Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 25662: PI 1994-017-00 PL IDAHO MODEL WATERSHED HABITAT- LEMHI
Project Number:
Title:
Idaho Model Watershed Habitat
Stage:
Closed
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
25662
Contract Title:
PI 1994-017-00 PL IDAHO MODEL WATERSHED HABITAT- LEMHI
Contract Continuation:
Previous: Next:
19794: PI 1994-017-00 PL ADMIN/IMPLEMENTATION HOLISTIC RESTORATION
Contract Status:
History
Contract Description:
The project scope is to implement high priority action items to maintain, enhance and restore fish habitat and fish passage in the priority stream segments of the Upper Salmon Basin Watershed Project area within the administrative boundaries of the Lemhi Soil and Water Conservation District.

Implementation of measures funded under this plan will achieve the objective of the Northwest Power Planning Council's Strategy for Salmon Recovery, the National Marine Fisheries Service Salmon Recovery Plan in terms of stabilizing and improving habitat for anadromous fish and the "Four Governors Salmon Recovery Recommendations for Salmon Recovery".

Migratory and habitat connectivity across the watershed's valley bottom areas is of high importance to ecologically-based restoration efforts because the tributary sub-watersheds tend to be dominated by federal lands and often provide habitat strongholds for native species of fish and wildlife.

Key habitat limitations in the watershed's bottomland areas include migration problems/ blockages and streambed sedimentation. Addressing these limitations may offer an opportunity to enhance the watershed's anadromous salmonids and will clearly benefit other native species of salmonids, other fish, and wildlife.  The primary opportunity for addressing these problems in the Lemhi and Mid Salmon- Panther watersheds is through the LSWCD and the USBWP and their collaborative efforts on non-federal land.

The goal of the projects identified is to improve anadromous fish passage in both specific local reaches and the overall aquatic health of the sub-basin. Enhance the watershed to maintain and restore balance with watershed processes that will restore geomorphic diversity, reduce bank erosion, lower summer temperatures and improve fish habitat with assistance from the local watershed group providing local technical support.
Account Type(s):
Expense
Contract Start Date:
01/01/2006
Contract End Date:
12/31/2006
Current Contract Value:
$389,084
Expenditures:
$389,084

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

Env. Compliance Lead:
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Jan Brady Bonneville Power Administration Yes COR jebrady@bpa.gov (503) 230-4514
Mickey Carter Bonneville Power Administration No Env. Compliance Lead macarter@bpa.gov (503) 230-5885
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Elizabeth Olson Lemhi Soil and Water Conservation District (SWCD) Yes Administrative Contact lemhiscd@custertel.net.bad (208) 756-3211x101
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Diversion fish passage improved A: 119. Manage and administer projects
Bid documents and landowner contracts B: 118. EXPIRED: landowner coordination 09/30/2006 08/15/2006
meeting notes C: 118. EXPIRED: Board meetings
Diversion modification complete D: 84. L13 10/20/2006
Diversion repair complete E: 84. L3ao fix
Siphon Installed F: 80. Big Timber 09/30/2006 09/10/2006
Fence Installed G: 40. Side channel rearing 09/15/2006
Structure installed H: 84. Side channel rearing 09/15/2006
Fish passage improved I: 84. L44 fix 08/31/2006
Installation of irrigation pipe J: 149. Install irrigation pipe--SVGC
Installation of sprinkler system K: 150. Install sprinkler system--SGVC
Submit FY 05 annual report M: 132. Fy05 annual report 06/26/2006 06/26/2006

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 149 Install Pipeline
  • 1 instance of WE 150 Install Sprinkler
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed)
  • 1 instance of WE 80 Install Siphon
Sockeye (O. nerka) - Snake River ESU (Endangered)
  • 1 instance of WE 150 Install Sprinkler
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 80 Install Siphon
  • 1 instance of WE 149 Install Pipeline

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Manage and administer projects
B 118 EXPIRED: landowner coordination
C 118 EXPIRED: Board meetings
D 84 L13
E 84 L3ao fix
F 80 Big Timber
G 40 Side channel rearing
H 84 Side channel rearing
I 84 L44 fix
J 149 Install irrigation pipe--SVGC
K 150 Install sprinkler system--SGVC
L 185 Periodic Status Reports for BPA
M 132 Fy05 annual report