyon Creek watershed specifically related to:  Water quantity, water quality, passage and diversion, and watershed health.

The project directly addresses the following RPA actions:

Action #150, #152, and #153.
Account Type(s):
Expense
Contract Start Date:
11/01/2005
Contract End Date:
03/31/2006
Current Contract Value:
$63,848
Expenditures:
$63,848

* Expenditures data includes accruals and are based on data through 30-Apr-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
David Kaplowe Bonneville Power Administration Yes COR djkaplowe@bpa.gov (503) 230-5365
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Lynn Rasmussen Nez Perce Soil and Water Conservation District (SWCD) Yes Contract Manager lynnrasmussen@co.nezperce.id.us (208) 843-2931
Christine Read Bonneville Power Administration Yes Contracting Officer clread@bpa.gov (503) 230-5321
Kimberly St Hilaire Bonneville Power Administration No Env. Compliance Lead krsthilaire@bpa.gov (503) 230-5373


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Project coordination A: 118. General Project Coordination 03/31/2006 03/24/2006
Public meeting B: 99. Public Meeting 02/10/2006 02/15/2006
2 newsletters mailed to 300 people C: 99. Create and mail watershed newsletters to landowners in the Big Canyon Creek watershed. 02/24/2006 02/28/2006
Marketing Plan Developed D: 174. Marketing Plan Completed 03/31/2006 03/31/2006
List of projects for implementation E: 114. Identify and select projects for installation in the Big Canyon Creek watershed. 03/31/2006 03/31/2006
Design package for four land improvement projects. F: 175. Prepare engineering and technical designs 03/31/2006 03/31/2006
6 maintenance plans. G: 174. Develop maintenance plans. 02/28/2006 03/31/2006
Bio-Control Plan H: 174. Develop weed control plan 01/31/2006 02/01/2006
Weed Control Plan I: 174. Weed Control Plan for Mainstem Big Canyon Creek. 02/28/2006 02/28/2006
Finalized Categorical Exclusion (CX) J: 165. Environmental Compliance 02/15/2006 02/17/2006
0.2 miles riparian plantings; 4 acres grass seeding K: 47. Plant vegetation 03/31/2006 03/31/2006
300 acres seeded with direct seeding systems L: 48. Install direct seeding systems 11/30/2005 12/12/2005
Temperature data M: 157. Stream Temperature Data Collection in the Big Canyon Creek Watershed 12/30/2005 12/30/2005
Data sent to StreamNet statewide database. N: 161. Supply publicly available databases on an annual basis to the Idaho StreamNet Project Leader. 02/09/2006 02/09/2006
Inventory Protocol O: 156. Develop stream inventory method 03/31/2006 03/31/2006
Stream reaches identified P: 157. Stream Reaches Identified for future inventory 03/31/2006 01/31/2006
GIS database Q: 160. Create GIS database 03/31/2006 03/31/2006
Annual report for FY 04 contract R: 132. Contract period final report 03/31/2006 03/31/2006
SOW package for next contract T: 119. Manage and Administer Project 01/04/2006 02/24/2006

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 48 Practice No-till and Conservation Tillage Systems
  • 4 instances of WE 174 Produce Plan
  • 1 instance of WE 175 Produce Design
  • 2 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 118 General Project Coordination
B 99 Public Meeting
C 99 Create and mail watershed newsletters to landowners in the Big Canyon Creek watershed.
D 174 Marketing Plan Completed
E 114 Identify and select projects for installation in the Big Canyon Creek watershed.
F 175 Prepare engineering and technical designs
G 174 Develop maintenance plans.
H 174 Develop weed control plan
I 174 Weed Control Plan for Mainstem Big Canyon Creek.
J 165 Environmental Compliance
K 47 Plant vegetation
L 48 Install direct seeding systems
M 157 Stream Temperature Data Collection in the Big Canyon Creek Watershed
N 161 Supply publicly available databases on an annual basis to the Idaho StreamNet Project Leader.
O 156 Develop stream inventory method
P 157 Stream Reaches Identified for future inventory
Q 160 Create GIS database
R 132 Contract period final report
S 185 Quarterly status reports
T 119 Manage and Administer Project