Contract 33170: 2002 072 00 EXP USFS RED RIVER WATERSHED RESTORATION
Project Number:
Title:
Red River/Newsome Creek Watershed Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
33170
Contract Title:
2002 072 00 EXP USFS RED RIVER WATERSHED RESTORATION
Contract Continuation:
Previous: Next:
n/a
  • 35897: 2002-072-00 EXP USFS RED RIVER WATERSHED RESTORATION
Contract Status:
Closed
Contract Description:
Project/Contract History:

This project began in 2002 and became part of the Nez Perce Tribe Fisheries Watershed Department’s habitat restoration program.  In 2002, the Red River Ecosystem Analysis at the Watershed Scale (EAWS) was completed.  While this was mainly a Forest Service effort, the NPT was involved in the transportation planning and review of the document.  NPT field personnel also surveyed approximately 100 miles of roads and 264 high priority culverts/stream crossings.  In 2003, the NEPA process was initiated on the Upper Red River Watershed Restoration Project which consists of road decommissioning, road improvements, one major culvert replacement, and campground improvements.  NEPA and ESA consultation were completed in 2004, as well as the engineering surveys for the road decommissioning and improvements.  In 2005, the Bridge Creek Campground Improvements were implemented, as well as awarding and initiating the 12 miles of road decommissioning and 9 miles of road improvements.  The contract for the final design and replacement of culvert 1709 was also awarded.

This project has been, and is still currently a part of the Nez Perce National Forest - Nez Perce Tribe Watershed Restoration Partnership.  Since the project’s inception we have shared project planning, costs, and implementation responsibilities.  There are two contracts under this project.  The primary contract is with the Nez Perce Tribe.  This contract with the Nez Perce National Forest includes only the funding for specific subcontracts.

Summary of FY 07 Contract Implementation:

FY 07 contract implementation will include 5 culvert replacement surveys & designs, 12 miles of road decommissioning and the removal of 1 log culvert/makeshift bridge, and large woody debris placement in the mainstem of Red River.  Erosion control and revegetation (seeding with annual rye mix), will also be conducted on the decommissioned roads.  The Nez Perce Tribe, under their own separate contract, will assist the Nez Perce National Forest in reviewing bids, contractor selection, field supervision and the final inspection of the road decommissioning subcontract.  NPT also conducts the implementation/project effectiveness monitoring and evaluation for all culvert replacements and road decommissioning and improvement.
Account Type(s):
Expense
Contract Start Date:
03/01/2007
Contract End Date:
06/30/2008
Current Contract Value:
$135,391
Expenditures:
$135,391

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Stephanie Bransford Nez Perce Tribe Yes Technical Contact stephanieb@nezperce.org (208) 983-0675
Mickey Carter Bonneville Power Administration No Interested Party macarter@bpa.gov (503) 230-5885
Lois Geary US Forest Service (USFS) No Administrative Contact lgeary@fs.fed.us (208) 983-7008
Melany Glossa US Forest Service (USFS) No Supervisor mglossa@fs.fed.us (541) 367-3145
Amanda Hendrix Nez Perce Tribe No Technical Contact amandah@nezperce.org (208) 621-3542
Bruce Hollen Bonneville Power Administration No Env. Compliance Lead bahollen@bpa.gov (503) 230-5756
David Kaplowe Bonneville Power Administration Yes COR djkaplowe@bpa.gov (503) 230-5365
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
Michelle Roberts US Forest Service (USFS) Yes Technical Contact mmroberts@fs.fed.us (208) 983-4091
Scott Russell US Forest Service (USFS) Yes Contract Manager sarussell@fs.fed.us (208) 983-4092


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Complete
Environmental compliance documentation submitted to BPA A: 165. Provide Environmental Compliance Documentation to BPA 06/01/2007 06/01/2007
Design Culvert Replacements B: 175. Design up to five culvert replacements 05/30/2008 05/30/2008
Decommission 12 miles of road in Red River Watershed C: 33. Red Pines Road Decommissioning Phase III 10/31/2007 10/31/2007
12 miles of erosion control on decommissioned roads. D: 55. Erosion Control on Decommissioned Roads 10/31/2007 10/31/2007
Seed & Fertilize Decommissioned Roads E: 47. Seed Decommissioned Roads 10/31/2007 10/31/2007
FY 07 SOW package and accrual estimate F: 119. Management, Coordination and Communication 11/30/2007 11/23/2007

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 33 Decommission Road/Relocate Road
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 55 Erosion and Sedimentation Control
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 33 Decommission Road/Relocate Road
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 55 Erosion and Sedimentation Control
  • 1 instance of WE 175 Produce Design

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Provide Environmental Compliance Documentation to BPA 02/09/2007
B 175 Design up to five culvert replacements 02/09/2007
C 33 Red Pines Road Decommissioning Phase III 03/30/2007
D 55 Erosion Control on Decommissioned Roads 03/30/2007
E 47 Seed Decommissioned Roads 03/30/2007
F 119 Management, Coordination and Communication 02/09/2007
G 185 Periodic Status Reports for BPA 02/09/2007