Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Complete |
---|---|---|---|---|
Funding Package - Submit draft to COTR | A: 119. Provide BPA programmatic information | 09/26/2006 | 08/04/2006 | |
Environmental Compliance Documents | C: 165. Complete all environmental compliance documentation | 06/30/2008 | 11/07/2007 | |
install pipeline | D: 149. Install pipeline from headgate to start of Phase 1 pipeline | 07/03/2007 | 03/09/2007 | |
remove and install diversion structures | E: 84. Remove existing diversion dam, reconstruct dam with roughened channel ramp | 07/03/2007 | 03/02/2007 | |
Repair pipeline to correct previous installation | F: 149. Repair pipe | 06/30/2008 | 06/30/2008 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered) |
|
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened) |
|
Trout, Bull (S. confluentus) (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 119 | Provide BPA programmatic information | |||||||
B | 185 | Periodic Status Reports for BPA | |||||||
C | 165 | Complete all environmental compliance documentation | |||||||
D | 149 | Install pipeline from headgate to start of Phase 1 pipeline | |||||||
E | 84 | Remove existing diversion dam, reconstruct dam with roughened channel ramp | |||||||
F | 149 | Repair pipe | |||||||
G | 132 | Progress Report not required |