Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 32587: 1991-078-00 EXP BURLINGTON BOTTOMS WILDLIFE MITIGATION PROJECT
Project Number:
Title:
John R. Palensky Wildlife Area
Stage:
Closed
Area:
Province Subbasin %
Lower Columbia Willamette 100.00%
Contract Number:
32587
Contract Title:
1991-078-00 EXP BURLINGTON BOTTOMS WILDLIFE MITIGATION PROJECT
Contract Continuation:
Previous: Next:
26709: 1991-078-00 EXP BURLINGTON BOTTOMS WILDLIFE MITIGATION PROJECT
  • 37526: 1991-078-00 EXP BURLINGTON BOTTOMS WLDLF MITIG
Contract Status:
History
Contract Description:
In 1991, Burlington Bottoms (BB) was the first site in Oregon to be purchased by the Bonneville Power Administration (BPA) under the Willamette and Columbia River Basins Fish and Wildlife Programs, to provide partial mitigation for the impacts associated with the construction of hydroelectric facilities.  The Oregon Department of Fish and Wildlife (ODFW) was contracted by BPA in 1993 to conduct interim management of the BB site, which included completion of a habitat assessment or habitat evaluation procedure (HEP).  In addition, a hydrology and hydraulics assessment was also conducted on the site in 1993. Results of the HEP and hydrology study were incorporated into the Environmental Assessment/ Management Plan written in 1994 (DOE/EA-0928).  Implementation of the EA/Management Plan began in 1995, and included custodial oversight and habitat restoration projects, including non-native vegetation removal.  In 2001, a second management plan was written, titled Five-Year Habitat Management Plan, 2001-2005.  This Plan addresses specific goals and objectives to be carried out over a five-year period, using various enhancement strategies to achieve the overall goal of protecting, maintaining and enhancing wildlife habitat on the site.        
          
Funds needed to implement the habitat management plan are approved by the Northwest Power Planning Council (NWPPC) through their provincial review process or other interim process.  The mechanism for proposing and implementing the BB project in the future is expected to change as the NWPPC implements a basinwide subbasin planning effort.

The purpose of this scope of work is to continue implementation of the five-year habitat management plan and related  issues.  Specific objectives and tasks include: 1) complete the installation of a water control structure; 2) habitat enhancement activities including non-native plant removal and native planting; 3) custodial management of the site; and 4) monitoring and evaluation of past enhancement activities.

The overall goal of this project is to protect, maintain, and enhance wildlife habitat and associated habitat units (HUs) for the site.  Additional goals include continuing the implementation of the five-year habitat management plan and resolving the future ownership and management of the site.  These actions are to be undertaken in a manner that meets the mitigation requirements of (BPA) for this site in the most efficient and effective way possible.

Coordination of this agreement will include the Oregon Department of Fish and Wildlife and the Bonneville Power Administration.

During the term of the project, project activities and expenditures shall be consistent with BPA's Final Environmental Assessment/Management Plan and Finding of No Significant Impact (December 1994, DOE/EA-0928).  Project activities not considered in the 1994 Environmental Assessment will comply with NEPA requirements in separate documentation.  Consultation with the USFWS and/or NMFS will occur as necessary and the appropriate NEPA compliance and concurrence verification will be obtained.
Account Type(s):
Expense
Contract Start Date:
04/01/2007
Contract End Date:
03/31/2008
Current Contract Value:
$90,049
Expenditures:
$90,049

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Complete coordination A: 119. Manage and Administer Projects 03/31/2008 03/31/2008
Complete environmental compliance requirements B: 165. Produce Environmental Compliance Documentation 01/31/2008 01/31/2008
Complete ownership proposal C: 189. Continue discussions related to the future ownership of Burlington Bottoms 03/31/2008 03/31/2008
Complete coordination D: 189. Coordinate with surrounding landowners 03/31/2008 03/31/2008
Complete water control structure installation E: 181. Install Water Control Structure 11/15/2007 11/15/2007
Complete wetland enhancement F: 181. Enhance Wetland Habitat 11/15/2007 11/15/2007
Complete plantings G: 47. Plant native vegetation 02/28/2008 02/28/2008
Complete vegetation removal H: 53. Remove invasive, non-native vegetation 02/15/2008 01/15/2008
Complete operation and maintenance activities I: 186. Operate & maintain water control structure; maintain roads/trails needed for management access 03/31/2008 03/31/2008
Complete debris removal J: 27. Remove debris 03/31/2008 03/31/2008
Complete site monitoring K: 26. Monitor authorized and unauthorized uses of the site 03/31/2008 03/31/2008
Complete data collection L: 157. Data Collection 03/31/2008 03/15/2008
Complete data analysis M: 162. Analyze data 02/29/2008 03/15/2008
Complete FY06 annual report N: 132. Complete 2006 Annual Report 05/31/2007 02/15/2008
Submit draft of FY07 annual report O: 132. Submit draft of 2007 Annual Report 03/31/2008 03/31/2008

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Wildlife
  • 1 instance of WE 26 Investigate Trespass
  • 1 instance of WE 27 Remove Debris
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 53 Remove Vegetation
  • 2 instances of WE 181 Create, Restore, and/or Enhance Wetland
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Manage and Administer Projects 02/09/2007
B 165 Produce Environmental Compliance Documentation 02/09/2007
C 189 Continue discussions related to the future ownership of Burlington Bottoms 02/09/2007
D 189 Coordinate with surrounding landowners 02/09/2007
E 181 Install Water Control Structure 02/09/2007
F 181 Enhance Wetland Habitat 02/09/2007
G 47 Plant native vegetation 02/09/2007
H 53 Remove invasive, non-native vegetation 02/09/2007
I 186 Operate & maintain water control structure; maintain roads/trails needed for management access 02/09/2007
J 27 Remove debris 02/09/2007
K 26 Monitor authorized and unauthorized uses of the site 02/09/2007
L 157 Data Collection 02/09/2007
M 162 Analyze data 02/09/2007
N 132 Complete 2006 Annual Report 02/09/2007
O 132 Submit draft of 2007 Annual Report 02/09/2007
P 185 Periodic Status Reports for BPA 02/09/2007